HomeMy WebLinkAboutReport on 1999 Street Reconstruction Project, Feb 1999 File No. 55-99-100I
Report On
1999 Street Reconstruction Project
Oak Park Heights, Minnesota
• February, 1999
' File No. 55 -99 -100
Bonestroo
Rosene
WAN Anderlik &
' " Associates
Engineers & Architects
1
A MINNESOTA STAR CITY
Project Schedule
Receive Feasibility Report / Schedule March 1999
Neighborhood Meetings
Meeting with City of Stillwater April 1999
Meeting with the County April 1999
Neighborhood Meeting May 1999
Public Hearing / Order Plans June 1999
And Specifications
Approve Plans and Specifications November 1999
Open Bids December 1999
Award Project January 2000
Construction Begins Spring 2000
Substantial Construction Completed September 2000
Final Project Completion October 2000
Assessment Hearing December 2000
' JA BorestroO, Recede Anderhk and Associates. Inc. is an Afbrmabve AcnonlEqual Opportunity Employer
Bonestroo Prmopals Otto G Bonestroo, PE • Joseph C AnOerhk. PE • Marvin L. Sorvala. PE -
Richard E Turner. PE. • Glenn R Cook, PE. • Robert G. Schumcht, PE. • Jerry A Bourdon. PE
' Rosene Robert W Rosene. PE and Susan M Eberli n. CPA, Senior Consultants
MUM Anderlile & Associate Principals Howard A Sanford. PE • Keith A Gordon. PE • Robert R Pfetterle. PE
Richard T. Foster. PE David O o PE • Robert C . AJA • Mark A. Hanson, PE
M h rd T. Ra t P P R E • T
0 K.leld. Told. P PE Ken Robe P Andersoderson. P • Mark R RoHS, PE
A ssociates Sidney P Williamson. PE LS • Robert F Kotsmieh • Agnes M Ring • Michael P Rau, PE
t Allan Rick Schmidt, PE
Engineers & Architects Ochres. St. Paul Rochester, Willmar and St Cloud MN • Milwaukee. WI
Webslte: www. boneStroo Cam
1
' February 11, 1999
' Honorable Mayor and City Council
City of Oak Park Heights
' 14168 57th Street
Oak Park Heights, MIST 55082
t Re: 1999 Street Reconstruction Project
Our File No. 55 -S9 -100
Dear Mayor and Council:
' Transmitted herewith is the feasibility report for the 1999 Street Reconstruction Project, which
includes Area D, Area E and a portion of Area B of the Comprehensive Street Plan.
' This report includes information regarding the project scope, design details, costs, and financing.
Respectfully submitted,
BONEST , RO ENE, ANDERLIK & ASSOCIATES, INC.
' Karen S. Shimon, P.E.
' I hereby certify that this report was prepared by me or
under my direct supervision and that I am a duly
' Registered Professional Engineer under the laws of
the Stat of Min e2
en S. Shimon, P.E.
1
1
Date :February 11, 1999 Reg. No. 25428
1 2335 West Highway 36 • St. Paul, MN 55113 • 651 - 636 -4600 • Fax: 651-636 -1311
Table Of Contents
Page No.
Letter of Transmittal I
Table of Contents 2
Executive Summary 3
Introduction 7
Feasibility 11
Design Recommendations 13
Assessments / Revenue 15
Project Schedule 18
Appendix A Costs
Appendix B Testing Results
Figure No.
1
Comprehensive Street Plan Areas
2
Area D Location
3
Area E Location
4
Area B Location
5
Pavement Condition Index — Area D
6
Pavement Condition Index - Area E
7
Pavement Condition Index — Area B
8
Street Life Cycle
9
Typical Street Section
10
Proposed Storm Sewer - Area D
11
Proposed Storm Sewer — Area E
12
Area D properties to be Assessed
13
Area E properties to be Assessed
14
Area B properties to be Assessed
Oak Park Heights 1999 Street Reconstruction Project 2
I
I
Executive Summary
Background
In May of 1993 the City of Oak Park Heights authorized the preparation of a Comprehensive Street
Plan to develop a street rehabilitation program for its older streets. Figure 1 identifies the areas that
were incorporated into this rehabilitation program. The program started in 1995 with the
reconstruction of Area A.
' Scope Of Study
This study focuses on the proposed 1999 pavement management project, which includes
improvements to 3.2 miles of streets in Area D, 1.3 miles of streets in Area E and 0.5 miles of streets
in Area B for a total of 5.0 miles. Figure 2 illustrates the project location and limits for Area D,
' Figure 3 illustrates the project location and limits for Area E and Figure 4 illustrates the project
location for Area B.
I
I
I
1
I
Summary of Proposed Improvements
The proposed improvements consist of the following.
• Pavement reconstruction consistent with the policies established by the 1995 reconstruction
project for District A which include:
• full depth recycling of the existing bituminous pavement (grinding it up to create aggregate
base),
• subgrade correction where necessary,
• installation of concrete curb and gutter,
• installation of concrete driveway aprons,
• paving a 3" bituminous mixture surface, and
• saw and seal bituminous wear course.
• Storm sewer improvements.
Recommended Staging of the Work
If the improvements are ordered, it is recommended that the work be accomplished under one
construction contract. The proposed schedule for bidding and execution of the work is outlined in
Oak Park Heights 1999 Street Reconstruction Project 3
I
' the report. The work is intended to be completed in the Summer of 2000.
' Summary of Costs
The following table summarizes the estimated costs of the proposed project. In Area D, Area E and
' a small portion of Area B concrete curb and gutter is proposed. The majority of Area B has existing
concrete curb and gutter (Figure 4) and therefore, it is recommended that the curb in this area be
removed and replace only where necessary. The cost for the street reconstruction has been divided
into two categories, "Areas of Proposed Concrete Curb and Gutter" and "Areas of Existing Concrete
Curb and Gutter ".
1
1
1
1
1
Summary of Estimated Costs
Areas of Proposed Concrete Curb and Gutter
Summary of Estimated Costs
Area of Existing Concrete Curb and Gutter
Construction
Construction
Total Cost
Total Cost
Cost Total
Cost per foot
per foot
Street Reconstruction
$1,737,600.00
$73.00
$2,172,100.00
$91.00
Storm Sewer
$223,100.00
$9.00
$278,900.00
$12.00
Total
$1,960,700.00
$82.00
$2,451,000.00
$103.00
Summary of Estimated Costs
Area of Existing Concrete Curb and Gutter
Oak Park Heights 1999 Street Reconstruction Project
pi
Construction
Construction
Total Cost
Total Cost
Cost Total
Cost per foot
per foot
Street Reconstruction
$137,400.00
$50.00
$171,800.00
$62.00
Storm Sewer
NA
NA
NA
NA
Total
$137,400.00
$50.00
$171,800.00
$62.00
Oak Park Heights 1999 Street Reconstruction Project
pi
I
1
i
1
' Summary of Financing Implications
1
1
Summary of Total Cost
Note: the total cost of the project does not include the cost for televising the sanitary sewer or
testing the water main for leaks. These tests are necessary to determine if any major repairs are
needed.
