HomeMy WebLinkAbout2005-09-23 BRAA Weekly Project UpdateJulie Hultman
From:
Sent:
To:
Kelley, Brian [zka| nestroo.00n]
Friday, September 23, 2005 4:02 PM
Eric A. Johnson; Tom Ozzello; Judy Holst; JuIie Hultman
Cc: Postler, Dennis M; Erickson, Karen S
Subject: Weekly projec update
Here is the update for this week:
Fox Hollow
� Buildirig construction in progress
�
All sanitary sewer testing is completed. 1 area of concern will be addressed when the TV tapes are received
from |nfnabaoh. This area is where they cut an 8" saddle into the sanitary sewer main. The cut is 'agged, and
needs to be re-examined to determine if it is a point where a blockage could occur. Should we determine that this
cut needs to be re-done, there are options that exist to fix it from inside the pipe (as opposed to excavating down
to the saddle).
DNcKma, Square
No change from last week. Cured-in-place storm sewer repairs are being coordinated with Infatech.
9/26/2005
Page 1 of 1