Nothing much to report this week:
Fox Hollow
�
TV testing of sanitary sewer should be done next week. Infratech will be callirig me to schedule this. That will be
all of the sanitary sewer testing other than visual inspections when the structures are adjusted to final grade.
McKean Square
�
Infratech is nearly done cleaning the storm sewer lines — there are a few lines with larger rocks that need special
equipment. They wiU be back to finish on Tuesday.
�
After the cleaning is done, the storm sewer lines below the streets will be inspected with a closed circuit TV
camera to determine extent of cracked pipe.
�=
After the extent of the cracked pipe is determined, the pipes will be removed/replaced and the street will be
restored.
Have a great weekend!