The following summarizes the financing implications that will result from implementing these
projects.
Revenue
Total Project Cost
Construction
Total Cost
$1,030,950
Cost Total
$85,800
Street Reconstruction - Areas of Proposed
$1,737,600.00
$2,172,100.00
Concrete Curb and Gutter
County Turnback Reimbursement
Street Reconstruction- Areas of Existing
$137,400.00
$171,800.00
Concrete Curb and Gutter
Storm Sewer
$223,100.00
$278,900.00
Total
$2,098,100.00
$2,622,800.00
Note: the total cost of the project does not include the cost for televising the sanitary sewer or
testing the water main for leaks. These tests are necessary to determine if any major repairs are
needed.
The following summarizes the financing implications that will result from implementing these
projects.
Revenue
Total Project Cost
$2,622,800
Residential Assessment Revenue (261units)
Proposed Concrete Curb and Gutter
$1,030,950
Residential Assessment Revenue (60 units)
Existing Concrete Curb and Gutter
$85,800
OPH Commercial Assessment Revenue
$108,680
Stillwater Revenue
$230,230
County Turnback Reimbursement
General Fund
$1,167,140
The following streets within Area D are bordered by properties within the Stillwater city limits:
(Assessments and City Costs)
- Panama Avenue - Paris Avenue south of Beach Road.
' Osman Avenue - 65 Street North
Ozark Avenue North - 64` Street North
- Part of Oxboro Avenue - Alley (Oxboro to Panama)
1
Oak Park Heights 1999 Street Reconstruction Project
5
I
1
1
1
1
1
11
1
1
The condition of these streets are such that they require reconstruction. Since Oak Park Heights
residents do live on one side of the road it would be appropriate for the city to attempt to arrange the
reconstruction of the street and ask the City of Stillwater to fund their half of the roadway either
through their general fund or through assessments. If the City of Stillwater decides not to fund the
project, it is recommended that these streets be removed from the project. The following
summarizes the financing implications that will result if these streets are removed.
Total Project Cost (W /O roads bordering
Stillwater)
$2,215,940
Residential Assessment Revenue (247units)
Proposed Concrete Curb and Gutter
$975,650
Residential Assessment Revenue (60 units)
Existing Concrete Curb and Gutter
$85,800
OPH Commercial Assessment Revenue
$79,280
County Tumback Reimbursement
General Fund
$1,075,210
Special Issues
Council will need to consider the information provided in this report and the information that will
be obtained from the residents at the neighborhood meetings and public hearing to decide whether
to accept the recommendations of this report or to modify the proposed project.
In essence, the project as proposed follows previous policy decisions concerning the pavement
management program and precedent set from the 1995 reconstruction project. There is, however,
one previously established policy that Council should note would not be followed under these
proposed improvements. The City's standard street width in new developments is 32 feet from face
of curb to face of curb. The previous street capital improvement plan that was adopted by council,
recommended a minimum street width of 30 feet. However, the existing streets in Area D and Area
E are only 24 feet wide. In many cases on this project it is not practical to widen the street several
feet due to existing trees, landscaping etc. Therefore, we recommend most streets in this area to be
reconstructed to a width of 28 feet.
Oak Park Heights 1999 Street Reconstruction Project 6
I
I
I
I
1
1
Introduction
Purpose
This report provides information concerning the proposed Area D, Area E and a portion of Area B
Street Reconstruction Project. Figure 1 shows a location of these areas.
Project Description
This 1999 reconstruction project includes Area D, Area E and a portion of Area B of the original
pavement management report. Area D lies north of Highway 36, south of east 65th Street, and east
of Panama Avenue as well as segments of Osman Avenue, Ozark Avenue, 64 Street, and Oxbom
Avenue. Area E lies south of Highway 36 and includes Peller Avenue, Penrose Avenue, 58 Street,
57` Street, and Perkins Avenue. The portion of Area B is east of Osgood along Upper 55 Street
North and 56 Street.
Background
The first area of the Comprehensive Street Plan included Area A, which was constructed during the
I995 season. The project described in this report will be the second rehabilitation project of the
Comprehensive Street Plan. It includes Area D as shown in Figure 1, Area E as shown in Figure 2
and the portion of Area B as shown in Figure 3.
In the fall of 1996, soil borings were performed on Paris Avenue / Beach Road. The results, shown
in Appendix C, indicate a 6" bituminous pavement and a 9" gravel base. There is much value in this
amount of bituminous and gravel because these materials can be salvaged and reused on the project.
In the spring of 1997 test holes were dug on the other residential streets in areas D and E to
determine the soil characteristics. The results, which are shown in Appendix C, indicate that sandy
clay exists below the bituminous surface. To provide support to the road, the material below the
bituminous surface should be gravel. The test holes show that the streets are good candidates for a
reclamation process, which would grind up the existing bituminous and mix it with some of the
sandy clay to create an aggregate material that would provide a solid base for the road.
Oak Park Heights 1999 Street Reconstruction Project
I
I
I
The condition of the existing pavements in Area D, Area E and Area B were last rated in 1987. For
the 1998 street reconstruction report, the computer program, Paver, was used to help predict the
ranking of the roads. These predicted rankings are shown in Appendix C and on Figure 5, Figure
' 6 and Figure 7. For Area D and Area E the average pavement condition index (PCI) for the
predicted 1998 value was 58 and for Area B the average was 47. The general life cycle of a street
' is shown in Figure 8. This figure shows that by the year 2000 the average PCI for the streets in Area
D /Area E and Area B will be 24 and 18, respectively.
' The table below presents general categories to define PCI Rankings.
I
1
Maintenance Recommended
Pavement Condition Index
Seal Coat
50 -100
Overlay
30 -60
Reconstruct
0 -40
' In general, PCI rankings below 35 require removal of the existing bituminous pavement before
' constructing a new bituminous surface. The existing aggregate base may also have to be
reconstructed. PCI rankings between 35 and 55 require bituminous surface removal or major
patching before constructing a bituminous overlay. PCI rankings over 55 typically do not require
' bituminous overlays and generally routine maintenance such as patching, crack sealing, and seal
coats are cost effective.
' The deflection testing of Area D and Area E was completed in the summer of 1997. The results of
' this test show that the majority of the streets have an adequate subgrade. The testing identified Pans,
Peabody and Ozark as streets that may need subgrade correction. Therefore, quantities and costs for
' some subgrade correction have been included in this report. In addition, the results showed that 65 d ',
64', Upper 63` 62n Paul, Peabody, Paris, Ozark, Penrose and Perkins would experience cracking
of the bituminous surface.
