Loading...
HomeMy WebLinkAbout1998-07-10 NAC Planning ReportN PLANNING REPORT TO: Tom Melena FROM: Scott Richards DATE: 10 July 1998 RE: FILE NO: BACKGROUND NORTHWEST ASSOC IA1 ED CONSULTANTS '•■.strogrovogprao COMMUNITY PLANNING - DESIGN - MARKET RESEARCH Oak Park Heights - Valley Senior Services Alliance: PUD Concept Plan Review 798.02 - 98.02 ENCLOSURE 3 Application. Valley Senior Services Alliance (VSSA) has made application for rezoning to Planned Unit Development and Concept Plan approval of the Haase property south of 58th Street. The property is now zoned 0, Open Space Conservation. The property to the south of 58th Street is part of the PUD for senior housing and care facilities, the remaining property to the north of 58th Street is proposed to be rezoned to CBD, Central Business District and be developed as part of the Citys Town Center concept. VSSA is a non--profit organization funded by Presbyterian Homes Housing and Assisted Living, Inc., Lakeview Hospital, and Croixdale Residence and Apartments. The alliance is dedicated to serving older adults in Washington County and the St. Croix Valley. Market. The campus for older adults south of 58th Street would include duplex and cottage units, independent living apartments and cooperative, assisting living facilities, dementia/Alzheimer living facilities, and a central area that will provide health services, food service, and laundry. The facilities would be situated around a City park with extensive trail systems providing connections internal to the site and to neighborhoods and commercial areas that surround the site. The applicants have completed a comprehensive market study and have concluded that an opportunity exists in that there are few older adult services currently in place in the Oak Park Heights/Stillwater area. The demand for services and housing facilities, as provided with the planned VSSA development, are expected to increase by more than 30 percent in the St. Croix Valley over the next decade. 1 5775 WAYZATA BOULEVARD, SUITE 555 ST. LOUIS PARK, MINNESOTA 554 1 6 • r- • . PHONE 6 1 2 5 9 5 - 9 6 3 6 FAX 6 1 2 5 9 5 - 9 8 3 7 E-MAIL N AC @ WINTERNET.COM Staging. The development is planned to be constructed in two phases. Phase 1 is expected to begin the Fall of 1998 as soon as financing, plans and approvals are in place. Phase 1 will consist of 90 units of independent living apartments, 36 Alzheimer /dementia units, 126 assisted living units, 42 duplex units, and central facilities including dietary/ kitchen, laundry and other central offices and amenities. After market absorption of Phase 1, Phase 11 is planned to consist of 90 independent living cooperative units, 68 skilled nursing units, and 108 cottages, quad homes and duplex units. Adult day care and other central services and amenities would also be added at this time. Layout. The development has been designed to complement the surrounding current and planned property uses. As requested by neighbors in the Autumn Ridge and River Hills neighborhoods, streets that had been planned to continue into this property will not be constructed. Significant setbacks have been provided from existing single family homes. Trails throughout the project will wrap around lakes and ponds on the site and link existing trails to the City Park that will be developed as part of the project. The project has also been phased to provide a reasonable transition of land uses and densities. Low density cottages and duplexes are adjacent to existing single family and the multi story, multi family housing and health care facilities are in the center of the development and towards 58th Street, adjacent to the areas planned for future commercial uses. Attached for reference: Exhibit A -Site Plan Exhibit B - Conceptual Grading Plan Exhibit C Conceptual Utility Plan Exhibit D Site Section - Assisted Living Facility to River Hills Neighborhood Exhibit E -Floor Plans (Three Sheets) Exhibit F - Park Dedication Memo Dated 24 June 1998 ISSUES ANALYSIS Comprehensive Plan. The subject site is currently designated for low density residential by the City's 1991 Annexation Area Comprehensive Plan Amendment. In that the City is currently in the process of updating the Comprehensive Plan, the new Land Use Map and text will be revised to reflect a combination of high density /mid density and low density residential use as well as the City park and if the City is agreeable to the proposed uses as reflected in this concept plan. The Planning Commission and City Council should comment at this time regarding the overall change in land uses for the area in question. Zoning. The entire site is currently zoned 0, Open Space Conservation. The area to the south of 58th Street will be zoned PUD with the R--B, Residential Business - Institutional District as the underlying basis for zoning standards. Due to the variety in types of uses Page 2 and densities, the PUD zoning and approvals will allow for a comprehensive approach to evaluating and addressing the applicant's proposal. Also, it allows for a reasonable method for review and approval of a phased development. Adjacent Uses. Uses adjacent to the subject site are listed below. The proposed uses of the site are generally compatible with others in the area. However, attention will need to be given to protecting the single family neighborhoods to the east and west from any potential impacts. 