Loading...
HomeMy WebLinkAbout2005-07-22 OPH Email Re Water Main TestJulie Hultman From: Tom Ozzello Sent: Friday, July 22, 2005 11:17 AM To: Julie Hultman Subject: RE: Fox Hollow -- Water Main Test Fox Hollow passed the water pressure test on Thursday, July 21, 2005 with Tess than 1.5 # loss over two hours. The conductivity test can be done after building service is established. The sewer testing must pass when conducted or the builder will be responsible for making any necessary repairs. tom From: Julie Hultman Sent: Friday, July 22, 2005 11:12 AM To: Tom Ozzello Subject: Fox Hollow - Water Main Test Hey Tom Has Fox Hollow passed their water main test since Wednesday (July 20th)? If so, am I correct in understanding that passing of the test constitutes my being able to issue them their construction permit for the condo project so that they may get to the point of placing the necessary fill over the sanitary sewer main which should be scheduled for testing at such point the backfilling has been done? Thanks, Julie H. 1 ci)