PLAN REVIEW REPORT -1
The following plan review report represents a comprehensive code record for the project
outlined below. In addition, this report contains a compilation of current (2003 Minnesota
State Building Code) code violations and/or project specific conditions, which require plan
revisions, corrections or further clarification by the proper design authority prior to
construction authorization or permitting for this project. Please review Plan Review Report
- 1 completely and respond to the Building Inspection Department by letter of verification,
including (but not limited to) necessary revised plan sheets or specifications, copies of relevant
addenda(s), change orders, shop drawings, etc. Said correspondence must provide all relevant
and /or necessary information required to complete the plan review process and issue a
Building Permit. Please respond as soon as possible.
Date: January 24, 2005 _ aU(
Project Title: Kowalski's Market !� OOCAS
Project Description: Renovation of existing one story retail building
Project Site Address: 5804 Neal Ave. North - Oak Park Heights, MN
Architectural Firm: Harriss Architects
Address: 331 Second Ave. North Suite #200 - Minneapolis, MN 55401
Contact Person: George Johnson
Phone: 612.339.2190
Fax:
Structural Firm: BKBM Engineers
Address: 5930 Brooklyn Blvd. - Minneapolis, MN 55429
Contact Person: John Timm
Phone: 763.843.0420
Fax: 763.843.0421
Contractor (General/Manager): Zeman Construction Co.
Address: 8900 10 Ave. N - Golden Valley, MN 55427
Contact Person: Jon Hormann
Phone: 763.398.8900
Fax: 763.398.8939
Applicable Codes: 2003 Minnesota State Building Code & 2000 International Building Code
2
Code Review Information
Frontage increase
If =100 [F/P — 0.251 W /30
N /A, the existing project was designed having 60 feet of open yard on all sides and utilizing
unlimited area provisions permitted by code.
Allowable Building Area
The existing shopping center consists of Group M Occupancies, Type V -B construction,
one story slab on grade, fully sprinklered having unlimited area as permitted by IBC 507.
Aa = At + [At If/100] + [AtIs/1001
N /A, designer will utilize unlimited area provisions permitted by IBC 507.
Occupant Load: 950 Exits Required: 3(retail) Minimum Exit Width Req'd: 142.50"
Exits provided: 3 (retail) Exit width provided: >142.50"
No separation required between the retail (M) area and storage (S -2) area. The Kowalski
Market area is a nonseparated use and designed to the most restrictive use requirements of
Groups M and S -2 occupancies.
No separation required between the retail area and incidental storage areas ( <10 %).
The architectural and structural documents for the project described above have been
reviewed for substantial compliance with the 2003 Minnesota State Building Code. The
following (attached) nonstructural comments, based on the 2000 International Building
Code, as amended by the 2003 Minnesota State Building Code, shall be resolved before
construction authorization is issued. The architect or engineer of record shall respond by
letter of verification and submittal revised construction documents, addenda's or change
order's; or with the additional submittal of required shop drawings that clearly identify
that said corrections have been made as required by this plan review report.
This plan review report is a "nonstructural" code analysis based on the current 2003
Minnesota State Building Code. Although every attempt has been made to identify "code
issues" or "concerns" for proper and necessary change, the project designer(s), the
building contractor(s) and the property owner(s) are ultimately responsible for providing
complete code compliance and maintaining minimum construction standards for the
safeguarding of life or limb, health, public welfare and property.
3
Comments contained within this report shall not be construed to relieve from, lessen the
responsibility, or grant authorization for work in violation of any laws or ordinances of the
jurisdiction.
