Here is the update for this week:
Fox Hollow
Building construction in progress
}�
All sanitary sewer testing is completed. 1 area of concern will be addressed when the TV tapes are received
from |nfnabeoh. This area is where they cut an 8" saddle into the sanitary sewer main. The cut is 'agged, and
needs to be re-examined to determine if it is a point where a blockage could occur. Should we determine that this
cut needs to be re-done, there are options that exist to fix it from inside the pipe (as opposed to excavating down
to the saddle).
McKean Square
No change from last week. Cured-in-place storm sewer repairs are being coordinated with Infatech.