Here is the project update for this week.
Fox Hollow
• No change from last week. Retaining wall and building construction in progress. Contractor has been
addressing erosion control issues promptly.
• TV testing of sanitary sewer will be completed by Infratech next Thursday or Friday. 111 be on site to inspect.
McKean Square
• TV testing of all storm sewer lines below the street will be completed next Thursday or Friday in conjunction with
Fax Hollow sanitary sewer. 111 be on site to inspect. All cracked pipe will be identified and corrections will be
scheduled.
Have a great 3-DAY weekend!
Brian M. Kelley
Construction Supervisor
Bonestroo, Rosene, Anderlik, & Associates
Office: (715) 381-8340
Mobile: (651) 324-5586