CODE RECORD
Project Title: Kowalski's Market
Code Info.: Existing Building — Group M & S -2 occupancies, Type V -B
construction
Review Date: January 24, 2005
Location: City of Oak Park Heights, MN
Address: 5805 Krueger Lane North - Oak Park Heights, MN
Plan Review No.: PR -05 -101
Date Received: January 8, 2005
Plans Examiner: Richard Lockrem, Minnesota Certified Building Official # 1237
Questions as to this report are to be directed to Building Official Jim Butler
Phone Number: Direct No. 651.275.9590 General No. 651.439.4439 Fax: 651.439.0574
Est. Const. Value: Unknown
Const. Doc.'s Dated: January 3, 2005 (w /o Specifications and HVAC)
Addendum No.(s): none submitted
Except as noted herein, the construction documents for the above noted project has been
reviewed for substantial compliance with the requirements of the proposed 2003 Minnesota
State Building Code.
The following code commentary should be incorporated into the contract documents for
this project prior to the start of construction. Said contract documents should be revised to
meet code - as necessary - before construction is started.
This building code plan review does not include the review of state fire codes, electrical
and/or plumbing installations, site grading or civil work, landscaping, septic designs, well
construction, or other site utilities. Separate review, approval and/or authorizations must
be obtained for work covered by the State Department of Health, Plumbing Codes
Division, the State Board of Electricity, the MPCA and the Minnesota DNR Municipal
City /County Zoning and Fire Codes have also not been included as part of this review.
This plan review report is a "nonstructural" code analysis based on the proposed 2003
Minnesota State Building Code. Although every attempt has been made to identify "code
issues" or "concerns" for proper and necessary change, the project designer(s), the
building contractor(s) and the property owner(s) are ultimately responsible for providing
complete code compliance and maintaining minimum construction standards for the
safeguarding of life or limb, health, public welfare and property.
4
Comments contained within this report shall not be construed to relieve from, lessen the
responsibility, or grant authorization for work in violation of any laws or ordinances of the
State of Minnesota of this jurisdiction.
Plan Comments:
Sheet L1 -0:
Revise and resubmit Landscape Plan 1/L1 -0 to include at least one accessible curb ramp
providing access to the new building entrances. The curb ramp(s) shall comply with
MSBC 1341.04028 subp. 4.
Review and revise the existing accessibility parking stalls adjacent to the Kowalski's building
portion entrance. At least two van accessible stalls shall be provided for the ten accessible stalls
shown at Site Plan 2/L1 -0. See MSBC 1341 regarding van accessible stall requirements and
proper accessible parking signage requirements.
Sheet A2 - 0 and A2.2:
Revise Wall Types 2 and 4 and similar wall details to include a vapor retarder over the foam
sheathing per Minnesota Energy Code 7676. Resubmit revised details for review and approval.
Please verify which service areas will provide service counters for customer assistance (i.e
Bakery, Deli, Meat Department and Starbucks). Each customer service area counter requires a
minimum 36 -inch clear width and a maximum counter height of 36 inches above the finished
floor per MSBC 1341.0720 subp. l . Submit shop drawings of these service counters for review
and approval.
Provide revised plan and section for the stair and landing at 9/A2 -0. The stairs shall have
handrails installed on both sides mounted 34 -38 inches above the treads. If a 42 inch guard is
required on the open side of the stairs ( >30 inches grade) the handrail shall be installed on the
inside face of the guard. See IBC chapter 10.
Revise the Door Schedule to replace the 2' -8" doors ( #122, 123, 139, 131 and 132) with 3' -0"
doors. The 2' -8" doors do not comply with the minimum clear opening width per IBC chapter 10
and MSBC 1341. Also review the accessible maneuvering clearances at the push (12 ") and pull
(18 ") sides of these doors per MSBC 1341 requirements. These door modifications will require
the width of Hall #122 to increase to 5' -0" clear inside width to accommodate the door
requirements.
Provide shop drawings for the automatic horizontal sliding doors #100A, B, C and D. These
doors shall be equipped with break away hardware for emergency egress requirements per IBC
Chapter 10.
5
•
Review and revise the pull side (18 ") maneuvering clearance at doors #106, 111A, 115 and 123
per MSBC 1341.
Sheet A3 - 0:
Revise the entire sheet A3 -0 to identify the locations of safety glazing for the window types
shown in 7/A3 -0.
