HomeMy WebLinkAboutPL 2022-00166 New & State Review Report CITY OF OAK PARK HEIGHTS 1111111111 111111111111 11
14168 OAK PARK BLVD N.
OAK PARK HEIGHTS, MN 55082- * 2 0 z z - 0 0 1 6 6 *
(651)351-1661 FAX: (651) 439-0574 ISSUED: 08/15/2022
Permit #: 2022-00166
ADDRESS : 13961 60TH ST N
PIN : 05.029.20.11.0156
LEGAL DESC : N/A
: LOT 0 BLOCK 0
PERMIT TYPE : PLUMBING
PROPERTY TYPE : COMMERCIAL
CONSTRUCTION TYPE : NEW CONSTRUCTION
VALUATION : $ 179,900.00
NOTE: PERMIT ISSUED FOR PLUMBING AND AIR PIPING,VAC PIPING AND MED GAS PIPING TO NEW PARK DENTAL
S'I RUCTURE. WORK SHALL COMPLY WITH MN STATE PLAN REVIEW AND PLANS. PERMIT INCLUDED A 1-1/2 INCH WATER
MTER AND RADIO.
VALUE OF PLUMBING 179900 WATER METER FEE 0
APPLICANT PLUMBING-COMMERCIAL 1,799.00
PLUMBING STATE SURCHARGE COMMERCIAL 89.95
COMMERCIAL PLUMBING& HEATING INC. WATER METER 1,686.00
24428 GREEN WAY AVE.
FOREST LAKE,MN 55025-0000 WATER SALES TAX 124.34
(651)464-2988 WATER FUND 210.00
Minnesota State License#:2668731 SAN SEWER FUND 35.00
TOTAL 3,944.29
Payment(s)
OWNER CHECK 155303 3,944.29
DRF STILLWATER DENTAL LLC
7101 W 78TH ST#100
MINNEAPOLIS, MN 55439-
AGREEMENT AND SWORN STATEMENT
The work for which this permit is issued shall be performed
according to: (1)the conditions of this permit;(2)the
approval plans and specifications;(3)the applicable city
approvals,Ordinances,and Codes;and,(4)the State Building
Code. This permit is for only the work described,and does
not grant permission for additional or related work which
requires separate permits. This permit will expire and become
null and void if work is not started within 180 days, or if work
is suspended or abandoned for a period of 180 days any time
after work has commenced. The applicant is responsible for
assuring all required inspections are requested in conformance
with the Minnesota State Building Code.
SEPARATE PERMITS REQUIRED FOR WORK OTHER THAN DESCRIBED ABOVE.
mot DEPARTMENT OF
LABOR AND INDUSTRY
Division of Construction Codes and Licensing
REPORT ON PLUMBING PLANS
PROJECT: Park Dental St. Croix Valley, 13961 60th St.N, Oak Park Heights, Washington County, Minnesota,
Plan No. PB-R2204-0244
OWNERSHIP:
SUBMITTER: Commercial Plumbing and Heating Inc.,24428 Greenway Avenue, Forest Lake, MN 55025
Plans Dated: April 28, 2022
Initial Date Received: April 27, 2022
Last Date Received: July 5,2022
Date Approved: July 6, 2022
This review is limited to the provisions of the Minnesota Plumbing Code, Minnesota Rules,Chapter 4714 and
assumes the data on which the design is based are correct. Approval is contingent upon meeting the requirements
listed below. A copy of the approved plans and this report must be retained at the project location.
INSPECTIONS: This project will be inspected by the local municipality. The contractor/installer must obtain
all required inspection permits from the Oak Park Heights Building Official, Julie Hultman. All plumbing
installations must be tested and inspected in accordance with the requirements of the Minnesota Plumbing Code.
No plumbing work may be covered prior to inspection.
REQUIREMENT(S):
1. All plumbing shall be installed in accordance with Chapter 4714. All pipe, fittings,traps,fixtures,
materials, and devices shall be listed or labeled by a third-party listing agency and comply with the
applicable standards referenced in the code(see Sections 301.2 and 1701.1).
2. The horizontal drainage piping must be installed with a uniform slope of at least 1/4 inch per foot(see
Section 708.1). Where municipal sewer depth, structural features,or building arrangement preclude this
slope, a minimum slope of 1/8 inch per foot may be utilized for piping 4 inches and larger if approved by
the authority having jurisdiction.
3. No plaster traps are shown on the plans or being proposed on this application. Be advised plaster traps are
approved for special conditions under Minnesota Rules,part 4714, section 1004.1. Plaster traps when
provided or supplied by owner must be in compliance with the following:
a. Listed by an independent 3rd party to a nationally recognized standard for the application (Section
301.2).
b. Plaster trap must be in accordance with the manufacturer's installation instructions and Minnesota
Rules,part 4714, section 1004.1.
c. All concealed interiors must be constructed of plastic or similar noncorrosive partitions.
d. Flexible pipe is not an approved material.
4. Water supply connections to fixtures or equipment which have inlets below the spill line must be provided
with an approved backflow preventer(see Section 602.3). This shall include a model trimmer.
'443 Lafayette Road N., St, Paul, MN 55155 « (651) 284-5005 • www.dli.rnn. ov
An Equal Opportunity Employer
Park Dental St Croix Valley
Plumbing
Plan No. PB-R2204-0244
Page 2 of 3
07/06/2022
5. Sewers crossing above or less than 12 inches below a water service must be constructed of materials
approved for use within a building(see Sections 609.2, 720.1,and Table 701.2). The water service should
not contain any joints or connections within 10 feet of the crossing. This shall include the RCP storm sewer
crossing.
