HomeMy WebLinkAbout2007-05-24 City Ltr to Homeowner Re Permit Conditions Timeline CITY 01 a OAK PARK HEIGHTS 14168 Oak Park Boulevard No. • P.O.Box 2007 • Oak Park Heights,MN 55082-2007 • Phone:651/4394439 • Fax:651/439-0574 May 24, 2007 Mr. Larry Phillips 5272 Stagecoach Trail Oak Park Heights, MN 55082 Re: Variance Permit Dear Mr. Phillips, On June 22, 2004, the City of Oak Park Heights approved a variance from Section 401.A.7 of the Zoning ordinance to permit the construction of a single-family structure at 5272 Stagecoach Trail, subject to conditions being imposed thereon. Condition 2.e. reads that a building permit shall be issued for a single-family structure on the subject site no later than July 1, 2005 and the structure shall be completed with a certificate of occupancy issued by July 1, 2006. Building Permit#2005-00061 was issued to you on March 25, 2005, for the construction of a single-family residential structure. The last recorded inspection to this permit is a framing inspection completed on 8/17/05. The time line for completion of this project is well over due. This letter is to inform you that I shall void this permit in 60 days from the date of this letter if the following conditions are not completed and complying with the Zoning and Building Codes adopted by the City of Oak Park Heights. The following conditions must be met: 1) A new site plan, drawn to scale,must be submitted to the Building Inspection Department for approval. Please note that the south driveway shown on the site plan submitted in March of 2005 is not permitted. Zoning Code Section401.15.6.d states that a driveway must lead directly into a garage and shall be constructed of concrete, asphalt cobblestone, or paving block. Please note that Class 5 rock is not acceptable. 2) The landscaping of your yard must be completed. This includes the necessary block retaining walls to be constructed in the front and rear yards. Again, a site plan must be submitted for approval. The landscaping shall include sod in the front and side yards to the edge of the curb on Stagecoach Trail and ornamental grass, or other acceptable vegetation may be used in the rear yard. Tree City U.S.A. • Page 2 3) The siding and soffits of the structure shall be completed. 4) The deck on the Southwest corner of the structure must be completed. The columns and beam shall be sided, deck boards installed and a guard rail installed at a minimum height of 36"with the maximum clear opening of the spindles no more than 4 inches. 5)' The door(s) going to the other deck must be secured so that the maximum clear opening is not greater than 4 inches. Prior to occupying this structure the following must be completed,inspected and approved by.the Building Official. The structure shall have the following: 1) One completed bathroom with a toilet, lavatory, shower or tub, and a finished floor. 2) A kitchen sink and hot and cold water supplied to all plumbing fixtures. 3) A heat source in the structure. 4) A final electrical inspection of the structure. 5) Final electrical,plumbing, heating, and building final inspections must be requested by you,completed and approval granted prior to occupancy of this dwelling. Please be advised that if these directions are not completed and complying to the City Codes, legal remedies may be pursued to correct these violations. Contact me if you have any questions. Sin erely, imBu / Building Official CC: Eric JohnsonCity Administrator , Mark Vierling, City Attorney Scott Richards, City Planner Julie Hultman, Planning& Code Enforcement Officer