Sheet A4 - 0, A4 - 1, A4 - 2 and A5 - 0:
Revise numerous sections that indicate fiberglass insulation installed at ceiling joists and exterior
walls to provide installation of a vapor retarder on the warm side of the assembly per Minnesota
Energy Code 7676. Also explain how this insulation will remain in place for the duration of the
building with the absence of gypsum board as usually provided.
Modify section 2/A4 -1 to cover the exposed foam insulation above the ceiling tile height.
Sheet A5 - 1:
Revise details 11 /A5 -1 and 13/A5 -1 to include sill flashing below the window sill and extend
beyond the building exterior wall.
Submit the manufactures installation instructions and literature for the EIFS system for this
project. The information submitted for review and approval should address drainage plane
requirements.
Sheet SO
Please complete and submit "Special Inspection and Testing Schedule" signed and dated by all
required individuals. See sheet S0 -1 for required special structural inspections.
The soils bearing design for this project is assumed to be 2,500 psf per the structural notes on
sheet S0 -1. The soil bearing capacity must be verified by a registered soils engineer. The soils
engineer shall also verify the required frost footing depth for non - heated areas.
The following information and comments is for review and may be incorporated
into the construction documents. It is not necessary to provide a written response to
the following as part of the plan review process. It may be beneficial to provide the
following information to the general contractor.
6
General Comments:
In accordance with IBC Chapter 17, a Special Inspections Agreement must be completed, signed
and submitted to this office prior to permit issuance. Required special inspections must be
determined by the appropriate design professional and the required third party inspection
agencies must be contracted for said work. Submit a copy of a completed and signed Special
Inspections Agreement for review — ASAP. [IBC Chapter 17 and MN Rule 1300.0130]
Fire sprinkler shop drawings and hydraulic calculations must be submitted to this office for
separate review and approval prior to installation of any portion of the system. Municipal water
capabilities /supply, including residual and static pressure & GPM flow rate(s) of the supply
line(s) must also be included in the submittal for design verification purposes. Submit required
fire sprinkler information as soon as possible for separate review. [IBC Chapter 9 and NFPA 13]
Plans must designate a specific area to be used for recycling space. Designate a recycling space
on the contract document set for code review pursuant to MSBC 1303.1500.
[MSBC 1303.1500]
Provide verification that specified interior finished ceiling tile assemblies (as specified in section
09511 of the specification manual) will meet the minimum flame spread index and smoke
development ratings as required when part of a plenum ceiling assembly. (Minimum flame
spread index of 25 and a smoke development rating of 50.) Provide details for review.
[IMC 602.2]
No mechanical, plumbing or electrical work may be installed until proper construction
authorization has been obtained from this office.
[MSBC 1300.0130]
Verify that all wood used in direct contact with concrete or masonry will be that of a pressure
treated type designed for such conditions see details 5, 7, & 9/A2.2 and other similar
installations. [IBC 2304.11]
Glazing installed within 60- inches of the floor and within 24- inches of the vertical plane of a
door (measured in the closed position) must be "safety tempered" glass. (ALL glass within 60-
inches of the floor.) Verify that glass set adjacent to doors will be "safety tempered" glazing per
code. [IBC 2406.4]
A complete code analysis (code record) report must be submitted to the jurisdiction of authority,
including a reduced copy of the code record floor plan. Your code record submittal did not
include a reduced floor plan sheet (11 x 17 max size) with appropriate code record information.
Submit a reduced size code record floor plan with all applicable code information in response to
this item for review and record purposes. (Note: The code record must include computations
indicating allowable area compliance for the building, shafts, exit passageways, overall travel
distances to the most remote location(s), occupancy groups, fire department connection, room
exit load quantities, main exit width occupant load quantities and other pertinent code
information as applicable to the occupancy.) [MSBC 1300.0130]
7
All exterior walls must be protected with a water - resistive barrier (behind the exterior finish) that
must be securely attached to the wall sheathing. The water - resistive barrier must be installed in
such a manner as to provide a continuous barrier (incorporating required flashings) behind the
exterior finish/veneer. Provide details /specifications of the required water - resistive
barrier /flashing conditions for code review and inspection purposes pursuant to IBC section
1404. [IBC 1404]
Wall finishes within 24 inches of the front and sides of water closets and urinals must be finished
with a smooth, hard, non - absorbent surface material to a height of 4 -feet above the finished floor.
