HomeMy WebLinkAbout2012-12-05 Planning Report TPC 3601 Thurston Avenue N, Suite 100
Anoka, MN 55303
ENCLOSURE
Phone: 763.231.5840
Facsimile: 763.427.0520
TPC@PlanningCo.com
PLANNING REPORT
TO: Eric Johnson
FROM: Scott Richards
DATE: December 5, 2012
RE: Oak Park Heights — Xcel Energy / A.S. King Plant — Interim Use
Permit Application for Temporary Office Trailers
FILE NO: 236.02 — 12.10
BACKGROUND
Dan Flood, representing Xcel Energy, has made application for an Interim Use Permit to
allow placement of six temporary office trailers at the A.S. King Power Plant. The plant
is located at 1103 King Plant Road and is adjacent to the St. Croix River. The trailers
are to be used for a temporary increase in administrative and engineering personnel
while the plant is shut down for maintenance to the boiler. The trailers are to be placed
on site after approval by the City and are to be removed by July 31, 2013.
The property is zoned I, Industrial District in which power plants and accessory
structures are a permitted use. The King Plant is also in a River Impact District which
requires a conditional use permit for construction activities. In that the request is for
temporary placement of the trailers, the application is treated as an interim use, not a
conditional use.
Attached for reference:
Exhibit 1: Letter from Dan Flood, Xcel Energy, November 21, 2012
Exhibit 2: Site Plan — Trailer Locations and Restroom Locations
Exhibit 3: Picture of Proposed Trailer
Exhibit 4: Trailer Floor Plan
ISSUES ANALYSIS
Project Description. The description of the proposed need for the trailers is provided
by Xcel in the project application as follows:
This request is being made to place six temporary office trailers on site starting
November 1, 2012 thru July 31, 2013 to support an increased work force during this
time. All trailers will be approximately 10 feet by 60 feet and will be stand alone trailers
used for office work. These trailers will have temporary electrical and internet
connections to support administrative work. There will be no plumbing in these trailers
and all personnel will use onsite facilities located immediately adjacent to the trailers. All
trailers will be leveled, blocked and tied down for severe weather with temporary stairs
for access. These trailers will be placed on existing gravel areas located on site, see
attached drawing. The trailers will begin to arrive in November 2012 and all will be
removed by July 31, 2012.
Note the additional description of the project found in the letter from Dan Flood of Xcel
Energy found as Exhibit 1. Also, the trailers will not be put into use until the City Council
reviews and is favorable to the interim use, which will likely occur at their December 27,
2012 meeting.
Comprehensive Plan. The Comprehensive Plan designates this area as industrial
land use. The power plant and its accessory structures are recognized as industrial
land uses consistent with the maps and policies of the plan.
Zoning Ordinance. The site is zoned I, Industrial District in which power plants and
accessory structures are a permitted use. The King Plant is also in the River Impact
District which requires a conditional use permit for significant changes to the plant. The
temporary use of the trailers is not considered a permanent or significant change to the
plant site, thus will require an interim use. Section 401.32.0 lists temporary office and
administrative structures as an interim use in the I District.
Parking. The site currently has 117 permanent parking spaces on an existing blacktop
surface. An additional parking area of 400 spaces on gravel outside of the fence will be
used for the additional temporary personnel. The number of permanent plant
employees is 108 with another 250 during the plant maintenance.
Parking calculations for the plant are as follows:
Existing Office Space:
18,400 square feet x.9 = 16,560 / 200 = 83 + 3 = 86 parking spaces
Temporary Office Space:
3600 square feet x .9 = 3240 / 200 = 16 parking spaces
As per the Zoning Ordinance requirements, 102 parking spaces are required both for
the existing and proposed office space. The combination of the 117 spaces on the
blacktop and 400 spaces on the gravel will be more than adequate for the 350 people
that will be employed at the plant during the maintenance.
2
Lighting. No additional lighting has been proposed. Existing site lighting will be
utilized in the areas where the trailers are to be placed. Any new lighting of the site will
need to be in compliance with the Zoning Ordinance and subject to review and approval
of City staff.
Trash Handling. All trash and recycling for the trailers will be handled with the existing
facilities on site.
Restrooms. The six trailers shall not contain restroom facilities. As indicated in the
site plan found as Exhibit 2, existing restroom facilities in adjacent buildings will be
utilized.
Grading and Drainage. There will be no grading or drainage issues with the proposal.
The trailers will be placed on existing gravel surfaces.
Setbacks. The trailers will be compliant with all lot line and shoreland building
setbacks of the Zoning Ordinance.
Department of Natural Resources. The Department of Natural Resources (DNR) has
been notified of the request. There should be no issues in that the structures will be
temporary. The interim use approval by the City is subject to any further review or
comments by the DNR.
Design Guidelines. In that the structures are temporary, they are not subject to Design
Guideline Review.
