HomeMy WebLinkAbout2006-07-21 BRAA Project UpdateJulie Hultman
From: Long, Chris VV[clonS@boneotroo.00n]
Sent: Friday, July Z1.2OOG8:28AM
To: Eric A. Johnson; Tom Ozzello; Judy Hoist; Julie Hultman; Jim Butler; Ehokson, Karen S; Pastier,
Dennis M
Co: Hanson, Davd D; Kelley, Brian
Subject: OPH Project Status Updates
Novak Avenue North/Norwich Avenue North:
• The sanitary sewer and water main are complete on Novak and Norwich.
• The storm sewer is currently being installed and should be finished early next week.
• Both streets are expected to be ready for aggregate backfill late next week.
Page 1 of 1
Project Issues:
• Electrical concrete coriduit in conflict with SS-8 and stub - The conduit is scheduled to be
located on Monday morning. Following the Looahe, decisions can be made in resolving the
conflict.
• Overhead power lines and poles have not been removed Art Nelison, with Excel, is working
on this issue, but said it may take some time before they can be removed.
Pine Grove Gardens:
• All utilities are complete.
• Approximately 75% of the concrete curb is complete. The remaining B618 concrete curb should be
completed today.
• The curb will be backfilled on Monday.
• The streets are expected to be paved by late next week,
'Wal-Mart:
• The water main connection on 58th Street was completed by wet tap yesterday.
Lowes:
• All three fill sites are currently being used by Frattalone (No|de —2 sites, CSM — 1 site). All silt fencing
surrounding these sites is to specification.
• Vosson Plumbing is on-site installing the internal utilities for the R.J. Ryan/CSM site east of Applebees.
Oakgreen:
• Expected construction start date: end of August/early September.
Let me know if you have any questions or concerns. Thanks.
Chris Long
Bonestroo, Rosene, Ander lik & Associates
Phone: 651-492-7747