From Figure 8, the predicted average PCI ranks the streets in the "Reconstruct" category. The
' deflection tests showed that a majority of the streets would crack under repetitive use and several
streets actually require subrgrade correction. The test holes showed that the streets are in need of
1
a solid base. These results make it feasible to recommend the total removal of the existing
bituminous. Some streets will require removal of the existing aggregate base and subgrade
improvements as well. In Area D, Area E and a small portion of Area B concrete curb and gutter
Oak Park Heights 1999 Street Reconstruction Project 8
1
' is proposed. The majority of Area B has existing concrete curb and gutter (Figure 3) and therefore,
' it is recommended that the curb in this area be removed and replace only where necessary.
The streets included in this project are listed below along with the length and recommended width
of each street:
1
1
I
Area D
Street Name
Length
(Feet)
Existing
Street Width
( Feet)
Proposed
Street Width
(Feet)
Upper 61st Street North
1010
24
28
62nd Street North
1360
24
28
63rd Street North
1260
24
28
Upper 63rd Street North
1260
24
28
64th Street North
1260
24
28
Peacan Avenue North
700
24
24
Peabody Avenue North
400
24
24
Paris Avenue North / Beach Road
2200
24
32
Paul Avenue North
750
24
28
Panama Avenue North
1770
24
28
Paris Avenue (residential area)
975
24
28
Osman Avenue North
600
24
28
65' Street North (Beach to Peaean)
700
24
28
64` Street North Oxboro to Ozark
350
24
28
Ozark Avenue North (64 to 65')
320
24
28
Oxboro Ave. North (62 Id to Hwy 36)
1150
24
28
Alley (Oxboro to Panama)
670
24
28
Total
16,735
3.2 miles
' The italicized street names are those that are bordered by properties in the city of Stillwater. These
streets would only be reconstructed if an agreement can be reached with Stillwater to pay for the cost
of half of the roadway.
1
1
Oak Park Heights 1999 Street Reconstruction Project
2
I
1
I
1
F
1
1
1
I
Area E
Street Name
Length
(Feet)
Existing
Street Width
eet
Proposed
Street Width
Feet)
Peller Avenue North (56 to 59)
1350
24
28
Penrose Avenue North (56 to 59)
1350
22.5
28
Penfield Avenue
560
18
18*
56 Street North (Penrose to Peller )
370
24
28
Upper 56` Street North
220
24
28
57 Street North (Peller to Penfield)
830
24
28
58 Street North (Stagecoach to Peller)
990
23
28
Perkins Avenue North (56 to 57)
650
18
18*
57 (west of Perkins)
330
20.5
24
Total
6650
(1.3 miles)
"UU w we ,ucauon ui exrsimg ouuamgs, the maximum allowable street width is 18 feet.
Lyme
Street Name
Length
(Feet)
Existing
Street Width
(F eet)
Proposed
Street Width
(Feet
Ozark
660
32
32
Upper 55` Street
550
32
32
56' Steel
1150
32
32
56' Street Circle
400
32
32
Total
2760
0.5 miles)
Oak Park Heights 1999 Street Reconstruction Project
10
1
Feasibility
The 1998 Reconstruction Project is feasible. The following table summarizes the estimated costs
of the proposed projects. The cost for the street reconstruction has been divided into two
categories, "Areas of Proposed Concrete Curb and Gutter" and "Areas of Existing Concrete Curb
and Gutter ".
Summary of Estimated Costs
Areas of Proposed Concrete Curb and Gutter
Summary of Estimated Costs
Area of Existing Concrete Curb and Gutter
Construction
Construction
Total Cost
Total Cost
Cost Total
Cost per foot
per foot
Street Reconstruction
$1,737,600.00
$73.00
$2,172,100.00
$91.00
Storm Sewer
$223,100.00
$9.00
$278,900.00
$12.00
Total
$1,960,700.00
$82.00
$2,451,000.00
$103.00
Summary of Estimated Costs
Area of Existing Concrete Curb and Gutter
Summary of Total Cost
Construction
Construction
Total Cost
Total Cost
Cost Total
Cost per foot
per foot
Street Reconstruction
$137,400.00
$50.00
$171,800.00
$62.00
Storm Sewer
NA
NA
NA
NA
Total
$137,400.00
$50.00
$171,800.00
$62.00
Summary of Total Cost
Oak Park Heights 1999 Street Reconstruction Project 11
Construction
Total Cost
Cost Total
Street Reconstruction - Areas of Proposed
Concrete Curb and Gutter
$1,737,600.00
$2,172,100.00
Street Reconstruction- Areas of Existing
Concrete Curb and Gutter
$137,400.00
$171,800.00
Storm Sewer
$223,100.00
$278,900.00
Total
$2,098,100.00
$2,622,800.00
Oak Park Heights 1999 Street Reconstruction Project 11
I
1
1
I
1
1
1
I
I
1
At the time the 1993 Comprehensive Street Plan was prepared the fate of Paris Avenue/Beach
Road was not certain. However, it is now the intention of the county to negotiate the tumback of
this roadway to the city. As a part of this negotiation, an agreement will have to be reached
regarding the amount of money the county will reimburse the city for the reconstruction of this
street. It is important that Paris Avenue / Beach Road is reconstructed at the same time as the
rest of the residential streets in Area D. Most residential streets in this area intersect this
roadway, and the reconstruction of these intersections in conjunction with the rest of the streets
will allow the new design to correct drainage problems. Also the residential streets can be
designed to correctly tie into Paris Avenue / Beach Road which does not have curb and gutter but
will have concrete curb and gutter when it is reconstructed. An additional benefit to
reconstructing these roadways at the same time is the excess ground up bituminous material from
Paris Avenue / Beach Road can be used as aggregate base on other residential streets.
Oak Park Heights 1999 Street Reconstruction Project 12
I
Design Recommendations
' The following are the design standards recommended for this project.
' Street Section: In the areas of proposed concrete curb and gutter the existing bituminous surface
would be reclaimed (ground up) and recycled by using it as an aggregate base. Three inches of
' new bituminous would then be placed over an average aggregate base depth of 8 inches. In the
areas of existing concrete curb and gutter the existing bituminous would be reclaimed and
recycled. Four inches of new bituminous would then be place over an average aggregate base
' depth of 6 inches. Even though these two street sections are different, the strength of the roads
are equivalent. These two street sections are illustrated in Figure 10.
' Street Width: The existing streets in Area D and Area E are 24' wide and 32' in Area B. The
city's standard street width is 32', and the streets in Area A were reconstructed to this width.
However, several of the streets in Area D have mature trees in close proximity to the street.
