From: Long, Chris W [clong@bonestroo.com]
Sent: Friday, July 21 2006 8:28 AM
To: Eric A. Johnson; Tom Ozzello; Judy Hoist; Julie Hultman; Jim Butler; Erickson, Karen S; Post ler,
Dennis M
Cc: Hanson, David D; Kelley, Brian
Subject: OPH Project Status Updates
Novak Avenue North/Norwich Avenue North:
• The sanitary sewer and water main are complete on Novak and Norwich.
• The storm sewer is currently being installed and should be finished early next week.
• Both streets are expected to be ready for aggregate backfill late next week.
Project Issues:
• Electrical concrete conduit in conflict with SS-8 and stub - The conduit is scheduled to be
located on Monday morning. Following the Locate, decisions can be made in resolving the
conflict.
• Overhead power ines and poles have not been removed - Art Neilson, with Excel, is working
on this issue, but said it may take some time before they can be removed.
Pine Grove Gardens:
• All utilities are complete.
Approximately 75% of the concrete curb is complete. The remaining B618 concrete curb should be
completed today.
• The curb will be backfllled on Monday.
• The streets are expected to be paved by late next week.
Wal-Mart:
• The water main connection on 58 Street was completed by wet tap yesterday.
Lowes:
• All three fill sites are currently being used by Frattalone (Node — 2 sites, CSM — 1 site). All silt fencing
surrounding these sites is to specification.
• Vosson Plumbing is on-site installing the internal utilities for the R.J. Ryan/CSM site east of Applebees.
Oakgreen:
• Expected construction start date: end of August/early September.
Let me know if you have any questions or concerns. Thanks.
Chris Long
Bonestroo, Rosene, Anderlik & Associates
Phone: 651-492-7747
8/7/2006