Fire Substation - Cost Estimates - Councilmember Swenson
expressed concern regarding response time and the overall safety
of the Oak Park Heights community due to the distance of trip
from the Bayport fire station. He also noted the Highway 36
reconstruction would slow response time from Bayport. For these
reasons he wished to go ahead with a study to look at
construction of a fire substation in Oak Park Heights. He
presented cost estimates showing that it would cost approximately
$500,000.00 to build a fire substation and provide the initial
equipment. Councilmember Schaaf, seconded by Swenson, moved to
table this item until the August 14, 1995 meeting and to direct
the City Planner to update the fire hall study that had been done
several years ago. Carried 4 -0.
Correspondence:
Letter - Lois Hall - Canadian Geese Problem - Lois Hall was
present and described the problems caused a growing flock of
canadian geese adjacent to her home. aouncilmember Swenson,
seconded by Kern, moved to direct staff to contact the Department
of Natural Resources to see what expenses the city would face if
it relocated some or all of the geese. Carried 4 -0.
Chamber of Commerce Newsletter - Council acknowledged receipt of
the Chamber of Commerce Newsletter.
Thank You Letter - Valieta Andrews - Council acknowledged receipt
of Valieta Andrews' thank you letter.
Tower Asphalt Request For Payment - Councilmember Kern, seconded
by Swenson, moved to approve payment to Tower Asphalt for street
reconstruction for $273,071.32. Carried 4 -0.
Adjournment:
Councilmember Schaaf seconded by Kern, moved to adjourn the
council meeting at 10:47 p.m. Carried 4 -0.
City Administrator Robertson noted that the Council would be
going into a closed meeting to discuss a personnel issue.
Respectfully submitted,
,l71?
Michael - obertson
City Administrator