' Widening the street to 32' would require the removal of some of the trees and landscaping.
Therefore, it is recommended that the majority of the streets be widened only to a width of 28'.
This would provide for a minimum of an 8 foot parking lane on both sides of the road and a 12
' foot driving lane.
Street Surface: Saw and seal the new bituminous wear course. This procedure extends the life
' of the street section by reducing the moisture that penetrates the surface and causes the
deterioration of the bituminous material.
Curb: In Area D and Area E curb will be concrete barrier curb (MNDOT B618). In Area B the
curb will be surmountable curb to match the existing curb.
' Storm Sewer: It is recommended that new storm sewer be installed where it will eliminate
existing drainage problems and prolong pavement life by reducing ponding on the pavement
' surface. Figure 10 shows the proposed storm sewer for Area D. The proposed storm sewer in
Area E is shown in Figure 11. The existing storm sewer castings in each area will be updated to
meet current standards.
' Driveways: All existing driveways will have concrete aprons installed.
1
1
Oak Park Heights 1999 Street Reconstruction Project 13
1
Existing Utilities
' Sanitary Sewer: The sanitary lines will be televised during the plan and specification phase of
this project. The condition of the existing lines will not be known until that report is received.
Water Main: Leak tests will be performed on the existing system to determine the condition of
the existing lines.
' Storm Sewer: Visual inspections will be done on the existing system to determine if any repairs
need to be made. Only minor repairs and casting replacement is anticipated at this time.
1
1
1
1
1
1
1
Oak Park Heights 1999 Street Reconstruction Project
14
1
I
1 - --
1
I
1
1
1
1
1
1
I
1
Assessments / Revenue
The assessment policy as established by the city council for the 1995 Reconstruction Project was
based on the following:
• Each residential property will be assessed the same amount
• This amount is based on the amount to be paid by the average size lot on this project
• Commercial properties will be assessed on a front footage basis
A new policy that is presented in this report is that the city of Stillwater should pay for half of the
cost of the streets that abut properties that lie within Stillwater city limits.
The assessment amounts are as follows:
Residential PropeE gh
Proposed Concreutter
Eakar rk Heits
$3,950 / each `� 41
a � Qp/jV1 � X1
Residential Propek Heights
Existing Concrettter
$1,430 /each
Commercial Property in Oak Park Heights
$56.00/ front foot
Stillwater Properties
$51.50/ front foot
The figures above were calculated using the following rate schedule, which was established in the
1993 Comprehensive Street Plan.
Assessments Rate Classifications
Residential Curb (75% of total Curb Cost)
Commerical/Industrial Curb (75% of total Curb Cost)
Residential Street (50% of total Street Costs)
Commercial/Industrial Street (50% of total Street Costs)
Oak Park Heights 1999 Street Reconstruction Project
15
0
1
The total assessments for the project are as follows:
' Oak Park Heights Commercial Property Assessments
1
C
1
1
1
Property
Assessable
Footage
Assessment
St Croix Villas Condos
1087
$60,800 ($2,029 per unit)
Church
330
$18,480
Orchard Park Condos
165
$9,240
Oak Park Heights Garden
360
$20,160
Total
135
$108,680
City of Stillwater Revenue
Property
Assessable Footage
Amount
2 houses on W Street
298
$15,340
HSI Washington Count
330
$16,990
School
630
$32,440
House — 6282 Panama
165
$8,500
Church
135
$6,950
School
330
$16,990
Washington County Correctional Facility
555
$28,580
Washington Count Building
1500
$77,250
4 houses on 65 Street
528
$27,190
TOTAL
$230,230
' Oak Park Heights 1999 Street Reconstruction Project
1
I
1
1
The total project revenue is shown below:
Revenue
1
1
Total Project Cost
$2,622,800
Residential Assessment Revenue (261units)
Proposed Concrete Curb and Gutter
$1,030,950
Residential Assessment Revenue (60 units)
Existing Concrete Curb and Gutter
$85,800
OPH Commercial Assessment Revenue
$108,680
Stillwater Revenue
$230,230
County Tumback Reimbursement
?
General Fund
$1,167,140
' As is shown, the burden on the general fund would be approximately $1.2 million. This burden on
the General Fund would be reduced with the turnback agreement for Paris Avenue/Beach Road.
1
1
1
r-
Oak Park Heights 1999 Street Reconstruction Project
17
1
Project Schedule
Receive Feasibility Report / Schedule
Neighborhood Meetings
Meeting with the City of Stillwater
Meeting with the County
Neighborhood Meeting
Public Hearing / Order Plans
and Specifications
Approve Plans and Specifications
Open Bids
Award project
Construction Begins
Substantial Construction Completed
Final Project Completion
Assessment Hearing
February 1999
March 1999
March 1999
April 1999
May 1999
September 1999
October 1999
November 1999
�p w�U
y 2000
September 2000
October 2000
e
� : �: .111 •�'
Oak Park Heights 1999 Street Reconstruction Project 18
I
1
I
I
1
W
( -(n
(n
N
NOO
NO�OOr
U)
co
N
O
a0
'
U
cn
nO
co
'
ID
co
cn
O
U
O
C
r
r
C
n
'
^�
CL
C
v!
r
X
N
1
C
C
Q
a)
Q
m
Q
n
Q
M
1
1
I
1
v
c0'ITN
( -(n
(n
N
NOO
NO�OOr
co
N
c0
N10
a0
W
anN
nO
co
ID
co
O
C
r
r
r
n
a0
O)
r
r
a0
N
1n
N
V
m
I'
n
M
w
w
w
o
m,
m
m
M�
N
V
N
O)
N
r
N
O)
N
r
r
r
N
M
O
O
(D
00
In
(D
M
N
O
OD
N
U d '
V)
60
vi
6n
(n
to
,
(n
yr
ca
(0)
WW
n
r
N
w
O
F
.
7
r
(O
(0
(0
O
O
CO
N
CO
C
cO
V
n
N
I�
m
t0
c
N
a
N
N
N
m
W
N
N
l0
m
m
m
co
V
OO
O
O
CO
r
r
r
N
OD
m
.-
.
