December 18, 2017
Mr. Eric Johnson,Administrator
City of Oak Park Heights
14168 Oak Park Blvd.N., P.O. Box 2007
Oak Park Heights, MN 55082-2007
Reference: Oak Park Senior Living Phase 5 — Plan and Drainage Design Review,
4th Submittal
Dear Eric,
We have reviewed the plans and drainage calculations submitted regarding the proposed Oak
Park Senior Living Phase 5 development re-submitted on 11/14/2017. All comments relative to
our letter of 9/14/2017 have been addressed and there are no additional comments or
recommendations. The general comments are included in this letter for continuing reference.
General Comments
1. The City reserves the right to inspect the construction of the project. The City or its
designee shall be present for water and sanitary sewer service connections to the City's
systems.
2. The Owner will need to comply with all requirements of the NPDES Construction
Stormwater Permit and the Middle St. Croix Watershed Management Organization.
The City reserves the right to require additional erosion control measures as
determined/necessary during the construction of the project.
3. Lighting and landscaping to be reviewed by others.
4. The Owner shall be responsible for obtaining all required permits.
If you have any questions or require further information,please do not hesitate to contact me.
Regards,
STANTEC CONSULTING SERVICES INC.
33/1 2711avvt.,-....----
Lee M. Mann, P.E.
City Engineer
Phone: 651-604-4850
lee.mann@stantec.com
`;r.sigr with community in mind
Mr. Eric Johnson
Page 2 of 2
Reference: Oak Park Senior Living Phase 5 -Plan and Drainage Design Review, 2nd
Submittal
cc: Andy Kegley, Public Works Director
Julie Hultman, Building Official
Scott Richards, City Planner
Mark Vierling, City Attorney
Lisa Danielson, City Arborist
Design with community in mind
Julie Hultman
From: Eric Johnson
Sent: Thursday, December 21, 2017 10:14 AM
To: Tim Nolde
Cc: Tim Freeman
Subject: FW: Oak Park Senior Living Phase 5
Attachments: Johnson_mann_2017-12-18_OakParkSrLivingPhase5_review.pdf
FYI
From: Mann, Lee [mailto:Lee.Mann@stantec.comj
Sent: Monday, December 18, 2017 3:27 PM
To: Eric Johnson <eajohnson@cityofoakparkheights.com>
Cc:Andrew Kegley<akegley@cityofoakparkheights.com>; Scott Richards (Scott@PlanningCo.com)
<Scott@PlanningCo.com>;Julie Hultman <jhultman@cityofoakparkheights.com>; Lisa Danielson
<LDanielson@cityofoakparkheights.com>; Mark Vierling (MVierling@eckberglammers.com)
<MVierling@eckberglammers.com>
Subject: Oak Park Senior Living Phase 5
Eric,
Attached is our review of the latest submittal dated 11-14-2017 for the referenced project. Our previous
comments have all been addressed and we have no further comments or recommendations.
Let me know if you have any questions.
Lee M. Mann, PE, MN, WI, C.A,
Principal
Stantec
2335 Highway 36 West, St. Paul MN 55113-3819
Phone: (651) 604-4850
Cell: (651) 775-5956
Lee.Mann@stantec.com
5 Stantec
The content of this email is the confidential property of Stantec and should not be copied,modified,retransmitted,or used for any purpose except with
Stantec's written authorization.If you are not the intended recipient,please delete all copies and notify us immediately.
-4'Please consider the environment before printing this email.
1