The finish material shall be a type that is not adversely affected by moisture. [IBC 1209.2]
Floor finishes in toilet and shower/bathing rooms must be finished with a smooth, hard
nonabsorbent surface that extends upward onto the walls at least 5 inches. The finish material
shall be a type that is not adversely affected by moisture information on proposed floor finishes
[MSBC 1305.1209.]
The concrete floor slab must be protected with an under -floor waterproofing/dampproofing.
[IBC 1806]
The minimum frost depth protection/coverage for any footing on this structure is 3' — 6"
(southern zone) from finished grade to the bottom of every/any footing. Verify with the soils
engineer if an additional frost footing depth may be required near the loading dock area.
Revise the plans as necessary and resubmit details for further code review. [MSBC 1303.1600]
Guards serving as a protective device in a "public" area must be constructed not less than 42-
inches in height and have an intermediate ornamental pattern such that a 4 -inch diameter sphere
could not be passed through any opening up to a height of 34- inches in the guard. From a point
measuring from 34- inches to 42- inches above the walking surface, the guard's intermediate
pattern must be constructed so that an 8 -inch diameter sphere could not be passed through any
point. Revise the cedar and iron retaining wall guard/fence (3/A0.2) pattern and resubmit plans
for review. [IBC 1003.2.12]
Exiting Comments:
Required exterior lighting at/near exit door stoops must be interconnected with emergency power
backup as part of the required exit discharge system. Verify that the electrical power plan is
compliant and emergency back -up power is interconnected with exterior lighting at/near each
exit door stoop/landing per code. [IBC 1003.2.11]
Exterior lighting/illumination is required at/near each required exit door stoop /landing. Said
exterior exit illumination must also be interconnected with the required emergency power backup
system as part of the required exit discharge system. Revise the electrical plans as required to
provide for the required exterior exit illumination at each exit door stoop /landing and
interconnect each exterior light with the buildings emergency back -up power system per code.
[IBC 1003.2.11]
8
Please clarify the design conditions of proposed door locking hardware within the facility.
Verify that all exit access and/or exit doors will be provided with locking devices meeting the
provisions of IBC 1003.3.1.8 for operation from the inside without use of a key or special
knowledge or effort (no thumb -turn locking devices). Please clarify the door locking hardware
conditions for review. [IBC 1003.3.1.8]
Illuminated exit signs must be provided at each exit and along the entire exit access system so
that no point in an exit access corridor is more than 100 feet from the nearest visible exit sign.
Provide illuminated exit signage along the means of egress system as required by code and
resubmit plans for further code review. [IBC 1003.2.10]
Please clarify the design conditions of proposed door locking hardware within the facility.
Verify that all exit access and/or exit doors will be provided with locking devices meeting the
provisions of IBC 1003.3.1.8 for operation from the inside without use of a key or special
knowledge or effort (no thumb -turn locking devices). Please clarify the door locking hardware
conditions for review. [IBC 1003.3.1.8]
When a room or space requires two or more exits, each exit shall be provided with an illuminated
exit sign. [IBC 1003.2.10.1]
The means of egress, including the exit discharge, must be illuminated at all times the building is
occupied. Provide for required exit illumination along each means of egress system out to and
including exterior exit discharge landings. Emergency backup power supply shall be provided to
automatically illuminate the means of egress in the event of a power failure. [IBC 1003.2.11]
Miscellaneous Code Commentary:
Note: In accordance with state law, prior to excavation or grading on any site, utilities must be
located. Call Gopher State One Call at 1- 800 - 252 -1166 (651- 454 -0002 local) as soon as possible
to schedule utility locations for this site. [Minnesota Statute 216D.01 to 216D.07]
Note: Prior to the start of any site clearing, grubbing, excavation, or grading, you will be
responsible for verifying that proper procedures have been followed for obtaining an NPDES
Grading Permit from the Minnesota Pollution Control Agency (MPCA). Generally, when site
construction affects areas of 5 -acres or more, an MPCA - NPDES Grading Permit is required.
