2007-05-18 Finance Dept. Email Re Collection of Connection Charges
Julie, Judy Judy: R From: Judy Holst Sent: Friday, May 18, 2007 10:08 AM To: Julie Hultman Subject: FW: Manley Commercial - Oak Park Center I have calculated the connection charges based on the 1.24 acres Dennis recommends. Sewer $1,870 per acre = $2,318.80 Water $8,718 per acre = $12,050.32 Storm Sewer $7,089 per acre = $8,785.58 Total $23,134.88 1 assume this will need to be collected on the permit if we do not get the money up front. From: Pastier, Dennis M mailto: Dennis, Postler©bonestroo.com] Sent: Tuesday, May 15, 2007 10:45 AM To: Judy Holst; Julie Hultman Subject: RE: Manley Commercial - Oak Park Center The plans that I have on file from them show the site to be 1.24 acres. I would use that number as the basis for determining the area charges for all three utilities. Thanks. Dennis ry