Loading...
HomeMy WebLinkAbout2021-06-16 TPC Letter - Applicant Reponse TPC3601 Thurston Avenue N, Suite 100 Anoka, MN 55303 Phone: 763.231.5840 Facsimile: 763.427.0520 TPC@Planni ngCo.corn June 16, 2021 Will Zintl WINN, LLC 11255 50th Street North Lake Elmo, MN 55042 RE: Oak Park Heights — WINNPARK Business Center — Planned Unit Development Amendment Review— (Lot 4) 5650 Memorial Avenue North FILE NO: 236.02 — 21.05 Dear Mr. Zintl: The City of Oak Park Heights is in receipt of your application materials submitted on June 8, 2021, for an addition to the existing building at 5650 Memorial Avenue North. The application consists of a request for an Amended Planned Unit Development and Design Guidelines/Site Plan Review. With this letter we are notifying you that the application is not complete. The City will deem it complete with receipt of the following items by June 23, 2021: 1. The building height would be 38 feet at the west elevation. The definition of building height indicates that the mean ground level of the building would be the starting point for measurement of height. Please verify the height based on the mean ground level. The building height limit for a Planned Unit Development is t. 35 feerLANS HAVE BEEN REVISED TO INDICATED MAXIMUM BUILDING HEIGHT AT WEST WALL IS TO BE 35'. GRADES TO BE MODIFIED J l -ACCOP� c., TION 2. Section 401.06.B.15 indicates that no building in a Planned Unit Development shall be nearer to another building than one half the sum of the building heights of the two buildings. Please verify the setbacks based upon the buildings to the north and south of the subject site. DNS ADDED TO SITE PLAN TO INDICATE THE PROPOSED ADDITION COMPLIES WITH SECTION 401.06.8.15 REFER TO -.100 SITE PLAN 3. The B-3 District limits the overall WINNPARK site at 80 percent impervious surface coverage. In 2000, the site was 79 percent impervious. With the increase in hardcover, please provide the calculations of hardcover with the building expansion. 80%. 4. Indicate where trash/recycling will be stored for the building. Please identify any wall signage planned for the building. REFER TO NEV. BIT TRASH AND RECYLCING LOCATION SHEET -IC AfrlI't,,,,,' SICMACC IC PPnPnCP' We would invite you and your representatives to a Zoom staff meeting on June 23, 2021 at 10:30 AM at City Hall to discuss these issues and address any questions you may have. Julie Hultman will in contact with you about the meeting invite. SUBMITTAL DOCUMENTS REVISED TO INCORPATE CHANGES TO ADDRESS COMMENTS. REVISION 1,DATED JUNE 18.2021. *# a• Will Zintl June 16, 2021 If all of the application materials are submitted as requested, the Planning Commission would consider the application at a meeting scheduled at 6:00 PM at the Oak Park Heights City Hall on July 14, 2021. Pursuant to Minnesota Statutes 15.99, Sub. 3(f), the City of Oak Park Heights is herewith extending the period of time for agency/city review of the application for an additional 60- day period (for a total of 120 days from the date of a complete application) inasmuch as the City has determined that additional research and study by the City staff relative to the complexity of the project as proposed will be required. Please contact me at scott@planningco.com or 952.221 .0547 with any questions you may have. Sincerely, Scott D. Richards — City Planning Consultant to the City of Oak Park Heights The Planning Company LLC pc: Eric Johnson Julie Hultman 2