HomeMy WebLinkAbout2005-08-12 BRAA WeeklyProject UpdateJulie Hultman
Let me know ifyou have any questions/concerns. Have a great weekend!
Brian M~ Kelley
Construction Supervisor
Boczmtroo,Rosecc
Office: (715) 381-8340
Mobile: (651) 324-5586
Fromm. Kelley, Brian [bke|lev@bonestroo.00ni
Sent: Friday, Augus 12, 2005 12:19 PM
To: Eric A. Johnson; Tom Ozzello, Judy Holst; Juiie Hultman
Cc: PooUer, Dennis M; Erickson, Karen S, Hanson, David D
Subject: Project update for week of 8-12-05
Here is this week's update for ongoing projects:
8/12/2005
Page 1 of 1
Fox Hollow
�Mandrel testing of sanitary sewer has been completed.
• TV testing of sanitary sewer will be scheduled. Once this is done, all of the utility testing will be completed.
Punch list inspections will not be done until after the parking lots are built.
�
Bonestroo's erosion and sediment control inspector has begun inspecting this site. Weekly inspections will
continue until all concerns are addressed. Then inspectionswiil be reducedtoevery any
major rain event.
McKean Square
• Burschville Construction has completed the sanitary sewer and water main punch lists.
� Most of the storm sewer punch Iist is done. They stiil have to clean all of the lines (Infratech did some this
morning until they had mechanical problems — they will be back on Monday), repair 2 sections of cracked pipe,
and TV the pipes.