OD
N
l0
N
V
m
n
I-
m
C7
Ifi
(0
(0
O
N
CO
0)
M
m
LO
<t
N
(3)
LO
(A
m
N
.-
.-
l0
M
O
fD
(O
W
l0
(0
M
N
O
O
N
ff)
fA
Vf
N
f9
E9
CA
617
V3
VD
69
Ln
fA
ffi
(A
-
C_
64
E
U
c
LL
ro
m
co
(o
0,0
m
0
o
m
co
co
cD
(,D
m
m
'D
m
m
o - -
•-•-,-
•-
n
r�
m
�
�
r
r
r
�
r
r
N
L
V9
�
%U4
w
00)
6
(a
�09
�69
�69
�es
�
�
I
(D
M
I-
O
O
00
a
N
M
a
O
OM
M
m
N
0
n
a 0
M
M
r
[p7
O
O
p
m
m
m
m
N
It
N
m
m
m
CO
(0
.-
N
N
W
N
(O
01
(0
1�
M
OD
C
V
O
N
N
N
V
(Ci
(7
u)
O
V
L0
M
•1
CA
(`1
N
h
O
m
m
m114
N
(D
V)
M
n
V
N
N
N
CD
V
N
y
(a
-
(A
6%
to
69
60
,
EA
,
Qf
69
69
69
69
%
64
N
c
c
U
E5
U
0
O
+
M
M
M
M
M
O
tD
uJ
M
M
M
M
M
M
M
M
M
�
C
M
M
M
M
M
M
M
V
M
M
M
M
m
M
M
M
M
O
0
n
69
n
C9
n
61)
r
U)
n
fR
(D
fR
O(
V9E9fAV)69
Rf»6
n
n
f>
r
r
P^
64
n
6%
fl9
60
6 n
O
U
co
w
w
m
w
d'
't
N
w
w
M
OD
00
07
OD
OD
O]
N
N
Cl)
N
N
N
N
M
N
N
N
N
N
N
(V
N
N
L
N
LL
O
O
O
O
O
O
O
O
0
0
(0
0
0
0
0
O
10
L
O
(D
co
CO
N
(D
N
(D
N
O
n
O
V
O
N
LO
f�
n
r
n
m
0
O
0
n
(0
Cl)
N
M
LO
'
r
(D
M
I�
c N
N
I 'D
D
O) LL
_J
O
M
c
co
Y
co
p
N
)0
=
p[
m
)
O
to
0
L
N
c o
YO
O
O
O
c
L
co
5
U
O
O
L
V
m
E
C
O
'C
O
t
C
M
L
r
c
L
X
L
(O
Z
Z
o
Z
t
Z
a
o
m
0
r
o
c
s
L
O)
L
Z
Ql
r
0
L
r
m
Z
p
Z
d
`)
O
o
o
n
c
Z
0(D
N
r
Z
O
O)
C0
ZZ
C
d
o
d
N
C
Z
Z
c
Q
Q
c
C>
�
z
D
N
d
M
N>
d
Q
>
c
w
Q
m
>
Q
Z
a)
o>
N>
Q
d
x
in
O
Cn
c_0
m
oQQ
>
EQ
c
�ininx
Q
o
0
h
T c
C
O
p
L
N
N
c
7
c
'
E
L
Y
N-0
d
N
in
CL
D
N
Dto�(DaD_D_dD_D_0(D(D000
M
V
O)
O1
N
m
O3
Co
0
(n
v
(^l
X=
O
F
1
I
I
1
I
1
1
1
1
U)
Of
r
O
W
rn
U)
to
'
O
U
�
r
r
r
0
r
'
m
c
0
E
O
et
�
r
N
'Q
LL
VJ
r.7
Q
m
'
X
co
N
w
i
r
C
Q
W
C
Q
f
W
Q
In
O
Q
r
1
I
1
1
1
1
1
Of
Of
r
O
W
rn
r
to
r
c0
r
r
r
0
r
O
0
0
O
et
r
N
'Q
N
O
r.7
m
y
e
v
r
v
O
W
f
W
In
O
T
r
CO
G%tO&!
ST
A to
m
LO
U
(4(o
tr,
0
0
F
v
rn
rn
m
m
C
O
n
O
V
Cl)
O
O
a
m
N
V
N
O
M
m
m
N
N
N
V
u7
C]
m
N
O
orj
(f)
E9
f9
(fl
H)
6
f»
M
H3
fH
H}
C
E
0
Q
U
0
c
LL1
m
d
—
m
m
m
m
m
m
m
m
o
o
cl
r
N�
m m mm
mm
cm
m
L
O
f9
[9
f9
f9
f9
69
ca
t9
E9
U
m
m
C
N
m
T
N�V
U
LO
�
N
N
N
m
m
C
h
N
n
r
N
0
U
0
U
I R
O
M
m
,
,
(h
D
O
a
rr-r`t
rlr�mr�
0
y
co
nr-
ofm of
rl-
r-
m0
r-
r-
of
r-
r;
LO
of
m
U
U
F9
b9
EA
EA
fR
f9
fA
f9
E9
m
m
m
m
m
m
m
m
It
N
N
N
N
N
N
N
L N
a m
ILL
000000000
C
L
N
m
WIN
N
m
m
N
M
LO
m
OJ w
J
N
L
N
L
L_
N
N
N
d
O
O
0
d
C
N
O
O
L
CL
U
co
L
L
O
O
O
O
D
LO
w
Q
L
N
In
lA
L
C
tf
—
YC
L
t�
L
O
fl
z
6-
(n
O
Y
z
j
U1
D
N
N
z(nzz
a
c
O
E
>
>
t
>
cu
>¢¢
drn
d
m¢
a`�i
z
¢
a
v
rn
3
p
m
c
m
N
C
C
L
L
L
Y
L
CS
CL
U)
ma-
CL
Sri�d
r
F
1
I
1
1
1
1
1
1
1
I
v
O
rr
v
(n
' O
U
M
0
Co
T
' czU
c
CO
E
N
�
O
N
' ^L
LL
''
VJ
Q
m
' X
cz
C
Q
Q
N
W?
Q
(O
1
1
1
I
v
O
rr
v
(n
LO
0
Co
T
aT
CO
N
PJ
O
N
(O
t0
O
N
W?
(O
n
N
O
O
49
44
(a
fA
to
U
�
N
�
0
O
H
'IT
0nvLn
O
C
M
O
LO
O
O
N
m
O
-
V
V
00
V
V
Cl)
I-
N
KS
(9
(9
(a
V3
(9
N
(9
c_
E
m
Q
U
c
W
m
m
—
m
O
N
o
LO
N
N
N
N
N
N
a
N
O)
N
(D
(D
(D
N
(D
O
E9
(9
(a
UA
(9
U
(O
(O
V
(D
co
O
Omco(v_m
v
m
M
N
N
V)
m
n
v3
(9
(»
(9
(9
a
5
c
U
0
U
0
O
+
u1
r
r
n
r
n
r
C
C
m
0
D
W
O
4
CG
U
U
f
699
V4
N
N
N
N
N
co
m
(7
(7
CO
L �
W
00000
t
O(D
UO (OO
N
(n
O
LO
r
a
C
LL
L
J
9
U
C
N
X
O
O
Z
d
N
O
d
N
a
c
Z
LO
m
-
N
N
N
Y
(n
Cn
4l
N
O
N
L
L
N
1
i
1
1
1
1
1
1
1 °
7
Q
1 X cn
C
CL
Q
1 Q
Q ,
cn
cn
O
1
1
1
1
1
1
1
1
V)
O
U
000000
000000
y
Of
N
C9
CY
Ln
IA
OD
N
y
1 n
_
N
V!