0 North of Site: Present zoning - partially 0, Open Space and partially B -2, General Business District. Present use - some vacant, a Wal -Mart, auto salvage and retail near Highway 36. ® South of Site: Not in City w Baytown Township. Present use -- large lot single family. 0 0 East of Site: Present zoning - partially 0, Open Space and partially R -1, Single Family Residential. Present use - single family neighborhoods (River Hills) /some vacant land. West of Site: Present zoning - partially R -1, partially 0, Open Space. Present use single family neighborhood (Autumn Ridge) and the Environmental Learning Center for High School. Subdivision. As part of the General Plan of Development approval process, a preliminary plat will be presented for review. Skip Sorenson, the project architect, has indicated that the main campus, which includes the Town Center, assisted housing, independent living, etc. would be platted as one lot. The two park facilities would be platted as two separate lots, and the 90 unit senior cooperative building as one lot. The clusters of twinhomes in the first phase would be platted as two separate lots and the second phase of housing in the lower acreage would be platted initially as an outlot. The roadways would be platted to City standards for right-of-way and would be dedicated to the City. General Design Review. Upon review of the concept plan, our office has the following general comments on the layout of the project: 1. It appears as though the main entrance of the facility faces south, away from 58th Street. The employee parking and what appears to be the service entrance would be accessed off of 58th. Wouldn't the complex be more accessible and less confusing to visitors if its orientation and front entrance was to 58th? It seems as though the front facade /entrance should be moved to welcome people to the complex off the main access road. Page 3 2. The plans should be reviewed by the Fire Chief, Police Chief and others concerned with emergency vehicle access to determine if proper access is being allowed for the complex. 3. Use of combined driveways, as indicated for the single family dwellings in Phase 11 should be encouraged for all units. 4. Related to the twinhome development in the northwest corner of Phase 1, the two twinhomes in the center area created by the roadway are in an awkward configuration. Possibly the southerly facing twinhome could be oriented to the west, creating more usable open space. 5 The orientation of buildings, especially in Phase 11, should be altered slightly so that homes do not directly line up with street ends. 6 The three cul -de -sacs do not meet City standards for maximum length. The dead - end streets should be redesigned to reconnect with the main drive or be considerably shortened. 7. Medians are not provided for the primary entrance to the main campus. 8 The lone house in Phase 11, adjacent to the southeast pond, seems out of context. It should be combined with other existing homes or additional homes could be added. 9 The driveway for the twinhomes in the northeast corner of Phase in should line up with the entrance to the senior cooperative building. 10. The City trail along 58th Street should be identified on the plans to show interconnections. 11. More trail crosswalks should be identified on the plans in anticipation of pedestrian /bicycle movements through the site. 12. The trail system should be extended in Phase 11 so that it follows the main roadway system throughout the development. Park Dedication. Section 402.08 of the Subdivision Ordinance requires a land dedication for residential development for the construction of City parks. The City has planned a park in this area since the property was first annexed. When the surrounding property was planned for single family residential, the Park Commission had developed a plan for a 28 acre park with two park shelters, large child play area, a baseball /softball field, soccer field and a trail system around the existing wetland complex. The VSSA project is proposing the dedication of park land to the City and the construction of an extensive trail system. Page 4 Based upon the current development program for both Phase 1 and 11 of the project, the park dedication requirements were calculated by our office in a memo dated 24 June 1998. The memo is attached as Exhibit F. The land dedication for that area developed residentially south of 58th Street would be 1 0.95 acres. The area north of 58th Street, which is to be developed with commercial land uses, would require a cash dedication equaling $1,750 per acre. Most of the land proposed to be dedicated is encumbered with the existing wetland complexes that are likely to be expanded as part of the project. Additionally, much of the land to be dedicated is near 58th Street and is not usable for park purposes. A more accurate calculation of the area to be covered by wetlands will be needed to determine a reasonable land dedication. Staff makes these initial recommendations in terms of park dedication for review and comment by the Park Commission, Planning Commission and City Council. 