Loading...
HomeMy WebLinkAbout2011-05-04 Planning Report T 3 601 Thurston Avenue N, Suite 100 ENC SURE 4 Anoka MN 55303 Phone: 763.23'1 .5840 Facsimile: 763.427.0520 TPC@PlanningCo. corm PLANNING REPORT TO: Eric Johnson FROM: Scott Richards DATE: May 4, 2011 RE: Oak Park Heights — Xcel Energy / A.S. King Plant: Max Todo Marine Services — Conditional Use Permit Amendment/Interim Use Permit FILE NO: 798.02 — 11.03 BACKGROUND Tom Huninghake, of Max Todo Marine Services, has made application for an amended Conditional Use Permit (CUP) and Interim Use Permit to allow for the marine services business to utilize the existing boat landing on Xcel Energy property as a barge parking and staging area. The boat landing is north of the Allen S. King Generating Plant and is accessed off an existing roadway within the Xcel property. The plant is located at 1103 King Plant Road and is adjacent to the St. Croix River. Xcel Energy has agreed to the use of the boat landing for the marine services use. The property is zoned I, Industrial District in which this marine services business would be a permitted use. The property is also in a River Impact District which required the original CUP for the Allen S. King Plant and the subsequent amendments that have allowed the plant to expand. Attached for reference: Exhibit 1: Letter from Xcel Energy Exhibit 2: Fact Sheet for Proposed Barge Staging Area Exhibit 3: Allen S. King Plant Property Layout Exhibit 4: Proposed Barge Staging Area Exhibit 5: Pictures of Barge Staging Area ISSUES ANALYSIS Project Description. The description of the proposed barge staging area from the applicant is as follows: "Background: Xcel Energy is the owner of property north of the Allen S. King Generating Plant (King) that is zoned for industrial use and is currently developed as a boat landing (Exhibit 3 and 4). The boat landing consists of a -900 foot access road (off of a King Plant maintained road) to the St. Croix River. Further, the landing has a -75 foot by -125 foot parking area/tum- around located approximately 125 feet back from the shoreline. In the past, the public had access to the boat landing until crime and other security issues drove Xcel Energy to close the landing. The property is still being maintained as a boat landing and is used a few times each year by Xcel Energy personnel as well as Federal, State, and Local agencies for gaining access to the river. Proposed Use as Barge Staging Area: MAX TODO MARINE SERVICES INC. is seeking to utilize the Xcel Energy owned property and boat landing as a barge staging area. The proposed use as a barge staging area is depicted in Exhibit 4 and will consist of the following activities: 1) The boat landing will be used as a barge staging area during non - frozen river conditions; 2) A barge will be moored in the St. Croix River, oriented perpendicular to the shoreline, at the boat landing when not performing marine activities in the river; 3) A barge will be moored in the St. Croix River, oriented perpendicular to the shoreline, at the boat landing during periods of loading /unloading of equipment and materials; 4) Vehicle(s), excavator(s), skid loader(s), dump truck(s), a crane, and other equipment as needed to support the barge's river -based operations will be staged in the parking area; 5) Materials will be temporarily staged in the parking area during periods of barge loading /unloading; 6) Routine barge operation and maintenance will take place in the parking area and along the shoreline as needed; 7) All work associated with the barge activities will occur between 7:00 AM and 5:00 PM, unless the equipment is needed for response to an emergency (e.g. recovery of a sunken boat); 8) No bulk fuel tanks will be stored at the boat landing; and 9) No external light sources, other than vehicle and equipment lights, will be installed or otherwise used." Comprehensive Plan. The