HomeMy WebLinkAbout2003-06-12 OPH Email Re Project UpdateJulie Hultman
From: Eric A. Johnson
Sent: Thursday, June 12, 2003 9:02 AM
To: Mark Vierling (E- mail); Jim Butler; Scott Richards (E- mail); Dennis Postler (E -mail)
Cc: Judy Holst; Jay Johnson; Julie Hultman
Gentlemen,
I just had brief discussion with Jason Myrlie, Hom4me; I expressed our concerns as discussed yesterday at staff
meeting.
A few items:
) I hold a copy the construction easement from Dr. Hall.
2) 1 stated that we need the connection and park fees prior to any permits being issued
3) That the watershed is meeting tonight to discuss their project (MnDOT approval as well)
4) Jason indicated that ALL the corrected, 8 copies, plans have been submitted. -- I WILL RECONFRIM.
5) That 4 signed copies of the DA are required.
6) That the 'mylars', once created (approved in form by the County) should go directly to Mark Vierling's office for his
review.
7) That the City needs an original Bank Commitment for the LOC.
8) That the City will not issue any permits at this time.
Just an update.
Eric