HomeMy WebLinkAbout2003-04-16 Planner Email Re 60/120 day timelines Page 1 of 1
Scott Richards
From: "Scott Richards" <srichards @nacplanning.com>
To: "Eric Johnson" < eajohnson @cityofoakparkheights.com >; "Mark Vierling" <mvieriing @eckberglammers.com >;
"Judy Hoist" <jholst @cityofoakparkheights.com>
Sent: Wednesday, April 16, 2003 2:50 PM
Subject: 60/120 day timelines
Eric, Mark and Judy:
Here are the 60/120 day timeline updates for current projects. WATE and Andersen were extended to 120 day. Oakgreen Village
was also extended to 120 day and a 30 day extension was granted by the applicant.
Oakgreen Village: Application- December 20, 2002; 60 day- February 17, 2003; 120 day- April 18; Additional 30 days- May 18
WATE: Application- March 25, 2003; 60 day- May 23; 120 day- July 22
SC Mall (Andersen): Application- February 21, 2003; 60 day April 21; 120 day- June 20.
Scott
4/22/2003