HomeMy WebLinkAbout2009-11-17 Bonestroom Memo Re Storm Drainage Pipe Resolutions Memorandum qc• Bonestroo Project: Olene Ave. N. and 2335 Highway 36 W St.Paul,MN 55113 To: Eric Johnson Olinda Ave. N.—Storm Date: 11/17/09 Sewer Improvements Tel 651-636-4600 Fax 651-636-1311 From: Chris Long Client: Oak Park Heights www.bonestroo.com Re: Storm Sewer Drainage Pipe Resolutions File No: 000055-09162-0 Background: The private backyard drainage system between Olene Avenue North and Olinda Avenue North has failed. The existing 8"drainage pipe was determined to be plugged just north of the existing catch basin, which is located in the northwest corner of the existing parking lot at 5816 Olene Avenue North. The existing catch basin collects all of the drainage from the parking lot, which entails the runoff from the garage of 14386 58th Street North, and the building units of 5802 and 5816 Olinda Avenue North. The remaining backyards drain to the north above ground and not into the existing drainage system. City staff flushed water into the system which exposed the location of the plugged pipe. Water exited to the surface at two locations on the 5834 Olene Avenue North property, and drained above ground to the north. The only water observed exiting the system was on this property. This report presents two options for resolving the plugged drainage system; a temporary solution, and a permanent solution.The information presented here is the result of initial survey data, observations and meetings with City staff, and review of utility record information. Storm Sewer Drainage Resolutions: Option 1— Excavate and Repair Existing Drainage System: This option provides a temporary solution to repair the existing drainage pipe. This work entails exploring and excavating the existing pipe at the plugged locations. The pipe will be removed and replaced at the plugged locations until the drainage system is functional. Restoration and seeding of the disturbed area will be required. The pipe is located on private property with no City drainage and utility easements. The amount of the work required will vary depending on the extent of the plugged pipe. 5 of 33 Option 2—Install Storm Sewer on Olene Avenue North(see Figure 1): This option provides a permanent solution including installing storm sewer pipe and catch basins to collect drainage from the existing parking lot and Olene Avenue North. The existing drain system will be left in place with no connection to the new storm sewer system. Connection to the existing catch basin manhole (EX. CBMH) will be required at the southeast corner of Olene Avenue North and 59th Street North. The existing catch basin (EX. CB) located in the existing parking lot will be removed and replaced. Removal and replacement of the street aggregate base section and bituminous will be required for the installation of storm sewer. Landscaping, fences, a light pole, and a sign will require removal between 5834 Olene Avenue North and 5816 Olene Avenue North. Restoration and seeding of the disturbed area will be required. The storm sewer pipe connecting the catch basin in the parking lot will require a 20'drainage and utility easement for maintenance purposes. Cost Estimate(subject to actual pricing): The estimated costs for the storm sewer drainage resolutions are shown below: Total Costs Option Construction Cost Engineering Cost Total Construction Cost 1 $ 8,000.00 N/A $ 8,000.00 2 5 48,000.00 5 8,000.00 $ 56,000.00 For Option 1 and the purposes of this report, it was estimated that one-third of the total existing pipe will require replacement. It was assumed that no engineering would be needed as the replacement of the drainage pipe is private work. The costs for Option 2 included engineering fees and contingencies. Since the construction work is located within the City's right of way and proposed drainage and utility easement, engineering design and inspection of the construction will be required. The costs do not include the acquisition of easements. Page 2 of 3 6 of 33 Summary and Recommendations: The estimated cost for Option 1 is significantly lower than Option 2. This reflects the difference in a temporary solution vs. permanent solution. The existing drainage pipe can be repaired, but is more susceptible to fail and plug again. It is recommended to install the new storm sewer in Option 2 as a permanent solution. Including this work in future street reconstruction projects would be beneficial and reduce costs. If a resolution is required soon and prior to street reconstruction, Option 1 provides the best temporary solution. Page 3 of 3 7 of 33 • I ' I 1 ill i • Ce) FM n ii '' 1 j 1, g 4 F i 5898 : `(11 14385 1 EX. STORM SEWER(TYP.) I • I' ` 1 1, k ; I li r I i i 5896 11 1. 1 '. I I CONNECT lib EX. CBMH 5898 : i i 1 Ai i {(t i III 5889 11 1 18" RCP STORM SEWER EX. PRIVATE BRAIN TILE i I I <'' ,ii 5887 ,i 12" RCP STORM SEWER II II I 5888 j' 5886 5880 REMOVE AND REPLACE BITUMINOUS, 11 �1 5871 ;_NEW CB NEW CBMH PATCHING (TYP.)II j \ 5872 5862 I { 1 1 i1 (11 11 II 5857 5858 li I j 15" RCP STORM SEWER I i 5835 PROPOSED 20' DRAINAGE i j ; 5834 AND UTILITY EASEMENT(TYP,) 5836 10 �i ; ii`` NEW CBMH 5862 Lii if ^ II s i 5817 _ ._ 5810 II ' ~O 5816 '1 r ' 12" RCP STORM SEWER REMOVE AND REPLACE 1 ( C7 1 •EX. CAtCH BASIN I . 1 ' , 1 14386 a � 11 a , I i 1 w N i. 5850 5800 ( 5802 1 i , , ' o So 100 `_ 1. Horizontal Scale In Feet { CI, Ni i. 1 i OPTION 2 - STORM SEWER DRAINAGE IMPROVEMENTS CITY OF OAK PARK HEIGHTS FIGURE: 1 Bonestroo Olene Avenue North - Storm Sewer Improvements STOR?,1 EWER.DWG DATE: 11/17/09 COMM: 55-09000-0 Ask -,, •"6 -„, L.,-„ \ ,,,,,-,,,,e• ...„:„._, # 7,41N- - --:.-7- \ ••1 . -'''' Ni_:. •''' 1 "\ • N (4.1$'` ::-':' vo-i ,. \ , vi ,„„.. ,..4.4:44-'"zj'kt;'*7:7; \ \ „„ , ,. F ,-, J ... j-- -avikove9 , ,.•s- --- - \ \ / 1 I Z I -, \ _ , •,,, \ • 1 t•—• )...,-----..... , <,z,, '',,,, T 0 1 --- , 1 sr— ^er. i'..- . .,:,1 1 A ,,,' • 1 I,:z.-- ,....5 t...... 4, .s,. —• . _.•. .., :,7' , ....,. •—.A. al _._ a pi ca t1/4,y4 t / 14d asiit...y ,I• ,.2 t. ' .:0 (7\e / t V., ?..i.- 1,. ., .. . 1 ,14161, ti, , Cgtle 1 ... CIO VI t•-- • ., . 2:::: 9 of 33 _E-_-?. • , ___: :, et, . . ,,,,,,.,, , .. . ,. _. .. ..._ ..... tare* Viarsilw-s. lINE.". . . -__ Fax T.: From: 1 ;,03 Fax: (ivpM) _ s4,30 1131atM ) I -13 Phone: .. . Re: CC: - . 1:1 Urgent Ikl For Review El Please Comment El Please Reply ci Please Recycle •Commentst — U.\C . (D -k 14 57)41 WOULD Li LE yov to ?boa • Curb Masters, Inc. 500 W Poplar $1illwater,MN 55062 (651)351-9200 Fax(651)351-9300 10 of 33