1. A reasonable, usable land area, free of wetland /storm water ponding encumbrances be dedicated to the City for park land purposes. VSSA is to grade, seedlsod and landscape all areas to be dedicated as City Park to the City's satisfaction before it is dedicated to the City. 3. VSSA is to construct all of the paths shown on the approved plan (bulit to City specifications as indicated in the Comprehensive Bicycle and Pedestrian Trail System Plan). The trails within the dedicated park land will be maintained by the City. Trail maintenance will be paid for by a "special service district" funded in part by VSSA. All trails outside of the park lands shall be the maintenance responsibility of VSSA. 4 VSSA shall be responsible for construction of an enclosed park shelter with toilet facilities; design of such shall be agreed to by the City and VSSA. 5. VSSA shall construct the parking lot adjacent to the park shelter. 6. VSSA shall construct a child's play area to the specifications of the Park Commission and City Council. The specifics of each of these recommendations will need to be discussed further as part of the General Plan of Development review and approval. Assessments. The applicant will be required to pay all assessments for the construction of 58th Street as well as area changes (sewer, water, and storm water fees) at the time of final plat approval. The amount of these fees will be calculated by the City Engineer. Page 5 Environmental Impact. A review of the "Guide to the Rules" of the Minnesota Environmental Review Program reveals that the proposed development will not create the need for an Environmental Assessment Worksheet (EAW). Lot Area and Width. Section 401.06.8.14 of the Zoning Ordinance states that there is no maximum lot area or lot width for properties developed as PUD. Generally, there is sufficient area within the 100+ acre site to accommodate the propose development. Setbacks. Within a PUD Zoning District, the base district setback requirements are applied only to the perimeter of the property. Separation of the structures on the interior of the development are required to be a minimum of 20 feet or one -half the sum of the two building heights. It appears from the preliminary site plan that all of the buildings will be constructed well beyond the perimeter setback requirements of the Zoning ordinance, More information will need to be provided as part of the General Plan of Development to determine the interior setback requirements. Site Access. The site w i l l be accessed off of three locations on 68th Street. The City Engineer should comment on the location of these curb cuts as to any existing or potential conflicts with proposed intersections. The City had planned for the eventual extension of roadways in this area from both the Autumn Ridge and River Hills neighborhoods. With the change in land use and residential densities proposed for the VSSA development, the streets will not be continued and made a part of the street network for this area. The project site plan has indicated potential outlots that could be retained in Phase 11 to allow for an extension of the roadways into the high school area or into the undeveloped area of Baytown Township that is south and west of the VSSA site. The Planning Commission and City council should discuss these outlot locations. Traffic Impact. The applicant has indicated that it will provide a traffic study that will estimate the volumes of traffic to be generated by this development and its impact on the local street network. The traffic study will be subject to review and approval of the City Engineer. Off-Street Parking. The plans have not been developed to a level of detail in order to analyze the off-street parking demands. Much of the main campus will utilize underground parking to meet the ordinance requirements. Of critical importance throughout the development will be the provision of adequate visitor parking stalls within all aspects of the VSSA project. Due to the fact that many of the residents, especially in the main campus, will not own cars, the demand for parking will need to be reviewed accordingly. Details on parking stall design will be provided as part of the General Plan of Development review. Architectural Appearance. No building elevations have been submitted by the applicant. Detailed building elevation plans will be required as part of the General Plan PP g P of Development review. The City has requested that the structures in this general area be Page 6 built of similar quality construction materials that were used for the Stillwater Area High School. Building Height. No building elevation plans have been received to date. It should be noted that no structure in residential zones may exceed 35 feet in height unless by conditional use permit according to the Zoning Ordinance. Lighting. The applicant has not submitted a lighting plan. A photometric lighting plan