Conditional Use Permit — River Impact District. Although this is an interim use and
not conditional use, it will be helpful for the Planning Commission to consider the
conditional use permit criteria, found in Section 401.03.A.7 of the Zoning Ordinance, as
part of its review.
1. Relationship to the specific policies and provisions of the municipal comprehensive plan.
2. The conformity with present and future land uses in the area.
3. The environmental issues and geographic area involved.
4. Whether the use will tend to or actually depreciate the area in which it is proposed.
5. The impact on character of the surrounding area.
6. The demonstrated need for such use.
7. Traffic generation by the use in relation to capabilities of streets serving the property.
8. The impact upon existing public services and facilities including parks, schools, streets,
and utilities, and the City's service capacity.
9. The proposed use's conformity with all performance standards contained herein (i.e.,
parking, loading, noise, etc.).
Due to the location of the King Plant in an industrial area, and the minimal, temporary
impact these structures will have on the site, the project is consistent with the above
criteria. The City Engineer should comment on any traffic concerns with having an
additional 250 people utilizing the roadways adjacent to the plant.
3
CONCLUSION AND RECOMMENDATION
Based upon the preceding review, City staff recommends approval of the Interim Use
Permit to allow for the allow placement of six temporary office trailers at the A.S. King
Plant subject to the following conditions:
1. The trailers shall be removed no later than August 31, 2013 unless an extension
is granted by the City Council.
2. Any freestanding or building lighting shall be in compliance with the Zoning
Ordinance and subject to review and approval of City staff.
3. Any changes to the grade or drainage associated with the trailer placement shall
be subject to review and approval of the City Engineer and applicable watershed
district.
4. The City Engineer shall comment on the traffic resulting from the increased
personnel at the plant. Any traffic control measures required by the City
Engineer will be implemented by Xcel Energy.
5. Xcel shall be required to comply with any permitting requirements of the City.
4
EXHIBIT
Xcel Energy*
414 Nicollet Mall
RESPONSIBLE BY NATURE* Minneapolis, MN 55401
1- 800 - 895 -4999
xceienergy.com
November 21, 2012
RE: TPC letter dated November 14, 2012
Dear Mr. Richards
This letter is in response to your request for more information regarding file NO 236.02- 12.10.
1. Provide mailing labels: Labels obtained thru Washington County and are attached with a
Map produced by the county.
2. Expand on narrative to discuss need for additional office space.
a. Beginning in December of 2012 Xcel Energy will begin the process of replacing
tubes in the reheater section of our boiler. Personnel will begin to arrive in mid
December for administrative and engineering work. The project itself will begin in
late February and completion is scheduled for early June. The need for additional
space is to house the additional workers involved in this project. Currently A.S. King
Plant facilities and offices are at maximum capacity and will not be able to house
additional personnel. Half of the trailers will be used to house administrative and
engineering personnel directly tied to the project while the other half of the trailers
would be used for break rooms where the craft would be able to take breaks. The
large number of craft personnel will be broken up into at least 2 separate shifts with
varied break times so that this number of trailers would be able to handle the number
of people. During times other than breaks these trailers would be idle.
3. Provide pictures / diagram of what the trailers will look like: See attached
4. Provide analysis of the number of parking stalls on site vs. the total square footage of office
space currently in use as well as the total with the trailers.
a. Approximately 117 permanent parking spaces on the blacktop; an existing additional
parking area of 400 spaces on the gravel outside the fence will be used for contract
personnel. Square footage of permanent office space is approximately 18,400.
Additional office trailers would add an additional 2000 square ft of office space, and
2000 square ft of lunch space. The number of permanent plant employees is 108
with the expectation of an additional 250 during the spring outage. Most of these
additional employees are members of the Minnesota Building and Labor Trades.
Xce/Ener
gy 414 Nicollet Mall
RESPONSIBLE BY NATUIE• Minneapolis, MN 55401
1- 800.895 -4999
xcelenergy.com
5. Provide a map of the restroom locations that will serve the trailer office spaces.
a. I have attached a drawing that shows both the trailer locations (in red) and current
permanent restroom / locker room locations (in Blue). Additional portable restroom
facilities (porta johns) will be located next to each trailer which would be serviced
daily.
If you have any further questions please feel free to contact me.
Thank you
Dan Flood
Xcel Energy I Responsible By Nature
Maintenance Planning and Scheduling Superintendent
1103 King Plant Road Bayport, MN 55003
P: 651-731-5736 C: 651- 485 -5280 F: 651 - 731 -7337
E : Daniel.flood @xcelenergy.com
-------.