Although our office has no jurisdiction over this matter, we are using this opportunity to make
you aware of your responsibility for securing required MPCA permits. For more information you
can contact the MPCA at (Metro) 651- 297 -2274 (Non -Metro) 800 - 646 -6247. [MN Rule
7011.9920]
Note: All plumbing plans (i.e., kitchen fixture and equipment plans, DWV and water piping
supply plans, RWL plans, gas and process piping plans, plumbing fixture plans and details and
all exterior site utilities, including on -site septic design plans) must also be submitted to the
Minnesota Department of Health, Plumbing Codes Division for separate review and approval.
9
• � n
1
Further information may be obtained by contacting the MDH at 651- 215 -0836. Submit required
plumbing plans to the MDH Plumbing Codes Division ASAP.
[MN Rule 4715]
Note: Floor plans must be submitted to the Metropolitan Council, Environmental Services
Division for proper and required SAC unit determination. Submit a copy of the floor plan(s) for
this project the MCES as soon as possible as a building permit cannot be issued without proper
SAC unit determination.
Note: Site grading, landscaping, utility installations, erosion control measures, etc. must all be
completed as approved by the City Engineering Department and Planning Commission without
alteration. Deviations from previously approved plans must be checked and approved by the
Engineering Department and/or the City Planning Commission prior to said change. In addition,
required erosion control devices must be installed and maintained throughout the construction
process as approved by the City Engineering Department.
[Local Codes]
Note: The main job -site entrance must be posted with the project address so that it is clearly
visible from the street. Said job -site address sign must be installed prior to the start of
excavation and grading for the project and must be maintained in place until final occupancy.
Permanent address numbers must be installed on the front of the building for final occupancy
inspection. [IBC 501.2 and IFC 505.1]
Note: As part of the construction process, and throughout the project, it will be your
responsibility to assure that building occupants are afforded a compliant exit access system
during and after construction. Please note that this will be verified throughout the construction
process during periodic inspection. [IBC 3302, 3303 & IFC 110]
Note: As part of the construction process, for the purposes of life safety, it will be your
responsibility to assure that readily accessible (operable/charged) fire extinguishers will be
located within the construction zone area during construction operation. Construction personnel
should be made aware of where extinguishers are located and how to operate said life safety
equipment. Please note that this will be verified throughout the construction process during
periodic inspection. [IBC 3309]
Note: Construction materials and/or equipment used or stored on this project site must be stored
and placed so as not to endanger the public, workers, or adjoining property for the duration of
this construction project. This will be verified throughout the construction process during
periodic inspection. [IBC 3301.2]
Pursuant to MPCA rules on hazardous material construction demolition, I would like to use this
opportunity to remind you that it is your responsibility to complete and submit a "Notice of Intent
to Perform a Demolition" form to the MPCA. Under MPCA rules, prior to initiating the
demolition process, you are required to have your building inspected for potential hazardous
contaminates. The hazardous material demolition inspector is then required to submit a "Notice
10
of Intent to Perform a Demolition" form to the MPCA on the results of said inspection. The
notice is required for verification and identification on -site hazards such as lead, mercury, PCB's,
asbestos and/or other environmental concerns. Once identified, hazardous materials are then
required to abated according to MPCA and Federal EPA Rules. For further information, contact
the MPCA at 1- 800 - 657 -3864. Please note that this is not a code requirement being mandated by
this Division, nevertheless, as a state rule, you should consider submitting the required abatement
verification notice (ASAP) for MPCA compliance purposes. No further response is necessary.