Comprehensive Plan designates this area as industrial land use. The power plant and the proposed use of the boat landing as a barge staging area are recognized as industrial land uses consistent with the maps and policies of the plan. 2 Zoning Ordinance. The site is zoned I, Industrial District in which power plants and marine service operations are a permitted use. The amended CUP is required to allow the expanded use of the boat landing area in the River Impact District. The Max Todo Marine Services business would be considered as an Interim Use of the boat landing area. As such, conditions can be placed on the Max Todo business, including a limited time period of operation for this location. It is suggested that the Interim use be allowed for five years. Section 401.05. Administration — Interim Use Permits outlines the allowances and criteria for uses that are to be located on a property for a limited time period. Parking and Traffic. The facility is to be located on the existing access roadway within the Xcel property. The access roadway connects to the main entrance road to the Allen S. King plant. Lighting. The facility is not proposed to be lit. Any new lighting of the site will need to be in compliance with the Zoning Ordinance and subject to review and approval of City staff. Trees /Screening. The pictures taken last fall of the site and attached indicate that the area surrounding the site is heavily wooded. There are no other uses or properties that are impacted by this request, so additional screening is not required. The applicant should position equipment to be stored on the property in such as way as it is less visible from the river. Grading and Drainage. Any grading and drainage issues shall be addressed subject to review and approval of the City Engineer and the applicable watershed district. From the pictures taken last year, it appears as though there could be potential run off from exposed areas into the St Croix River. Proper measures such as silt fence or a vegetated area next to the shoreline should be created to minimize soil run off into the river. Department of Natural Resources. The Department of Natural Resources (DNR) has been notified of the request. Molly Shodeen, the Area Hydrologist of the DNR indicated that she had no issues with the request. Design Guidelines. There are no structures proposed for the marine services business. Conditional Use Permit — River Impact District. The use of the boat landing as a barge staging area is subject to an amended CUP under the River Impact District. The Planning Commission should consider the conformity, environmental issues and impacts of the proposed project in making its recommendation. The conditional use permit criteria, found in Section 401.03.A.7 of the Zoning Ordinance, are found as follows: 3 1. Relationship to the specific policies and provisions of the municipal comprehensive plan. 2. The conformity with present and future land uses in the area. 3. The environmental issues and geographic area involved. 4. Whether the use will tend to or actually depreciate the area in which it is proposed. 5. The impact on character of the surrounding area. 6. The demonstrated need for such use. 7. Traffic generation by the use in relation to capabilities of streets serving the property. 8. The impact upon existing public services and facilities including parks, schools, streets, and utilities, and the City's service capacity. 