HomeMy WebLinkAbout2007-10-11 NAC Ltr. to ApplicantNORTHWEST ASSOCIATED CONSULTANTS., INC.
4800 Olson Memorial Hi Suite 202, Golden Valle MIN 55422
Telephone: 763.231.2555 Facsimile: 763.231.2561 plan ners@nacpla nnin
October 11, 2007
Sent via facsimile 952-541-9554
Mr. Paul Dahl
WCL Associates Inc.
4931 West 35t" Street OCT 1 2'
Suite 200
St. Louis Park, MN 55416
RE: Oak Park Hei — Bracke 3rd Addition Development / Best Bu
60th Street North and Krue Lane
FILE NO: 798.02 — 07.09
Dear Mr. Dahl:
The Cit of Oak Park Hei is in receipt of y our application submitted October 1, 2007
seekin consideration for y our project. The application consists of re for a
planned unit development/concept and g eneral plan, and site plan review for
consideration of a two phase multi-tenant retail commercial development containin up
to 50,750 s feet of tenant space at 60th Street North and Krue Lane. With this
letter, we are notif y ou that y our application will be deemed complete with the
receipt of the followin items b October 17, 2007. If the materials are not submitted b
that date, the application will be deemed incomplete and will not be accepted b the
cit
1. The si application should be amended to include a re for a zonin
district amendment ( from 0, Open Space to B-2, General Business District and
for subdivision review.
2. A complete si plan that indicates an elevation dia of the monument si
dimensions of all proposed si and specifications of how the si will be lit.
3. The parkin plan information should be clarified as to the ;number of proposed
parkin stalls on site for both phases. Some of the submitted plans indicate
proof of parkin stalls.
Mr. Paul Dahl
October 11, 2007
Page Two
4. The lighting plan should be clarified as to total height of parking lot fixtures.
Lights on poles cannot exceed 25 feet from ground level to the highest part of the
fixture. Specifications for all light fixtures, including parking lot and exterior
building lights must be submitted.
5. The building elevations should be labeled. The material and color legends
should be updated to reflect the proposed building in oak Park Heights.
Percentages of building materials, glass areas, and colored sign areas will be
required.
0. color elevations of each fagade of the proposed building is required.
7. Photos of similar Best Buy buildings from other locales would also assist in
Design Guideline review.
8. The plans should indicate a plan for location of rooftop mechanical units and how
they will be screened from Highway 30 and other surrounding properties.
9. Plans for trash enclosures or compactors must be provided.
10. Plans for screening of loading dock areas from the west will need to be provided
including a perspective diagram with landscaping.
11. A materials board will be required at the November 8, 2007 Planning
Commission meeting.
12. Any additional requests of City staff.
Staff reviewed the application materials at a meeting on October 10, 2007. There are
three issues that were identified that should be discussed with you as we proceed with
the project. Access and internal circulation, trail connections that will be required, and
the existing WalMart sign were highlighted as issues. We would invite you and your
representatives to a staff meeting on October 17, 2007 at 10:00 AM at City Hall to
discuss these issues and address any questions you may have.
If all of the application materials are submitted as requested, the Planning Commission
would consider the application at their meeting scheduled for November 8, 2007 at 7:00
PM in the City Hall Council Chambers.
Mr. Paul Dahl
October 11, 2097
Page Three
Pursuant to Minnesota Statutes 15.99, Subd. 3(f), the city of Oak Park Heights is
herewith extending the period of time for agency /city review of the application for an
additional 50 day period (for a total of 129 days from the date of application) inasmuch
as the City has determined that additional research and study by City staff relative to the
complexity of the project as proposed will be required. Please contact me with any
questions you may have.
Sincerely,
NORTHWES ASSOCIATED CONSULTANTS, INC.
Scott D. Richar s, AICP
Senior Planner
pc: Eric Johnson
Julie Hultman
Robert Brackey (via facsimile 651.489.1405)