TO: Eric Johnson
FROM: Scott Richards
DATE: March 6, 2008
RE:
FILE NO: 798.02 — 07.10
Oak Park Heights -- Oakgreen Village, Phase 1, PUD Amendment
And Phase 2 Concept and General Plan Approval, Preliminary
And Final Plat
Tim Nolde, representing Anchobaypro, has indicated that revised plans are still being
prepared for the Oakgreen Village Phase 1 PUD amendment and Phase 2 concept and
general plans. As of the date of this memo, the revised plans have not been received
by staff. A plan may be ready for insertion into the planning packet this week. As a
result, the Planning Commission will not be asked to make a recommendation at their
March 13, 2008 meeting to give staff an opportunity to review and comment.
The 120 day development timeline ends on April 9, 2008. Mr. Nolde has been asked to
provide a letter of extension of the timeline. If a letter is not received, the Planning
Commission will need to recommend denial of the application. It is anticipated that Mr.
Nolde will provide a letter and the Planning Commission and City Council will be able to
review this application in April.