9. The proposed use's conformity with all performance standards contained herein (i.e., parking, loading, noise, etc.). Due to the location of the boat landing in an industrial area, and the fact that it has been used as a landing for a number of years, City Staff recognizes no issue with the expanded use for the marine services business. The Max Todo Marine Services business will also be subject to an Interim Use in which specific conditions will be placed on its operation. Interim Use. Section 401.05.0 of the Interim Use Permit Section specifies a number of criteria for the review and approval of a use. A review of those criteria are as follows: 2. New Uses. a. Conforms to all zoning regulations as otherwise applicable. The use will be required to comply with all other Zoning Ordinance performance and use standards b. The date or event that will terminate the use can be identified with certainty. The use will be allowed to continue for five years from the date of City Council approval. c. The existence of the use will not impose additional costs on the public if it is necessary for the public to take the property in the future. There should be no issues with public costs. d. The user agrees to any conditions that the City Council deems appropriate for permission of the use. The applicant will be required to agree to the conditions in writing. 4 CONCLUSION AND RECOMMENDATION Based upon the preceding review, City staff recommends approval of the CUP and Interim Use Permit to allow for the marine services business to utilize the existing boat landing on the Xcel property subject to the following conditions: 1. The Interim Use of the site by Max Todo Marine Services shall be limited to five years from the date of City Council approval. The applicant may request an extension of the Interim Use Permit by the City Council prior to its expiration. 2. Any freestanding lighting placed on the site shall be in compliance with the Zoning Ordinance and subject to review and approval of City staff. 3. The applicant shall take measures to minimize soil run off into the St Croix River. A soil erosion plan or any grading and drainage plans for the site shall be subject to review and approval of the City Engineer. 4. The City will not require conformance with the Design Guidelines for the project. 5. The applicant shall position equipment and materials stored on the property in such a way as to reduce its visibility from the St Croix River. 6. All work associated with the barge activities will occur between 7:00 AM and 5:00 PM, unless the equipment is needed for response to an emergency such as recovery of a sunken boat. 7. No bulk fuel tanks will be stored at the boat landing. 8. The plans are subject to review and approval of the Department of Natural Resources and any other state or federal regulating agency, if applicable. 5 el") Xcel Energy - 1103 King Plant Road Bayport, Minnesota 55003 -1000 April 27 2011 Eric A. Johnson City Administrator 14168 Oak Park Blvd N. P.O. Box 2007 Oak Park Heights, MN 55082 RE: Conditional Use Permit (CUP) Amendment for the Allen S. King Generating Plant — Proposed Use of Boat Landing as Barge Staging Area Dear Mr. Johnson, Please find 3 copies of an application to amend the existing Conditional Use Permit for Xcel Energy's Allen S. King Generating Plant (King). MAX TODO MARINE SERVICES INC., the applicant, is seeking to utilize the Xcel Energy owned boat landing north of King as a barge parking /staging area. A fact sheet describing the activities associated with the proposed use as a barge staging area is included as part of the application. In addition, figures of the boat landing and staging area are included to provide further clarification. If you have any questions regarding this application, please contact me at 651- 731 -5733. Sincerely, P 71/1^- Darren Kearney Environmental Analyst Xcel Energy Enclosures cc: Tom Huninghake (MAX TODO MARINE SERVICES, INC.) Dan Flood (A.S. King Plant) Tom Smith (A.S. King Plant) w/o encl. Brian Behm (A.S. King Plant) w/o encl. Randy Capra (A.S. King Plant) w/o encl. EXHIBIT 1 Fact Sheet for a Proposed Barge Staging Area at Xcel Energy's Boat Landing Background: Xcel Energy is the owner of property north of the Allen S. King Generating Plant (King) that is zoned for industrial use and is currently developed as a