I have spoken with the landscape contractor for the Oakgreen Senior Living Phase 3 building(30 unit senior memory care)on north
end of the development,and he said that the landscaping(some planting,grading and turf behind the building)will be completed
within approximately the next 3 weeks. They are waiting for the excavation contractor to come back to do some catch basins and
grading. Once that has been accomplished, Lisa can inspect the site and sign off on the work if it has been completed.
Kathy Widin
Forestry Consultant
City of Oak Park Heights
1
Julie Hultman
From: Julie Hultman
Sent: Thursday, August 13, 2015 8:58 AM
To: Tim Nolde; Craig Berggeren (anchorlandcare @msn.com)
Cc: 'K.D.Widin'; Lisa Danielson
Subject: FW: Oakgreen Senior Living Phase III - Landscape Inspection
Hi Tim,
Please see Arborist Widin's landscape inspection report below. As this is one of the items conditioned for the final CO for the
building, please address the items remaining needed and contact Kathy with any questions regarding this report. Once the
remaining work has been completed and is ready for a follow up inspection,please let us know.
Haveagreatday! 8/1Ll!IS
Julie
-----Original Message L t P<
From: K.D.Widin [mailto:kdwidin@comcast.net]
Sent:Wednesday,August 12, 2015 7:54 PM C 3o �
Subject: Oakgreen Senior Living Phase Ill-Landscape Inspection
Q.or•Q
OPH Staff-
I inspected the installed landscaping at the Oakgreen Senior Living Project Phase Ill on Mon.8/10/15. The landscaping indicated to
be planted on the approved landscape plan dated 12/10/12 is present except for the omission of some daylilies in front of the
building(no room)and the moving of utility boxes and landscape screening from the north side of the building to the west side.
Several serviceberry and some ninebark shrubs indicated on the plan in the middle of the building on the north side have not been
planted. Landscape grading and planting on the north side of the building has not yet been completed. Please contact me if you
have any questions regarding this inspection or report.
Kathy Widin
Forestry Consultant
City of Oak Park Heights
1
Julie Hultman
��..�..
From: K.D.Widin <kdwidin @comcast.net>
Sent: Wednesday, August 12, 2015 7:54 PM
To: Eric Johnson; Mark Vierling (E-mail);Andrew Kegley; Betty Caruso;Julie Hultman; Scott
Richards; Mlejnek, Cristina;Jennifer Pinski; Lisa Danielson
Subject: Oakgreen Senior Living Phase III - Landscape Inspection
OPH Staff-
I inspected the installed landscaping at the Oakgreen Senior Living Project Phase Ill on Mon.8/10/15. The landscaping indicated to
be planted on the approved landscape plan dated 12/10/12 is present except for the omission of some daylilies in front of the
building no room) and the moving of utility boxes and landscape screening from the north side of the building to the west side.
Several serviceberry and some ninebark shrubs indicated on the plan in the middle of the building on the north side have not been
planted. Landscape grading and planting on the north side of the building has not yet been completed. Please contact me if you
have any questions regarding this inspection or report.