Loading...
HomeMy WebLinkAbout2008-03-06 NAC Planning MemoMEMORANDUM NORTHWEST ASSOCIATED CONSULTANTS, INC. 4800 Olson Memorial Highway, Suite 202, Golden Valley, MN 55422 Telephone: 763.231 .2555 Facsimile: 763.231 .2561 planners@nacplanning.com TO: Eric Johnson FROM: Scott Richards DATE: March 6, 2008 RE: FILE NO: 798.02 — 07.10 Oak Park Heights -- Oakgreen Village, Phase 1, PUD Amendment And Phase 2 Concept and General Plan Approval, Preliminary And Final Plat Tim Nolde, representing Anchobaypro, has indicated that revised plans are still being prepared for the Oakgreen Village Phase 1 PUD amendment and Phase 2 concept and general plans. As of the date of this memo, the revised plans have not been received by staff. A plan may be ready for insertion into the planning packet this week. As a result, the Planning Commission will not be asked to make a recommendation at their March 13, 2008 meeting to give staff an opportunity to review and comment. The 120 day development timeline ends on April 9, 2008. Mr. Nolde has been asked to provide a letter of extension of the timeline. If a letter is not received, the Planning Commission will need to recommend denial of the application. It is anticipated that Mr. Nolde will provide a letter and the Planning Commission and City Council will be able to review this application in April.