HomeMy WebLinkAboutPL 2025-00244 RemodelCITY OF OAK PARK HEIGHTS
14168 OAK PARK BLVIA N.
OAK PARK HEIGHTS, MN 55082-
(651) 351-1661 FAX: (651) 439-0574
ADDRESS : 5950 NOVA SCOTIA AVE N
PIN : 05.029.20.12.0047
LEGAL DESC : OAK PARK COMMONS
LOT 5 BLOCK 1
PERMIT TYPE PLUMBING
PROPERTY TYPE COMMERCIAL
CONSTRUCTION TYPE REMODEL
111111111111111111111111
ISSUED: 10/28/2025
Permit #: 2025-00244
VALUATION : $ 1,800.00
NOTE: WORK SCOPE: REPLACEMENT OF WATER FONT TAP & INSTALLATION OF CARBONATION CHILLER. WORK SHALL BE
PER MANUFACTURER SPECS, MN CODE & COMPLY WITH MN DLI PLUMBING REVIEW #PB-R2509-0013.
VALUE OF PLUMBING 1800
APPLICANT
BEELINE PLUMBING
7101 143RD AVE NW
RAMSEY, MN 55303-
(763) 292-4518
OWNER
OPC PROPERTIES LLC
4737 CO RD 101, STE 243
MINNETONKA, MN 55343-0000
AGREEMENT AND SWORN STATEMENT
The work for which this permit is issued shall be performed
according to: (1) the conditions of this permit; (2) the
approval plans and specifications; (3) the applicable city
approvals, Ordinances, and Codes; and, (4) the State Building
Code. This permit is for only the work described, and does
not grant permission for additional or related work which
requires separate permits. This permit will expire and become
null and void if work is not started within 180 days, or if work
is suspended or abandoned for a period of 180 days any time
after work has commenced. The applicant is responsible for
assuring all required inspections are requested in conformance
with the Minnesota State Building Code.
PLUMBING -COMMERCIAL 75.00
PLUMBING STATE SURCHARGE COMMERCIAI 0.90
LICENSE VERIFICATION 5.00
TOTAL 80.90
Payment(s)
CHECK 123469
80.90
SEPARATE PERMITS REQUIRED FOR WORK OTHER THAN DESCRIBED ABOVE.
DEPARTMENT OF
-• LABOR AND INDUSTRY
Division of Construction Codes and Licensing
REPORT ON PLUMBING PLANS
PROJECT: Starbucks, 5950 Nova Scotia Avenue, Oak Park Heights, Washington County, Minnesota,
Plan No. PB-R2509-0013
OWNERSHIP: Starbucks, 5950 Nova Scotia Avenue N, Oak Park Heights, MN 55082
SUBMITTER: Beeline Plumbing, 7101 143rd Avenue NW, Ramsey, MN 55330
Plans Dated: Refer to DLI stamped plans
Initial Date Received: September 2, 2025
Last Date Received: October 9, 2025
Date Approved: October 10, 2025
This review is limited to the provisions of the Minnesota Plumbing Code, Minnesota Rules, Chapter 4714 and
assumes the data on which the design is based are correct. Approval is contingent upon meeting the requirements
listed below. A copy of the approved plans and this report must be retained at the project location.
INSPECTIONS: This project will be inspected by the local municipality. The contractor/installer must obtain all
required inspection permits from the Oak Park Heights Building Official, Julie Hultman. All plumbing
installations must be tested and inspected in accordance with the requirements of the Minnesota Plumbing Code.
No plumbing work may be covered prior to inspection.
REQUIREMENTS:
1. All plumbing must be installed in accordance with the 2020 Minnesota Plumbing Code, Chapter 4714. All
pipe, fittings, traps, fixtures, materials, and devices shall be listed or labeled by a third -party listing agency
and comply with the applicable standards referenced in the code (see Sections 301.2 and 1701.1).
2. The re -use of existing fixtures/equipment is prohibited unless the fixtures/equipment conform to the current
Minnesota Plumbing Code (see part 4714.0101, subparts 3 and 4).
3. Indirect waste pipes in food and beverage establishments must meet the requirements of Section 801.3:
a. Ice maker drains must be the larger of the drain outlet or'/4-inch.
b. Food -handling fixtures must be trapped, piped separately, and discharged by an air gap. The drain must
be the larger of the equipment outlet or'/4-inch.
c. All other indirect wastes must be at least 1-inch in size.
d. Except for refrigeration coils and ice makers, indirect waste length may not exceed 15 feet.
4. The plans show the installation of a Micromatic Water Dispensing Tower and a Marco Friia Max 80
chiller/carbonator. Our understanding is that the dispensing tower is a dual tap that will serve filtered water
from one tap and carbonated water from the other tap, and the chilled water will be circulated through the
chiller and the dispensing tower to cool the taps.
The chiller/carbonator and the dual tap tower must be constructed such that a failure of the refrigeration
equipment and/or the circulated chilled water pipes will not result in a cross -contamination with the
carbonated water or filtered water. A failure of the refrigeration equipment/circulated chilled water piping
must leak into a space that is vented to atmosphere (see Section 603.5.4.2).
