1 NTERTE The Scienee You Build On. Letter of Transmittal 39
Client: Stillwater Area Public Schools Project No: B1602671
Project: Stillwater High School Renovations and Additions
Date: December 06,2016 Braun Intertec Corporation
11001 Hampshire Ave. S.
Bloomington, MN 55438
To: Kristen Hoheisel Phone: 651-351-3840
Stillwater Area Public Schools Email: hoheiselk@stillwaterschools.org
Independent School District#834
1875 Greeley St S
Stillwater, MN 55082
Re: Stillwater BLVD N, Oak Park Heights, MN
IDocuments Sent Comments
Fireproofing Fireproofing#5
ICopy List
Jared Olson,BKBM Engineers Jack Bronczyk, Kraus-Anderson Construction Company
Daniel Martin, Braun Intertec Corporation Jeff Moore, Kraus-Anderson Construction Company
Steven Martin, Braun Intertec Corporation Kristy Casper,Kraus-Anderson Construction Company
Aaron Fields, BWBR Architects, Inc. Randy LaFaive, Market&Johnson
Michael Smunty, BWBR Architects, Inc.
Julie Hultman,City of Oak Park Heights
Dustin Phillips, Kraus-Anderson Construction Company
Contact Information:
Sent By: Nicole Sotolova
Email: nsotolova@braunintertec.com
Phone:
Rev:05/05/2014 Providing engineering and environmental solutions since 1957
Rev.1 Issue:
BRAUN, 6.32.4 R 6/23/15
INTERTEC
Special Inspection Daily Report
City of: Oak Park Heights Page 1 of 1
Report No.: Fireproofing#5 Observation Date: 12/1/2016
Project Name: Stillwater High School&Pony Activity Center Project No.: B1602671
Project Address: Stillwater Blvd. N Braun Intertec PM: D. Martin
Client: ISD#834 Client Project No.:
Weather: Sunny Temperature: 35 •F
que cy
Freuen Inspection Coverage (Notes)
Periodic Sprayed'fire-resistant materials
Did the architect or engineer authorize changes to approved plans? (It yes,list details below)
Description and location of work performed:
1)Performed visual and Thickness observations of Cafco 300AC spray applied fireproofing on Beams,Columns,and Angles.
Zone 3 2nd level grids E-F,5.5-11.All thickness meet or exceed the thickness requirments supplied by Custom Drywall. No
Discrepancies Noted,
Thickness requirments
Beams 1"
Columns 1"
Angles 1"
1 Density Sample taken
2)Set up Adhesion/Cohesion test per ASTM E763 on Cafco 300AC spray applied fireproofing on Beams,Columns,and
Angles.3 test samples were set up on both 2nd and Roof levels in Zone 10 grids EE-KK,10-16 and H'-L',1-9 and Zone 12
grids EE-KK,25-30 and A*-D*,3*-12*
List tests performed:
Visual
•Are there any discrepancies noted from this day's observations? No
•Are there any outstanding discrepancies on this project? No
-If yes,see attached Summary Sheet.
• Report Discussed with and Given to Contractor? Yes
Report Emailed to:
Jeff Moore jeff.moore@krausanderson.com 612-790-6711
Jack Bronczyk jack.bronczyk@krausanderson.com 612-812-3972
To the best of our knowledge,work inspected was done in accordance with the approved plans,specifications and applicable
workmanship provisions of the current IBC,except as noted above.
ix --- Baumann, Troy
Signed: I.D.No.: 5067860 S1&52