[See MN Rule 7011.9920]
Mechanical Comments:
Copies of all mechanical equipment balancing reports, orsat test results for fuel burning
equipment and start-up certifications must be supplied to the city inspections department as soon
as possible upon completion of said work. [MSBC/IMC 1346.M309.2.3]
Verify that mechanical equipment will meet the minimum equipment efficiency ratings as required
by the Minnesota Energy Code. [MSBC 7676.1100, Subpart 5]
Note that MN Rules 1346 (International Mechanical Code/International Fuel Gas Code) requires
all gas piping to be tested at a minimum of 25 PSI. Please schedule this testing accordingly.
New gas lines may not be placed into service until this testing is complete.
[MSBC 1346.G406.4.1]
T & P relief piping from the water heater must be directed to a safe point on/near the floor in
instances where the water heaters are raised. Verify that each relief valve will be provided with
required relief piping installed per code. [MSPC 4715.2210]
Gas meter locations may require pipe bollard protection devices if located such that they are
subject to damage. Gas meters and/or regulator equipment adjacent to vehicle drives or parking
areas must be protected as required by the code. Provide for the required protective devices as
necessary. Please note that these devices must be installed before final inspection of the
building. [MSBC/1MC 1346.M304.9]
Plumbing vent pipes must be terminated a minimum of 12- inches above the finished roof surface
of a building. Revise the plumbing stack vent detail(s) as required to provide for the 12 -inch
minimum termination per the Minnesota Plumbing Code. [MSPC 4715]
Verify that all HVAC air handling equipment that is capable of moving in excess of 2000 CFM
of air (for either supply or return) will be provided with required automatic smoke detection
shutdown devices in the return air duct plenum - at each piece of equipment per IMC 606.
[IMC 606]
11
r1
Accessibility Comments:
Verify that tactile signage (restrooms, common storage areas, laundry rooms, directories, room
identification, etc.) will be designed and installed per MSBC 1341.0405, Item P and 1341.0476.
All required tactile signage must be installed for final inspection and issuance of the Certificate
of Occupancy. [MSBC 1341.0405 & 1341.0476]
In public /common use areas, equipment controls (or a portion thereof) such as electrical outlets,
alarm pulls, switches, robe and coat hooks, coat racks and rods, shelving etc., must be installed
within the required reach ranges of 48" — 54" AFF (15" minimum AFF for electrical outlets).
Verify that said equipment and devices will be installed per code and or revise details as
necessary. [MSBC 1341.0470 and 1341.0420, Subpart 5 and 6 and 1341.0405, Item M]
Verify that a "lever" or "paddle" style hardware system (accessible) will be installed/used
throughout the facility for accessibility code purposes. [MSBC 1341.0442, Subpart 9]
Provide a section and details for the accessible counter areas so that each is completely
accessible. The maximum height of an accessible pass through window is 36." It must also be
not less than 36" in width. If there is cabinetry at the receiving side, it must also be designed
with appropriate knee space at the underside. Verify compliance with MSBC 1341.072.
. [MSBC 1341.0720]
When a drinking fountain is provided, either a combination "high -low" drinking fountain, or two
separate drinking fountains (one mounted at the required accessible height and one mounted at a
higher elevation) must be provided. Identify the accessible drinking fountain feature /condition
you will be revising the plan to comply with code. [MSBC 1341.0405, Item J]
Verify that public telephones will be provided with required volume controls and that each will
be installed so that all controls, including the coin slot are within the required reach range of the
accessibility code. [MSBC 1341.0405]
Handicap parking stall signs must be installed 48" to 60" high from grade to the bottom of the
sign. Provide details as required to confirm compliance of height installation of accessible
parking stall signs. [MSBC 1341.0428, Subpart 4]
The toilet paper dispensers must be installed at the correct location of 7" to 9" in front of the
water closet. Provide details indicating proper installation locations.
[MSBC 1341.0488, Subpart 6]
Fire Code Comments:
Fire sprinkler shop drawings and hydraulic calculations must be submitted to this office for
separate review and approval prior to installation of any portion of the system. Municipal water
capabilities /supply, including residual and static pressure & GPM flow rate(s) of the supply
line(s) must also be included in the submittal for design verification purposes. Submit required
fire sprinkler information as soon as possible for separate review.