M
w
69
fg
N
(A
/O
N
o
U�
0
H
a
C
O
m
C
0
0
<C0
C7
m
m
M
N
i
6
�
�
LA L
Cd
N
LO
LO
N
? t
3
U
d
M
O
0
0
0
m
�CC)
�r�v
O
. O
N
M
7
Qi
_�
r
o
X 616
F 3
O_
w
C
O
U
d
m
Z
E
m
O
E
a
rn
U
U
rb
SOW
LLJm
y
m
m
m
m
m
m
C
o
m
a
o
a
a
a<
a
F
I
1
1
1
1
1
1
1
1
Appendix B
Area D- Testing Results
Street Name
Soil Boring
PCI
Test Hole
1998 Predicated Value
Upper 61"
At county rd.
51
Street
5.5" Bituminous
59
North
7.5" Base
85
Fill, mostly silty sand
with little gravel
62 Street North
70
2" Oil & Rock
78
18 " -20" sandy clay
Below heavier clay
63 Street North
59
74
Upper W Street North
2.5 "Bituminous
52
2" Oil & Rock
9.5 base
70
Sandy Clay some small
Fill to 5.0' mostly silty
Rock
sand
20" Sandy clay
Below more cla
W Street North
55
2" Oil & Rock
77
18" Sandy Rocky Clay
Bigger Rock more Clay
Pecan Avenue North
68
4 -5" Oil & Rock
70
12" Sandy Clay
Below Heavier Clay
Peabody Avenue North
84
Paris Avenue North/
Range from 5.5" — 7"
16
Beach Road
Bituminous Pavement
Range from 7.5 "- 18.5"
Base
Fill mostly silty sand
Paul Avenue North
42
51
I
1
1
1
1
1
11
1
1
1
n
1
Appendix B
Area D- Testing Results
Street Name
Soil Boring
PCI
Test Hole
1998 Predicated Value
Panama Avenue North
38
3" Oil & Rock
18" Sandy Gravel
Below 18" Rocky, some
big
Paris Avenue
39
(residential area)
53
Osman Avenue North
56
5" Oil & Rock
20" Sandy Clay
Heavy Clay
Some Big Rocks
65 Street North
67
2 -3" Oil & Rock
(Beach to Pecan)
Sandy Clay
Some Bigger Rock
6 Street North
(Oxboro to Ozark)
Ozark Avenue North
58
(W to 65'")
Oxboro Avenue North
5" Oil & Rock
(62 to Hwy 36)
20" Sandy Clay
Heavy Clay
Some Big Rock
Alley
(Oxboro to Panama)
I
I
1
[1
1
1
1
1
Appendix B
Area E- Testing Results
Street Name
Soil Boring
PCI
Test Hole
1998 Predicated Value
Peller Avenue North
59
2 -3" Mix
(56" to 59'")
81
Rocky, Sandy Clay
63
Penrose Avenue North
56
2 -3"
(56" to 59
73
12" Sandy Clay
72
Heavier Clay More
Rock
Penfield Avenue
32
56
56 Street North
56
3 -3.5"
(Penrose to Peller)
Big Rocks
12" Sandy Clay
Heavier Clay
Upper 5& Street No.
55
57 Street North
55
(Peller to Penfield)
58 Street North
84
(Stagecoach to Peller)
54
71
Perkins Avenue North
23
4 -5" (2 Lifts)
(56" to 57")
42
Big Rock Limestone
57' (west of Perkins)
87
N
i
0 750 15 00
STREET AREAS
OAK PARK HEIGHTS, MINNESOTA FIGURE 1
COMPERHENSIVE STREET PLAN
K: \55 \55134 \55134F08 FEB 1999 COMM. 55134
JA Sonestroo
0 Rosene
Anderlik 6
Associates
O d
O u
U
C mU m
O O c co
U]Et QQ
1 1 I
I
I l'
/J FI E
- -- --
--
- -- - - -
7
z
JZ
1
i
Z I I Q
O
U
O V)
I__________ _ ___
N 3 d
i cn
8, it
\ \ a 1
1 11 1
\ II 1
i n 1 1
I I 1 I
1 I11
1 I 1 1
I I I I
1 j I I I
I I I
I I I
I I I
I I I 1
I I '
I I I I
I I I I
I I
I I I 1
I I I I
I I I
I I I I
— I I
1 I I I
I ,I
fa
W
Q
III
Z
II
' W
'
'1 W
1 ,
O
1
I` a
W
- w
V)
0
W
N
O
a-
d
N
w
c�
H
U
W
O
Of
CL
00
0)
0)
w
w
O �
0 V)
w
.^
W
E' J
W
If
O Q Q
d 3 V)
f W J W
O -
CL O0V) J
Of 0) w
W Z
O- 0O U
M W
3
LLJ O
O D Q Of Of
of M
W
P �— �— 0)
W W W
www
P� P� f�w
V) (f) (1)0
IIIZ
I
Q
O
U)
w
Z
Z�
�
0
O
0 Q-
w �
= W
W
Y �
U)
Q 0)
O
a
M
In
N
E
u
U
m
m
m
w
0
a M LO
LO
M
LO
m m = m m m m = m = m = S � = m = w m
0 b�
O Y
U
C 0 7 m
0 O C m
m Q Q Q
LIME
a
V)
Z
w
w
O
a
w'
w
Of
V)
0
W
V)
d
M,
W
ry
L�
a
M
L
In
Z
O
U
Q
O
W
z
o
_ Of Ln
U' 0- o
VJ L M
= LL1
Y W i
� a
M
Q7 L
Y O� ,
Q O) i
O x
m m m= w m i m= m r m m m m m= m
o o OD
O Y
C U
O O O O
cm'Oco)
O O c m
m Cc Q Q
W
U'
N * :IA �NdWSO
FT
0
0
w
= Z �
a�
0
P
Q
W
Q
Z
W
W
O
d I
W
H
N
0
W
(n
d
O
a
w
H
H ~
H �
C7
m
m x
W U
D
U W
W ~
W
W a�
W C-)
U Z
Z 0
0 U
U C3
C� N
Z 0
CL
0
w d
0
0
m
m
N
N
O
V
Q
O m
� m
Z ro
? g �
0
O °
_ cr- ° o
O a �
W m
_ Lo
Y W o0
af of F rn
Q cn
a
rn i
Y 0
Q rn i
O r
m = m m m m m r m m m � m m m = = = m
o Kr
O Y
L
� C L
U
c mU CO
O O C m
En a: <
I
I
I
1
----- ----------- -
_
-- ____ --
---- -- ----- -
----------- - - ----------- - - - --
-- - -_ -
LO
IE n
I I I 1
I I I I I
L Y I 11 j
V I I I I
t'
I u l 1
LL
LLJ W I I I I
HAAN' I I I I I
I I I I
I 11 11 I I ; 1 I
I I I I I I II I
I I I I I I I I I
I 1 1 I I I I
1 1 I I I I I
i i`I i t i t �
1 I I
1 I
I I III I I I I I I I
I I I 11 I I I1II
I I I I I I A I
I 1 i; I I 1 1 I I I I I I
I I I I I I I�I
I I I I I i t Q Ld
UI i I
Ld
I L j l l i i i 1 I I
I X
U 1 Ji 1�1 \ O
P2 V$] IO2N Y S 7
N ']Ad Qoo0SO __ z
I CD I , o
W
° W
o W Q
0-
N,
N W
11
V
W
W
J
Q
J
00
O)
0)
U
0
W
d'
d
U
a-
a
M
0
0
U
O
(n
W
Z O
c Z Q�
m
V) 0 4
O
0 W
W W �
2
Y W N
Q cn
d �
rn �
Y N
Q rn
0 Y
O .6
O Y
q C L
U
C m U 0
OOCco
m[LQQ
T
W
U
L�
W
J
1
Q1
O
LLJ
H
U
w
a.