with specifications for all major lighting fixtures must be submitted as part of the General Plan of Development application and shall be subject to review and approval of the City Engineer. Ali lighting shall be hooded and so directed that the light source shall not be visible fro the public right -of -way or from adjacent properties in compliance with Section 401.15.B.7 of the Zoning Ordinance. Landscaping. Landscaping plans have not been submitted to date but will be required as part of the General Plan of Development. The City will require an evaluation of the existing trees on the site, what will remain, what will be moved, and what will need to be permanently removed. Preservation of the stands of mature trees, especially those on the west end near Autumn Ridge and the existing Oak grove, south and east of the large wetland complex, will be a high priority of the City. Screening and berming of existing neighborhoods, especially the River Hills area and the Baytown Township neighborhoods, will also be a priority in the landscape plans. For General Plan of Development, the following will be required: 1. Analysis of existing tree inventory including identification of all trees over eight inches in diameter (as measured 54 inches above ground). 2. An overall landscape plan indicating which existing trees will remain and what will be removed. Details shall be provided including identification of all species, numbers used, and size at time of planting. 3. Details shall be provided for landscaping around all buildings and in areas where screening shall be required. Signage. The plans to be submitted for the General Plan of Development will need to provide signage detail. Alt signage and informational or visual communication devices shall be in compliance with Section 401.15.G of the Zoning Ordinance. Grading and Drainage. Grading and drainage information has been submitted. The Cit y Engineer ineer has asked for additional information to be submitted at this time for a general review of the drainage issues. A more complete report will be forthcoming from the City Engineer. The drainage plan will be required to comply with the City Storm Water Plan, subject to review and approval of the City Engineer and the Valley Branch Watershed Page 7 District. All issues related to the general grading and drainage plan will need to be resolved as part of the General Plan of Development submittal. Utilities. A utility plan has been submitted. Said utility plan shall be subject to the provisions of Section 401.06.B.10 of the Zoning Ordinance and review and approval of the City Engineer. Development Contract The applicants will be required to enter into a development contract with the City should approval of the Concept Plan and General Plan of Development be granted. The development contact will specify the conditions of approval and address the issues related to phasing the development. RECOMMENDATION AND CONCLUSION Our office, having completed a through review of the submitted materials, finds that the applicants' requested rezoning and Concept Plan proposal is generally acceptable and appropriate for the subject site, as well as consistent with the City's Comprehensive Pan. Issues which remain to be addressed as the process evolves from a Concept Plan to General Plan of Development stage include detailed project plans such as site lighting, landscaping, signage, architectural elements, etc. The rezoning to Planned Unit Development will occur in conjunction with the General Plan of Development when all of the issues in this report have been addressed. The decision regarding the zoning designation of land within the City is a policy matter to be decided by City officials. Based upon unique elements of the applicants' proposal and the City's Comprehensive Plan, we believe that the requested rezoning is appropriate. Should the City Council make a similar finding, our office recommends approval of the following motion approving the submitted preliminary plat and Concept Plan. The Cit y Council of the City of Oak Park Heights hereby approves the PUD Concept Plan for the VSSA Senior Life Community subject to the following conditions: 1. The Planning Commission and City Council should provide direction as to whether this p roposal is an appropriate land use for the site in question and whether the new Comprehensive Plan should reflect that land use. The area in question, to the south of 58th Street, is to be rezoned from 0, Open Space Conservation to PUD, Planned Unit Development. 3 The applicants shall submit a preliminary plat for approval as part of the General Plan of Development process. Page 8 4. The Planning Commission and City Council provide direction as to the staff comments on the general design of the VSSA project as found on pages 3/4 of this planning report. 5. The Planning Commission, Park Commission, and City Council provide direction as to the staff comments related to park dedication as found on page 5 of this planning report. 6. The applicants shall be required to pay all assessments for the construction of 58th Street as well as area charges (sewer, water and storm water fees) at the time of final plat approval. 