[IBC Chapter 9 and NFPA 13]
12
"No Parking — Fire Lane" signs must be installed as indicated on the approved plan. Verify exact
location and number required with the City Fire Marshal. Said signage must be installed prior to
the final occupancy inspection of this structure. [IFC 503.3]
The location, size and type of required fire extinguishers for this project must be verified with the
City Fire Marshal. Required fire extinguishers must be installed prior to final occupancy
inspection of this structure. Verify fire extinguisher conditions/locations with the local Fire
Marshal prior to installation. [IFC 901.4.3 & NFPA Standard 10]
This building must be provided with a fire department key (knox) box for access to master keys
for the entire facility. The type of key box and the required installation location must be verified
with the Fire Marshal. Contact the Fire Marshal for verification of the type and location of the
required key (knox) box. Said key box must be installed for final inspection of this project.
[IFC 506]
The fire - sprinkler fire- department connection (OS & Y) must be located on the main street side
of the building near the building's main entrance (unless another location has been authorized by
the Fire Marshal). Provide further information on the proposed location of the OS & Y
connection for department verification per code. [IFC 912]
An on -site fire hydrant may be required as part of the fire suppression system for this building.
Verify required on -site fire hydrant locations with the City Fire Marshal prior to installation of
the firewater utility line and the OS & Y connector for this building. [IFC 508 & 912.2]
Provide additional information on the storage commodities and storage racking conditions within
this structure. Additional information on the type of commodities stored, the types of commodity
packaging materials, storage rack designs, the proposed height of the storage racks, the intended
height of commodity storage, rack aisle sizes, etc., must all be submitted for further code review.
This information is necessary to determine compliance with building and fire code regulations
pertaining to high -rack storage and proper classification of the building occupancy. Submit
additional information for review. [MSBC 1300.0130 & IFC Chapter 23]
Structural Comments:
Note: This plan review report contains only those "non- structural" building code issues and/or
conditions requiring revision or correction.
Also review the soils report for other recommendations based on the soil composition of the site.
Ask the soils engineer if an increase in footing depth is warranted at the loading dock area.
[MSBC 1300.0130]
Have the satellite dish installer submit their design requirements and method of anchorage for the
structural engineers review and approval.
13
,
Enerev Comments:
Energy calculations shall clearly indicate evidence that the building complies with either the
prescriptive of performance provisions of the Energy Code (MSBC 7676) must be submitted for
review. Submit necessary thermal energy envelope computations for code review and
verification. [MSBC 7676.0700]
Identify the "R" and /or "U" values of all required exterior envelope construction material and
insulation on/within the building for code review conditions. All construction material/building
insulation materials must be properly /clearly identified (on the plan sheets) with the proper
thermal "R" and/or "U" value for energy code verification and inspection purposes. Provide
required information for review. [MSBC 7676.0600]
Verify that proposed fenestration products meet the minimum performance standards set out be
MSBC 7674.0700, Subpart 3 for each new window or door installation. Provide manufacturer
data to substantiate the requirement. [MSBC 7676.0700]
An interior air barrier must be installed at all exterior wall and/or roof/ceiling membrane
areas of the building. The required air barrier must also be installed so that it is continuously
sealed at all penetrations, including electrical boxes, plumbing penetrations, framed wall
components and at the floors, walls and ceiling intersections of exterior walls and roof/ceilings.
The air barrier must also be sealed at intersections of all interior- exterior wall connections and
interior- exterior wall and roof/ceiling interconnections. Revise the plans
and/or specifications as necessary to incorporate the required air barrier at exterior /perimeter
walls and ceiling areas of the building and provide details for code review.
[MSBC 7674.0600]
Submit required plan review information, including revised plans, details,
specifications, Addenda's, or change orders (as required herein)
as soon as possible for completion of this review process.