I
U
d
Im
W
i
�Z
y
M �
c
O
U
O Ll N
Q
LLJ
Q
X
C)
Z
Z
— O
O
U '
Z
W
LLJ
Q
v
M
N
N
m
0
O
U
O
U)
LL)
Z Q
Z
o
O
_ Ckf Lo
O a LL
LLJ
LLJ M
Y W
Q V) "
Y O) N
O Y
m m m r = = = == m m m r m= m
o .c co
o �_co
U
C m U w
O O C m
2]2QQ
7mmq , p,r
I ""mi O
\N 1
,N \
u
i11 11 ',
1
, I,
I
I I ,
I I I I
11
11
11
11
1l
tl
11
11
}j
rr
I; Ili + �llryl
II II I rpgr
Ill ; I
1 I
1
1 1 I I I
I I I I I
I I I I I
I I I I I
F1 I
1
�I II
I I
II ;II I I
I , II II
1 I I I
I I I
I I I
I
I
I I 1
I I
I ; 1
I I I
I I
I '
1 I
i � i I
I I I I 1
I I I I 1
I' '
I
II I I I
I
C)
w
c
a�
a
U
O N
II
\ II
- -IL
r�
II
: cn
3 I� 7c
z
r 1- Ln
� } 7
� C
,t
L
..
Q
I
x
w
0
z
z
O
z
O
U
z
W
W
Q
0
w
Qf
D
w
a
00
rn
rn
0
w
U_
W
af
U
n.
0
0
0
m
cy m
m
a
a
m
� w
O
U)
W
z
Z o_
Q
00
CD IY v)
N
O
2 � 3
0 a-
Li
Y W °o
Cjf
Of
a Ln
N a)
Q rn <:
O Y
m = � r = " = = = = m = = m m � m r r
m
o� LO
N NO /
N N O /
M 03 4 N /
v 0 /
m° 0)_ a / W
OD
00 Cb L LLJ
o ° a / Q
i
a 0
°
,o o o o m
N
NO W W
d � I O
V " / > O Q
/ > v � Q
O �
/ � Q
/ Cn LL
> �w 0'
/ o> o> o o c N Q W W
O N W C' C.7
« N « E Q Q
u° m Of Of
O Z N « V N V y U N V « C O W W
N« N N •- N N '- d p N N N U Q Q
1 a •— N a c m o y m m v v w W W
00 / d m o a�i rn� v �v v o c c E �—
Z / >> > N c > m o > > rn Q Q
o 0 0 0 0 0°
Q 0 0 0-
0 ( c a o 0 c a o o_ a e a N o
/ X X
/ IY aY
r rZ rl
r a tl
I Q Q
I
r «
Q z 1 $ ° o v
0
of~ 1 0 0 LL o • o �"�
>� w > a >
I
G_ O I
W Z
m— O O O O O O O O O
� Q O O) 00 n cfl It r� N O
Z (if
(NOIIIONOO 1N3W3AVd)
O tl
O y �
i0 C L
U
O O C 0
m¢aa
■ -.
••
W
J
U
W
LL-
J
H
W
W
F—
W
C7
Li
F
O
W
Z
Z_
Q
W
2
Y
Q
d
Y
Q
O
No
W
W
0
0
rn
0
0
rn
rn
i
W
cn
Z
W
W
Of
a-
0
U
O
O
rn
m
0
°
U
m
rn
m
ai
L
\ /
« \
«
d
«
//
//
\®
4/
//
eg �
G9 )
)\ °
\§
\j a
=2 w
\, )
Lh
/
\j
2
Ld
/�
C)
<
\\
V
/
-
k
>/f
e
/
\
\�\
/
«
d
«
//
//
\®
4/
//
eg �
G9 )
)\ °
\§
\j a
=2 w
\, )
Lh
/
2
Ld
/�
a
<
\\
V
/
k
e
/
�o
/
\j/
/
/
4
z�
h
00
/<
/ }\
°
2
�
4
BEc
/
/
,
vr
G
//
//<
/
f
j(
/
ƒ
/3
U)
ƒ
/
LLJ
g
>
\/ �m
m
2
C
v
\]
%
\ \\
/
2J<
E
3a2
®
/
\
7§f
/
2
//\
�
R
LLJ
Z
/�
cr-3
«
d
«
//
//
\®
4/
//
eg �
G9 )
)\ °
\§
\j a
=2 w
\, )
\k
§n)m
� ■�
�.�
2
2
O
\
/
\
ƒ
\
\
U
�
/
\
E \
\ /
\ ®
/ \
\ \
�
E % (
/ )
\ \ \
~ i /
\ \ j
m m m m m m m m m= m= m= m m m m m
Lh
«
/�
\\
V
/
�o
LLJ
\j/
>
/
4
E
h
00
/ }\
°
k
�
4
BEc
®
,
vr
G
//<
/
f
\
U)
ƒ
LLI
v
\]
%
/
�2
2
\
® E
\k
§n)m
� ■�
�.�
2
2
O
\
/
\
ƒ
\
\
U
�
/
\
E \
\ /
\ ®
/ \
\ \
�
E % (
/ )
\ \ \
~ i /
\ \ j
m m m m m m m m m= m= m= m m m m m
Imo) W
w
Z
N
O �
V '
---------/
I I
I 1 ,
I '
I
1 1
I I "
1 I I
I
__ - --'J
I
II -
II 1
II
II
II
II
\ II
\ II
\ II
a \ II
N \ II
N \ II
\ N \ I I
\\ M \\ I I
\ q t1
\ \ q 1
\\ \q 1
1
♦\ N
\V \1 1
\\ 1 1 11 I I
\ 11 1
\\I 1V 1
I u 1
\ I1 1
I 11 1
1 i I 1
I 11 1
I 1 1 l
1 1 I
I I 1 I
I I 1 I I
I I II'
I I I I
I I I 1
I I I
I I I
I I I 1
1 I I 1
I �I
IIn:I l i
I I I
III 1
I
� 1 1
I
1 jl
lit �I
I I
1 1 III / 1N�
I I 1 III
I II II
I II 1I
I II rI
I I I I I
I II II
I
1 I 1 III
I II I
I I I ICI I
I 11 1
I II
� j I
I I I I I
I I I 1 1
I I I I I
I I I I I
I I I III
I I I I I
1 1 1 1 1
I I I 1
I I I 1 L
I I I I \ l
I I I
I I I \ \
I I I \
I I I
I I I
f I 1 !