7 The applicants shall provide accurate plans as part of the General Plan of Development approval process to determine all interior and perimeter setbacks. 8. The City Engineer shall approve all curb cuts onto 58th Street related to this development. 9. The Planning Commission and City Council shall comment on the outlot locations planned for eventual connections between Phase 11 and roadways outside of the VSSA development. 10. A traffic study will need to be submitted by the applicant as part of General Plan of Development review. The traffic study shall be subject to review and approval of the City Engineer. 11. The applicants shall submit detailed plans as part of the General Plan of Development review related to off - street parking locations, design and number of stalls. 12. Detailed building elevation plans and material samples for all proposed buildings shall be required as part of General Plan of Development review. 13. The applicants shall submit a detailed lighting plan as part of General Plan of Development review process. 14. The Planning Commission and City Council shall provide direction as to the staff comments related to landscaping as found on page 7 of this planning report. 15. Signage details will need to be provided as part of General Plan of Development review. Page 9 16. A detailed grading and drainage plan will need to be submitted that complies with the City's Storm Water Plan, subject to review and approval of the City Engineer and the Valley Branch Watershed District. All issues related to the grading and drainage plan will need to be resolved as part of the General Plan of Development plan submittal. 17. The submitted utility plan is subject to review and approval of the City Engineer. 18. The applicants shall be required to enter into a development contract with the City specifying the conditions of approval and address the issues related to phasing the development. Page 10 -r SITE FLAN • = 1501-0" • • • 1 1 + 4 FG P ! "G 1~ 7 . 'a l. _ t •C. •f" -f '1, Ys 'i, •' • r• ,r .-•‘• -cl") k EXHIBIT B w U z �• w 5 G Cr d 2N D, 0 0 IL U J V) 0 J 2 U J wd CO > ti EXHIBIT C CC LIJ rki C2 :. 34,7 keZW.2.E r2•X X 724 2 E3ORM/DEN UNIT i.w4 so, FT. 5EN1OR HOUSING LIVIN6 RQ0,1 , 41 , 2x15.1 LY4 POR6H 0..VORC.C. 1145 X 10 1, f2c 1,1x 7.5 OARAGt" 73, X 7 -,,azdzoseg 2 BDRM UNIT - SENJOR HOUSING ,sqa so. FT 3/145•=r-0- EXHIBIT E e 1 .7 • PATIO 10-0 x 1-0 2 EVRI\l/DEN UNIT - SENIOR HOUSING 1/4"=1,0* 1504 SQ. FT. X a. MSTR BEDp001 12-0 X 11.0 pm7F0,COM #5 100 x to-4 BEOROONI it:z 10-1 X 12-0 - - M517 i 5hZi71 PATIO GARA6E P1-3 X 21.1 3 BEDROOM UNIT - SENIOR HOUSING 1/4".1.-0" 1442 5,...G2, FT. KITCHEN 10• X 11-6 0 0 INC MEMORANDUM TO: Tom Melena FROM: Scott Richards DATE: 24 June 1998 RE: FILE NO: DEVELOPMENT PROGRAM Phase 1 Phase 11 NORTHWEST ASSOCIATED CONSULTANTS COMMUNITY PLANNING - DESIGN - MARKET RESEARCH Oak Park Heights Valley Senior Services Alliance: Park Dedication 798.04 - 98.09 For your information, 1 have recalculated the park dedication requirements based upon the revised number of units/beds for the proposed Oak Park Heights VSSA campus. Barbara Barry provided a revised Development Program for the project with the new unit numbers as follows: Independent Living Apartments 90 units Alzheimer Assisted Living 36 units Assisted Living 126 units Duplexes 42 units Central Dietary/Kitchen and Laundry Office Building 75,000 sq.ft. Independent Living Cooperative 90 units Skilled Nursing 68 units Duplexes 60 units Quads 16 units Single Unit Cottages 32 units 5775 WAYZATA BOULEVARD, SUITE 555 ST. LOUIS PARK, MINNESOTA 5 5 4 1 6 ••••••.• ••■•--- • .••• • • • • • • -• ••• •■• •.• ■■••••••..... 7 - • •••,,-.•••••• •- ••••■••••••••••-•••- r•-,•••-•••■••• • •■• • ••••••.• •■••■ .■•••••■ ■•••••••• •• • • .. •••••., ••,• 4•■•••••■•••,‘• • ••• • •• • •■ ••• • ■•• • ••••• ,,•■•••••••••••••••■••,.•••••• •••••,.......•••,•••••• " • • - • PHONE 6 1 2 - 5 9 5 9 6 3 6 FAX 6 1 2 - 5 9 5 - 9 8 3 7 E- MAIL N AC @ WI NTERNET .COM Based program on the listed above, our office has calculated the following park and P dedication: USSA - OAK PARK HEIGHTS SENIOR CAMPUS /PARK DEDICATION Units Beds Phase 1 Independent Living Apartments 90 117 Assisted Living 1 Alzheimer 162 178 Duplexes Quads Single Unit Cottages TOTAL 60 16 32 560 120 32 64 821 Park Dedication 1.56 acres 2.37 acres 1.12 acres 2.11 acres 0.91 acres Duplexes Phase 11 Independent Living Cooperative Skilled Nursing 42 84 90 68 158 68 1.60 acres 0.43 acres 0.85 acres 10.95 acres The land dedication requirement under the current VSSA Development Program is 10.95 acres. This does not include the acreage occupied by the central facility /office building or the acreage that would be purchased by VSSA, but included in the commercial development north of 58th Street. The Subdivision Regulations indicate that commercial /industrial p ark land dedication would be in the form of a cash dedication equating 51,750.00 per acre. The Park Board will meet on 30 June 1998 and should discuss the park dedication /planning issues for the VSSA development. pc: Mark Vierling Skip Sorensen Barbara Barry 2