6. Double wyes may not be used for drainage fittings in the horizontal position(see Section 310.5). Proper
pipe slope cannot be maintained on both of the offset branches.
7. PVC sanitary or storm sewers must meet ASTM D1785, D2665, D2729, D3034, F794, F891, F1488, or
F1760 with approved fittings(see Table 701.2). Only ASTM D1785, D2665, F891, F1488,or F1760 PVC
may cross above or less than 12 inches below potable water lines (see Section 720.1). Solvent welded joints
must use ASTM F656 purple primer and ASTM D2564 cement. The sewer must be installed by open-
trench on a continuous granular bed per Section 314.4.1.
8. AASHTO M252 HDPE pipes 4-inch to 10-inch or ASTM F2306 HDPE pipes 12-inch to 60-inch may be
used for storm sewers only if approved by the administrative authority as alternate materials prior to
installation (see Section 301.3):
a. Pipes must be listed and labeled. Fittings are not permitted.
b. Pipes must be installed with a minimum 10-feet separation from water piping and may not cross above
or less than 12 inches below water service lines (see Section 720.1).
c. HDPE pipes must not be installed within 10 feet of a building.
d. HDPE connection to a different material must use an approved listed application-specific transition
coupling meeting ASTM C1173 or ASTM C1461 (see Section 705.10).
e. Water-tight resilient joints must be used at all connections, including structures.
f. Installation must be open-trench per Section 314.4.1 and manufacturer's installation instructions.
Otherwise, the storm sewer pipe material must meet Table 701.2.
9. Materials used for subsoil drains must comply with Table 1101.4.6. Polyethylene pipe must meet ASTM
F667 and PVC pipe must meet ASTM D2729. Alternate materials may be used if approved by the
administrative authority prior to installation(see Section 301.3).
10. Stormwater infiltration systems may be subject to groundwater contamination and hydraulic failure. Verify
that the administrative authority has approved the design. Please contact the storm water program staff at
the Minnesota Pollution Control Agency(MPCA)for construction and permit requirements.
NOTE(S):
1. The scope of this project consists of constructing a new building. The plumbing installation includes a
water heater,wall hydrants, floor drains,a mop sink, exam room sinks, lab sinks,treatment sinks,a
breakroom sink, single compartment sinks,primary and overflow roof drains,and restroom fixtures. A
flammable waste interceptor and a grease interceptor will also be installed.
2. The building will be served by new municipal sewer and water services. New storm sewer will also be
installed serving area catch basins and building rainwater leaders.
3. The interior plans and specifications were prepared by a licensed plumber. Only the plumber who has
prepared the plans may use the plans for construction. If another plumber is contracted to install the
plumbing,they must submit their own plans and specifications for the project.
Park Dental St Croix Valley
Plumbing
Plan No. PB-R2204-0244
Page 3 of 3
07/06/2022
Authorization may be withdrawn if installation does not begin within one year. Additional requirements may
result from changed conditions or additional information.
Approved:
grAM7/ `26;(444"..%)
Bradley Williams, P.E.
Public Health Engineer
Plumbing Plan Review and Inspections
651/284-5836
Bradley.Wi lliams@state.mn.us
cc: Commercial Plumbing and Heating Inc.
Julie Hultman, Building Official
File
DEPARTMENT OF
LABOR AND INDUSTRY
June 27,2022
Commercial Plumbing and Heating Inc.
24428 Greenway Avenue
Forest Lake,MN 55025
Gentlemen/Ladies:
Subject: REQUEST FOR ADDITIONAL INFORMATION regarding plumbing at Park Dental St. Croix
Valley, 13961 60th St.N, Oak Park Heights,Washington County,Minnesota,
Plan No. PB-R2204-0244
We are NOT able to grant approval at this time of the plans and specifications submitted for the above-
designated project. The following comment(s)outline the changes and/or additional information that must be
submitted so that we can further evaluate the plans and specifications for compliance with the standards of this
department:
1. The plumbing plans were reviewed for this project and it has been determined that the submitted fee is
incorrect. There appears to be a total of 110 drainage fixture units which requires a$350 fee,4 roof drains
which requires a$200 fee, for a total fee of$550. Since you submitted$350,you must submit an additional
$200(see Minnesota Statutes, Section 326B.49, subdivision 2).
2. Please provide a utility site plan showing the water and sewer service connections within the property lines,
including pipe sizes, slopes,materials,and the designer's signature and license number. Please note that a
utility site plan is required for plumbing plan review for all new construction projects or whenever new
utility connections will be installed.
Please submit the requested information promptly so we may complete our plan review. No plumbing installation
related to the above-referenced plans shall begin until approval is provided by our office. When submitting
additional information,please refer to Plan No. PB-R2204-0244.
Sincerely,
got,/ Lrl.I:a.
Bradley Williams,P.E.
Public Health Engineer
Plumbing Plan Review and Inspections
651/284-5836
Bradley.Williams@state.mn.us
cc: Commercial Plumbing and Heating Inc.
Julie Hultman,Building Official
File
443 Lafayette Road N., St. Paul, MN 55155 • (651) 284-5005 • www.dli.mn.gov