..° ----- -
I. ALL NATES A
2_ THE. RE F,AS O N i
caNUC . s
E 20°4 PW`0' GRID y`YS'TF31 ELY'
E 1054.14
/� AzA ` N TFIE 2004 PIJ71'71 GRI
` 000 1}i PUN
TRANSFER VS R07A7 ED E G 4�9o 1966 8 IS
RGUSE !3 1966 PUNT
---~'L ` . ,. EXHIBIT T °E
2
4 � � �ECEr
...,"/--'- �/ ' Ell NM FAGUTIES L
, � .i 8TA 3000 N
NEYOR
_. _. ' a yyyy��� r ° • ♦ 4 • • 0U _ _ II
WATER E •'i- . � 691.4 � . .�•� ,��� /� ^��� -" ' �• �. _- ,�,_�-r' _, — ' ``� `} . �- a "OILPUYPl `� '�`
l FUEL Oil �•
— �� �M �/ STO •
HWS •
.' •� / -!� , <' DRAWING REVISED
/- T_______---
- -y- ,'�'� 27 '�' --"F *W se. O ; 139280. THE SIGH • '� ATTACHED GERTIFU
. ' � i ��� P ,„ 0 1 < FOR THIS PROJEC
f - •� '~ 3a - � �� ` T Vf'� , rl o ze ` ,- r 1 HE ED D
♦� AlA r - - GAT, PRE
• R
1
O_ - -. - 4 - 41v,,,, / - VI510 AN
. + -�1��1 Y FENCE -• . \ ' . ellti.'
FESSt ONAt° MNGIP T \ / ° oT D + a- B4 INTAKE c' STATE OF Nf
' ma y • c - B OOR S SIGNED
4 ° v 16 ` GAB. ,' ''� DATE .— IS
• • • a { O ELEM. .. - G$` 6 35 \18 9. - , .-- ,,iro B ` l uto 1� Sc aGa' ' jo T�n EWIPNE . �
ii� ® euaowc
• • \ • ...„31 Y 1V �Wt�IL 1 J L s4G _ : NR E R � f ! . 19
- o`' / r ° • \, 2 0 _ O • {]�M ,�F� E B AG. � ens. Rdµ G �cy{,s C, \ rcc
J v 0 . T 9= `.. t, 6 SM t i i0GT1 G
ROOM �� ` PRECIPITA.-1 t I �j• -r• /• ��
23
30 q2 �,`� I D
BBTAilON • �`` ���;� 19' O.
\\./7" -'...-- A /' ,, CATE _ - C��0 i
'� WV li ,..„ 0 „.,.. 4 1, /f, T R BR `l . ` al ' . lk *
' . . • • = ` iE . �! 2 18 "x21�x8_ DN. GATE ' '� / r - CANN .
\ _ D ISCHARGE
•
M5 L i
—
°
• A LA - _ / t
• Q H OLD -UP'
// / - SIGNAL E / /�. / �r... / PO �.•� --�..
f \ /// \�1 ° • • • it'- /` COAX 1" C / �_ _ /s Al
\\ \ \ •• • /� 1 AC POYR / //� 1 Y �� ' l .� f f
\ •\ r • ° AGID ClE 1NS , .i y ./ Y•r•�
\ \ \\ PONf�1 1 ON FENC�'/ �`� .i'� I r _ � _
\I CARD READER . HOLD - UP -- - - Ti M
e� T RL \ �-� N�. e POND BLDG. - -_ I _ . — .
\ \ �- -��' 20 O '
\ GA V! =
\:1f - - - 1 i - T' FENCE _ �4
N A`. "—\ .-- ._a,.. -- g WALK GATE - A
NI\ 62
J ;IL \ �� L r � __- - .' v \ SOUTH PROPERTY LINE 1 � T
e rtnemenecooll
2 -4G /A PRONE CABLES SITE
• 2" - FLT. TO GUARD HOUSE � — - .PFD k
1 -6 FI
1- <C 41B PNCNZ GABLES
f -- GUARD HOUSE TO FRONT GATE•3 - CKTS. iiii
GUARD HOUSE ,,. c . R PN4
'14 ^x97956
1 068 F�0' I _ 10500 SCONE TO FRONT GATE —
SPACE BY 8211 Tow Maryland 21 S M6024
® Baltimore, Marylann d 21236 -5997
WILLIAMS 800.782.1500
SCOTSMAN
www.willscot.com SECTION MODULAR
56' -0"
ri 12' -0" 7' -1" 30" 12' -0"
If (� f
9P —111111 •
cws r
` W . 9P 9 _
C
'p
ZD / \ \ \
>
4
II
�Q _ C OLUMN _ -
. s.,.... : in
N \ II
go
1
>
T L
- Cc µ t} y y y 4
1
• I �"- , .
Additional floor plans available. Floor plans and specifications may vary from those shown and are subject to in -stock availability.
DWN BY: � SERIAL #: REP: CAD FILE: THE USE OF THIS DRAWING FOR ANY MEANS OTHER THAT
MRW INTENDED IS STRICTLY PROHIBITED WITHOUT THE PRIOR
WRI1TEN CONSENT OF AN AUT
SCALE: [ DWG # DATE REV# SCOTSMAN REPRESENTATIVE. HORIZED WILLIAMS CO
1/8 " =1' IA-1 01 /01 /10 0
2010 Williams Scotsman, Inc. All Rights Reserved.