1_-
Q
N W
1..1�
Q
N �
LL
W
, W
V
N G
LL
O
co
0
W
O
d
O
CE
d
a
M
O
U
Q
O
W
Z
Z C m
Q
O
0 N
LLJ
(7 Q O
= W n
Y W i
� a
Q C/)
rn i
Y LO
Q 01 i
0 — z
O ^O
O ac
m C i 6
U
0 (a
O O c m
IM cr Q Q
■
O
W
Of
D
CD
LL
o .a
O Y
.m
C U
O N O O
C m W
C
O O c m
Cox <<
waq�rOV
-1W'r-
u
Q
Ld
ry
Q
W
W
V)
O
cn
(]
W
(n
O
0-
O
cr-
0-
W
a
M
N
LO
0
O
U
Q
O
(n
W
Z
Z Q
C7 m
0
_ � n
CD o
= W M
W N
Y � N
(if V) M_
LO
07 O
Q O)
0 r
O 0)
O Y
O
C m 'a m
O O C In
OEM
I offifilml 111h Biala
w
N I '1S IS
z
Eel
I
I
�I
I
I
I
I
1
I
e
I
I
1
I
I
I
I
I
1
I
MIN
mom 1011101
111111 11111
P1111012 illlE :1111111:
IN
I
\ I
\ I
1 , � 1 1 1 1 1 1
1 Vl \
I, I I
I I �
n 1
II i1 i I
I i 1
I I 1 I
1 I 1 1
I I I I
1 I 1 1
I I I I
I I I I
I I I
4 I 1 I
I I I I
I � I
I I I f
I I I I I
I 1 I I
I I I I
I I
1 I I I
I I I I
1 11 I I I I I
I I I I I I it
I I I
I I I
11 I I I I I
IQ I I I II
I
I I ri l
I I
1 1 I I I 1 1
1 1 I I I t
III I I I I II
I i 11 11 I
1 1 1 I I
t I I I
t l l l I I
I I I I I I I
I I
j l l l I I II
I I I I I I I I
I I I I I I I
I I I I 11 I
I I I I 11
it
:
I I
X11 j I j I I
I
1 1 1 I I I I
If I I I
i t I 1 1
\ I I I I
I I 1 1 I 1 1
I I I I 1 1 III
I I , 1 IIII
I I I I I I
I11 I I I I I I
I I I I I I
j I 1 j I I I p
I I I I I I I N p
I I I I I I I I
I I I I 11 III
I11 I I I I I f
i i I I l i I
1 II
WAN
Q
w
Q
V)
z
W
, N
V/
w
W
Q
N
W
V
LL
a
M
LO
M
0
O
U
O
LL)
z m
? � m
� Q
Of m
vi cD
i °
G a a
w � �
= n
Y W i
N M_
0
Y
0)
Q 0 i
O x
1111111 111111 11111111 111111 11110 11111 111111 1111111 1111111 111111 11110 11111111 111111 1111111 1111111 1111111 1111111 111111 111111
W-
1
I
--
r
I
Jr
OEM
I offifilml 111h Biala
w
N I '1S IS
z
Eel
I
I
�I
I
I
I
I
1
I
e
I
I
1
I
I
I
I
I
1
I
MIN
mom 1011101
111111 11111
P1111012 illlE :1111111:
IN
I
\ I
\ I
1 , � 1 1 1 1 1 1
1 Vl \
I, I I
I I �
n 1
II i1 i I
I i 1
I I 1 I
1 I 1 1
I I I I
1 I 1 1
I I I I
I I I I
I I I
4 I 1 I
I I I I
I � I
I I I f
I I I I I
I 1 I I
I I I I
I I
1 I I I
I I I I
1 11 I I I I I
I I I I I I it
I I I
I I I
11 I I I I I
IQ I I I II
I
I I ri l
I I
1 1 I I I 1 1
1 1 I I I t
III I I I I II
I i 11 11 I
1 1 1 I I
t I I I
t l l l I I
I I I I I I I
I I
j l l l I I II
I I I I I I I I
I I I I I I I
I I I I 11 I
I I I I 11
it
:
I I
X11 j I j I I
I
1 1 1 I I I I
If I I I
i t I 1 1
\ I I I I
I I 1 1 I 1 1
I I I I 1 1 III
I I , 1 IIII
I I I I I I
I11 I I I I I I
I I I I I I
j I 1 j I I I p
I I I I I I I N p
I I I I I I I I
I I I I 11 III
I11 I I I I I f
i i I I l i I
1 II
WAN
Q
w
Q
V)
z
W
, N
V/
w
W
Q
N
W
V
LL
a
M
LO
M
0
O
U
O
LL)
z m
? � m
� Q
Of m
vi cD
i °
G a a
w � �
= n
Y W i
N M_
0
Y
0)
Q 0 i
O x
1111111 111111 11111111 111111 11110 11111 111111 1111111 1111111 111111 11110 11111111 111111 1111111 1111111 1111111 1111111 111111 111111
o . y
co
O Y
c (o 'OC)
O O c m
Mcr <<
N,
w
LL-
C�
n
0
0
U
P r7
giow
LLJ
Q
LL)
Q
I
V)
F—
Z
L.LJ
V)
LLJ
Q
Q
H
O
U)
W
Z
C)
m
m
V U
O
_ � m
=
W W n
� � a
Q N n
a. LO
0) i
Y U')
0
o .o m
O y
m = L U
C m q
O O C m
mcc<<
-w �
r-
w
0
0
LO
LO
E
U
U
E
of
WIN
Q
W
Q
Z
W
w
Q
Q
O rn
U
W
Z m
Z � �
� Q
(n 0 N
_ 0 o
0 a 8
Ln
rn
W i
Q (n 0 a Ln
rn
Y N
O rn Y