boat landing (Figure 1). The boat landing consists of a —900 foot access road (off of a King Plant maintained road) to the St. Croix River. Further, the landing has a —75 foot by —125 foot parking area/turn- around located approximately 125 feet back from the shoreline. In the past, the public had access to the boat landing until crime and other security issues drove Xcel Energy to close the landing. The property is still being maintained as a boat landing and is used a few times each year by Xcel Energy personnel as well as Federal, State, and Local agencies for gaining access to the river. Proposed Use as Barge Staging Area: MAX TODO MARINE SERVICES INC. is seeking to utilize the Xcel Energy owned property and boat landing as a barge staging area. The proposed use as a barge staging area is depicted in Figure 2 and will consist of the following activities: 1) The boat landing will be used as a barge staging area during non - frozen river conditions; 2) A barge will be moored in the St. Croix River, oriented perpendicular to the shoreline, at the boat landing when not performing marine activities in the river; 3) A barge will be moored in the St. Croix River, oriented perpendicular to the shoreline, at the boat landing during periods of loading /unloading of equipment and materials; 4) Vehicle(s), excavator(s), skid loader(s), dump truck(s), a crane, and other equipment as needed to support the barge's river -based operations will be staged in the parking area; 5) Materials will be temporarily staged in the parking area during periods of barge loading /unloading; 6) Routine barge operation and maintenance will take place in the parking area and along the shoreline as needed; 7) All work associated with the barge activities will occur between 7:00 AM and 5:00 PM, unless the equipment is needed for response to an emergency (e.g. recovery of a sunken boat); 8) No bulk fuel tanks will be stored at the boat landing; and 9) No external light sources, other than vehicle and equipment lights, will be installed or otherwise used. Conditional Use Permit Amendment: Given the fact that Xcel Energy is owner of the property that the proposed barge staging area will be located on and also the fact that the property is immediately adjacent to King Plant property, MAX TODO MARINE SERVICES INC. is submitting an application to amend King's Conditional Use Permit in order to allow the activities set forth in this fact sheet. Other Permitting Needs: MAX TODO MARINE SERVICES INC. is responsible for obtaining all other required permits /approvals needed to operate a barge staging area at the Xcel Energy boat landing (e.g. Army Corps of Engineers, Dept. of Natural Resources, etc...). EXHIBIT 2 EXHIBIT 3 Figure 1. Allen S. King Plant Property Layout Wastewater Treatment Plant ,° • ; Note: Figure 2 provides deta plan 1 it ,yam ' '_ . i for area shaded in yellow i ce . � A�G a ° d Pt k' °3 ys. l'.!,',.',:::-_,1:1, ° S* �! 4° -- s ��» \\ A s a �a z scars s • `:' pp. - A 'n aah 8:m 5mae�'�' r . Y ,! £ .. 1 A ' # a , a ' "y Y t > ^a a s � : , y • x � ,.q • 1 . " ' � s"za Sr mg s y eE � s� ,�,� s zn tom $ y m - p $ ', 3 2 x , � `i a� �.. �a ' r '�' 'cs,c.k � � &�� i<a i"r i 1 t 'z' a S 1 bit ►.9� ,.. a� r _ rt a� S a € 2t • �` 3 �" \1 a ge s .,' °y r ..mot ; t ` . ° ' *` ' F o - -* + S e ' � '" Daltech 4- ' : * 4t.' . ,fi x »" , • . ''. A -- e ..7,4.1 it :49. ,, °. t , a . "� o m ''',ti \\' 2'4: w �. s ', r s � J ► i� r� x = 9 p , �rct ' 1) ` '' '''',,:, ' "4 � yr: ,: � __----,.-,....-c- ...4 - 'sw`� _ F• , ' 0 -r d row i.+�r a *an* . -may' s F *91 �° v ,t ,\ w. F igu re 2. Proposed Barge Stag Area (Clos - up) JP u s , _,+5`'' y ,Lr , w x . ' x r , A ' 1 � � Proposed B ;� �, � �� � A - � ��� �'�~�. � � ��a � �` _ � ' ' :',..',A, � St aging Area M y A- . ' , T °4 d- a , 3' Y Y t �. 414 1:‘ ?1.. t c fi b. - Yk fi, '..44,4"°4414 xxwx T ' *4 -, a `+ ff' .0. * " x ' x 5 d 'wt ' . <� , fit a s _ g , x ' #`" • a .