443 Lafayette Road N., St. Paul, MN 55155 • (651) 284-5005 • www.dli.mn.gov
An Equal Opportunity Employer
Starbucks
Plumbing
Plan No. PB-R2509-0013
Page 2 of 2
10/10/2025
5. All materials used in potable water systems must meet the requirements of NSF 61 (see Section 604.1). Pipe
and fittings with lead content must not exceed 0.25 percent lead in the wetted surface material (see Section
604.2). Solder and flux shall contain less than 0.2 percent lead. Joints must use ASTM B813 non -corrosive
non -toxic paste -type flux (see Section 605.1.4).
6. The plumbing system must be tested in accordance with Section 609.4. The potable water system must be
disinfected per Section 609.9.
NOTES:
The scope of this project consists of replacing a glass filler with a dual tap water dispensing tower supplied
with carbonated water and filtered water. Filtered water will be delivered to the tap as well as routed
through a new ASSE 1022 backflow preventer to a new chiller/carbonator unit. The dual tap will be used for
90 days before the glass filler will be re -installed.
2. This facility is served by existing municipal sewer and existing municipal water services.
The plans and specifications were prepared by a licensed plumber. Only the plumber who has prepared the
plans may use the plans for construction. If another plumber is contracted to install the plumbing, they must
submit their own plans and specifications.
The licensing authority may require additional plans, information, and fees. Changes to the plumbing
system may result. Any significant plumbing changes must be approved by this office prior to installation.
5. The current Minnesota Plumbing Code, Chapter 4714, and related information can be found at:
http://www.dli.mn gov/business/plumbing-contractors/2020-m innesota-plum bing-code
Authorization may be withdrawn if installation does not begin within one year. Additional requirements may
result from changed conditions or additional information.
Approved:
Scott Sawyer, P.E.
Public Health Engineer
Plumbing Plan Review and Inspections Unit
651/284-5803
scot t. saMerna.stat e. m n . us
cc: Beeline Plumbing
Julie Hultman, Building Official
File
Store 13347 Work Scope: CO2 Tanks in CBS Casework
Site Plan: Jacob Forschen
Master Plumber
PM 806865
El
CBS Overview Photo:
:T- ... , -
any_
Carbonator Install Location / Fridge For Relocation Photo:
Existing Sink
WNW
r'
1
MDEPARTMENT OF
LABOR AND INDUSTRY
THIS PLAN REVIEWED FOR COMPLIANCE WITH
THE MINNESOTA PLUMBING CODE, CHAPTER 4714.
DATE APPROVED: 10/9/2025
PLAN REVIEW NO: PB-R2509-0014
REFER TO THE REPORT ISSUED BY THIS
DEPARTMENT FOR ADDITIONAL REQUIREMENTS
i
RIGHT CBS undercounter fridge will be relocated and Carbon ator will be installed in its place. Do not
remove fridge until night of install.
Cold Filtered Water Font & Plumbing Photo:
Plumbing Scope:
Cold water font that will be replaced is outlined in the photo above. Ensure filtered water line reaches
planned Carbonator location. Add back -flow preventer as required byjurisdiction.
Fridge Relocation Area Photo:
Casework Modifications Required For Fridge Relocation:
CBS fridge will be relocated to the brewing area. Remove the large cabinet indicated in green above. Add
telescoping stainless steel support leg(s), since the Clover Vertica weighs—350Lbs. Undercounter
refrigerator stop / L bracket must be installed (or existing relocated) to ensure fridge is not able to be
pushed back into back wall components.Undercounter refrigerator stop / L bracket must be installed (or
existing relocated) to ensure fridge is not able to be pushed back into back wall components.
Fridge Relocation Electrical Receptacle Photo (if present):
Electrical Scope (if required):
Use existing open electrical receptacles immediately behind the fridge relocation casework or others
behind adjacent fridge. No scope nor electrical permit needed.
CO2 Tank Placement Area Photo:
"XWM WA- -7 W ! �
(2) 20Lb CO2 tanks will be installed adjacent to the Carbonator Location in the space where the CBS fridge
will be removed.
CO2 Tubing Run (if applicable):
Not Applicable - 2 x 201b CO2 tanks will be placed at the same location as the Carbonator.
Operations Message / Scope:
r�� `11:T'
iw
Prior to install night, the store needs to empty the brewing cabinets inside the green box shown above
and relocate those items elsewhere.
GC supplier to provide:
• ASSE 1022 backflow preventer per MN code
■ Analog pressure gauge
■ Compression tee
• 1/4x1/4union
• Telescoping stainless steel Leg or other appropriate bracing for countertop support (if necessary)
• PVC conduit and escutcheon plates for BOH CO2 tank installs
0 McLamine mounting panel for CO2 brackets (where side panel of casework has a cutout)
■ Snap -in Plastic Cord Grip (used on install night, need 2 per store)
Starbucks to provide:
■ CO2 brackets via Zephyr
• Appropriate length of CO2 tubing via Zephyr
• Micromatic font
• Friia Max 80 Carbonator