HomeMy WebLinkAbout2005-01-05 OPH Ltr to ApplicantCity of Oak Park Heights
14168 Oak Park Blvd. N •Box 2007.Oak Park Heights, MN 55082 •Phone (651)439-4439 •Fax (651) 439 -0574
January 5, Zoos
11th. Russell Girtz
cel. Energy
1103 Ding Plant road
Bayport, MT 55003
RE: ME RP Building Permit Application
Dear Mr. G irtz,
Thank you again for taking the time to meet with City Staff on December 21 2004 to
come to a viable approach on how we handle the issuance of City building permits for the
MERP. The following is the approach that will be utilized:
1) City Building Permits are needed for all typical buildings /structures and for all
footings and foundations that be utilized for equipment, buildings, towers, etc. It
is estimated that there are 10 +f- buildings that will require the typical building
permit and 30 +I- footing and foundation permits. No work may continence,
including excavations, until City permits are issued.
2) xcel Energy will need to submit the full scope of the plans and specifications for
all structures that are typically required for any construction in the City — such as
.a shell building. Xcel is also required to submit the full footing and foundation
plans, including side elevations, as proposed to accommodate the installation
anticipated equipment. Load calculations must be. submitted with these footing
and foundation plans. All plans submitted shall be approved and signed --off by
Xcel' s Engineer(s); all such engineers shall be licensed and registered in the State
of Minnesota.
3) All subrm* scions shall include as a cover page, the appropriate Submission Form, a
DRAFT form is attached hereto. The actual final form to be utilized must include
the information as outlined, but may contain additional information. Once such
Form is agreed upon, the same form shall be utilized throughout the project.
Again, such form shall be the cover sheet for each submission and shall be on
BLUE paper. It is understood that there will be approximately 40 +/- separate
submissions. Additionally, Xcel shall submit a master list of projects depicting
each element o.. an appropriate site reap. This will aid th,J .-"lity in referencing
each project.
4) Upon the receipt of a Building Permit Application utilizing the Submission Form.,
the City will review tie application and accompanying plans /specifications for
completeness. once deemed complete and an actual review is completed, the City
may then issue a "Building Permit ". It is understood that the submissions for a
building permit from xcel may net be actual final design drawings, but shall and
must represent better than 95% of the anticipated scope of the proposed element
but shall be in full compliaace (100 %) with the City's Conditional Use Permit as
issued *n 2004 for the MERP. Assuming a positive review, the City will then issue
a building permit for these submissions that meet the 95 % threshold and
construction (including excavation) may then commence.
However, the City will not grant occupancy or allow continued installation of
equipment until xcel submits to the City for approval the actual original "as.
built" drawings that are WET SSIGlIE'D by Xc el' s Engineer as well as a short
written statement that all construction is in compliance with the State of
Minnesota Building Code(s). Any such revisions in the "as- built §" shall be
clearly "clouded" on the revised drawings showing the changes. Because final
plans are not being submitted to the City, xcel may incur re- inspection fees. All
plan review and permit fees will be calculated by the City and must be paid prior
to the issuance of a Building Permit.
5) 'There shall be no filling of any additional lands without the City's written
approval. All excavated materials shall be either removed from the City Limits or
shall be utilized on site for "final" grading purposes. xcel shall submit a FINAL
site grading plan by Feb 41h, 2005 for City review and approval that depicts and
discusses all anticipated areas to be filled. No other areas may be disturbed, filled
or cut without a separate Conditional Use Permit from the City, Please also
indicate if there is to be any stockpiling of any fill material,
6) .Towable construction hours in the City are Monday — Saturday from 7 am to 10
pm. The purpose of the rule is to ensure the appropriate repast of City residents
from construction noise. The City cannot authorize a deviation from this rule.
However, this rule is applicable to heavy construction equipment, back-up
beepers and noise that emanates from the site during off - hours. Xcel may
undertake operations during these off -hours that do not create such noise
conflicts. Should the need arise for operations that would be 'n conk ict of this
time requirement, xcel Energy shall notify the City and property owners within V2
mile, no more than two -weeks in advance that discusses such off -hour operations
and when residents can expect the operations to cease. Such off hour operations
that generate noise shall not exceed seven days.
7) Herewith, the City is returning to your attention all documents, plans and
0 specifications that have been previously submitted to the City for this project 1.
(dated 11/24104) as these documents have been determined as incomplete relative
to our recent meetings. Additionally, to date the City has not accepted any
building perm. _ ecs or application fees for this project. future submissions
shall follow the protocols as outlined in this correspondence.
S) The City suggests that Xcel Energy prepare an informational document that will
be provided on a semi- annual basis to the local community that outlines the
MEP.P progress and where someone can secure information from Xcel about the
project and how persons may be able to deal with potential conflicts that may
arise. This. document should be mailed to the City and to all. property owners
within 1 Iz mile of the plant's southern. most STH 95 entrance. A. complete mailing
list and ready - labels can be secured from Washington County Surveyor's
Office that incorporates such radius.
The City recommends that we continue to meet on a consistent basis this winter and
early spring to ensure that our efforts are coordinated. The City understands that Xcel
does have important timelines; likewise the City also has critical timelines and
requirements that may not have been enumerated here that help to ensure that permits
are correctly in place and that all parties in the City are treated similarly.
Please let me know if you have any questions.
incere ? �
l�
Eric old n
i strator
Cc: City Council Members
Jinn Butler, Building official
Mark Vierling, City Attorney
Darrell Knutson, Xcel Energy
Mark Fritsch, Xcel Energy
Byron Nordell, Xcel Energy
Ron. Elsner, Xcel Energy
Toni Volkmeier, MFCA
Richard Sandberg, MPCA
Paul Hei kes, MT Dept of A.dmin, Building Codes and Standards
Xcel Energy
Metropolitan Emission reduction Project
Building Permit Submission Form
Proj ect ID Number:
Please Refer to Master Reference Sheet - Dated
Geocode of Parcel:
summary Description of This Submission:
ti
Attach additional pages if necessary,
Date Submitted to City:
Submitted By:
Date Construction is Estimated to Begin:
(The City must have at least 60 days for project review)
�'�ro eft element Values
Footings 1 Foundations
Service Electrical
HVAC
Plumbing
Fire Protection
Plant Processing Equipment
Other
Total Valuation of Submission
Attach Two SETS of FINAL CONSTRUCTION DRAWINGS that show all elements of the
improvement directly to this sheet. Submitted drawings must be "WET" signed by Minnesota
Registered Architect 1 Structural Engineer.
Attached a copy of the Master Reference Sheet with the current improvement circled on the Site
Arrangement Drawing and highlighted in the legend.
0 Are there any hazardous materials that will be needed in conJunction with the construction of this
improvement or in its final operation? if YES please explain on separate sheet and also attach
MSDS.
a Construction Hours in Oak Park Heights are: Monday through Saturday from 7 am till, 10 pm
(City Ordinance 1105.06)
0 All contractors must be registered and licensed to work in Minnesota, the City requires copies of
all licenses.