• + ° " ' :'r * ` ' "',a . r# " \ � `k ,a � , l „ ''''..).7 A '.s r s " ` � a . ` '"ati ,f y ' '� �' r� i ,. �'t�t ‘;',....."'"*A . ' a :°3+ E fg � t • ra ' g ,. * , nr t r % �` t�• "� �� ° 'Y "tt ;� � „� '� a � - a r t -� � � •3. f' a .F r: # t t F . . � �" t _ - / � - j ,. %.4..,: c - t ., - ,s °, > .. x. . `, -: Y w . :; . " +,.' b`IY „ " mod. , •: &' u 9 ' a, `5 ;: s. 4, . — ,a, .,..: :✓'t`r," +^ < . ; y , _ <r`d a„ k e` 8 y W t ° ✓! d ,x P'; '1r ° .y , ,.,: s8 't ;«" ; :. » • . ^ . enn . �x r#' ;r# t ' §8'- . - aw " I . , . - , .. . ° '."a . '`, "`: fit t '; - �„* k . ># ti. 1 ' „,,: i.... , ..,:::::;,..,: : - a , . ; , � ', , '�, ,� � tea:' , � , . � ^ ,r �, f°�. ,, .: t ° � :. ;��r. r , �r a ... -. ? , ..� + , '= . � s ^' •a # , �,, a , y e;,. ' , .�, .:—.11,., y ea ` ` - ar,. � i. ' - r ;.P ,c -.,: _` . -.rte. ,_ � ,. � -, -�,° �� , � ‘1';,;(' , . .n ` . x t »,,. ' 1 � ` °€ ,' a ri , -'!' s , : > . >� , F. : .,' +o- : C 'A S a ' � .r `...,..,.7.''1: . * a i r# �1 � `i/ s a „,,,-9e. jym \N"".. i - �4` + ` ' ' u e -- : "� • ..' � .' ' ,I. , 4,' - *, , t ' .. � yy * `s:�k` 3 � ” P t 1 # 3�' : s :- 1 ,, m... . r M x; .-i.,"'''''.‘ _ '� w ' '1 '::° <, , An y . a ,,- - - � • ° , , : , ;� ,. i; +S ^' ' r ' .., ' 6a ^ . , 1's i`' . a . y � nom , ., « p } < $ .; a '� � ?a ^ R «,< a .ax � �,� r � y :. , . +. :. .. +. 4' x 9"° 1:: i.. Fl ; ffe r"`w � . �" ae'� a , v�'A 4 , I - +' 1 ( .` 3 ;�''. , , ' b +t ti^ _ ,.. . . , . w 'zR; *�C,.. 'r , , k m #`- , to ai , ;:., r r : a x .: A. , s Y .. . <, ' , *t "* _ � ,i -�. � '+ }' . ? f ` � � . N t r q , � > ; $ ,�� # %. , ,. ,,, . , , . , , . : ' 4 Exis Ac es Ft� , �� _ „:,„...,,, *. m, . " r ' - _ .. ms'''s... yam - r , ”, , r . �a r ' t - >r,„ 4x t " x s " y c' ' L �� % w 5, � ,y - a , s ,..., .., ,� 1 5 R / R ° � 4 ° A , „, , Y , ,¢, ' -� ,� ..:,,,,,.\,,..,,,,,z ' , X43 • ' � ,. -.., , #". ., , .- .. ' .,+p,' 9 � g . N.. . , » ' + dt• r'� ,g ' - t,, ... , F ti .. %,<� y f < V+,+ MM � " .� � _ n y .. ;. ..: %g» E M.. k� '.yu i� '� 14.'' . ^ . 4 y a:: �.. Al :. ^ `. . -. J .,, A' . . , e . -'... '�` ,9 4 g =. 1. ° »�- ,:. ' n • + 2� , 4 ... .£ Y . x V .. n.. . , F, � r : : , ;. . ';..., .,. ,. ,. ? + '• { . F S,r ";4' ^A � , . .. „' ; _ . .. ,_ :.. + - >C- �._ S.< . ,.. . ., .y c , .,... .. �:.. _ems- , ' +� � ,, i ' - at �t . ... ,'. ..-.- , : ,. - .. -.F; , a r , a •� ,,iii '�' ,...... �' k^. .^f e �,1' >.� 6 .: -. . s ..t t v w.� -. k w, * .. ''''' : : c a ~ ti ,: < x , r ,,. ', "sda X$ +, €.' r �[ f a , 1. . ..... a+', � , ... . „ . . . R . . 1. .� ..: i :. , 5 :: -.:.. ..; . c »^ »' ... 'N . # ,. ' , i',. - fir „ � ° ” i . � ° r, . . . . , ' . � ,. � '', s.. . ' ,��, 3A= "'R t < 2 , L�x'i �, +. � . : : ,,,,..///' , s s. � ,' p:,:. p' i€• T � ' sit � � ' : r �; -� - �. ....„-#:.:. q� r� ''. ,,,,-- . .. #,. c , v ,,,\ 2t*,,,,, .. ... 4:- # s 1 k , :' �a' 3, dr' 7r7r.',.'k, /:,, l tio1/4 k w ...,,-,.., ,, ' ...... . ....-.,,,,,,.„--:7-.' ' += __ r +t . # � j t �. fi + 4 z t h ,. ` 4 4 Y 1 gd r olo f -' .«a .. . r' a # . ` R r- / ' . �,S kt z: . k . y' ' -g r/ _ � 5J } EXHIBIT 5 ',Ai 4X i x t7 " ' r 7 ,Jr tJ r! y ' A et' 1 .1y ; 1.* } + ix ' , µ ," ��� 4. ` t ' r # 4 ' '# " '�l SS }.° t l A ,_,_ y " � ±.Y s€ ' + r t ' ��" ; !YY 'cif /, i:*'''''',,...'.. '---31,'"'''''' l'iii.V.,;40,,,,.., ' ..4 ' ' .' i'. ,....);.;.%). •. ' ' '‘..t ,Ilit.'".i.,' i , iii f`." ' . ' ,...,..; ..,„ !!`„ :,..-A.,,'',...„44 xf 4 t .,, , -,, it.: . „, a- .;',1',..1;:,', F I. � ia " g t tM EFn #r .,,444 g * i t ¢fit , a. i i� ' i } j 1 a, r , g , ? d �� yt '` � yk 4 �'� d 4 ii ‘:!A • ,& �', ' 1. 4 ' '. a _ _ _ . i W r7 �g �v i,� v j r '4i1 + N r s fX .. i. v N 's ai;,. fix! i f.,: •'!. _ • r , i ... i . < #''1t `mot`,? , ,°* x t ,,is.,,.,.-ititi.1.14.4.!., ' v.... ',.,-, . T IN am 'i - ,1/46.. ' G f' P.; :N Cf4 �� 4tar / Max Tod() Marine Services Inc. 651.351.9079 C CAT