Loading...
HomeMy WebLinkAbout2002-03-06 Metro Land Surveying Ltr to BRAAi s Aff ri MEMO To: Dennis Postler From: John C. Johnson. Date: March 6, 2002 Re: Construction schedule Oak Park Station & S & C Bank Based on our telephone conversation March 5, 2002, it is my understanding that the City public improvement project schedule is as follows: 1. Approve plans & specs & authorize advertisement for bids March 12, 2002 2. Bid opening on April 3, 2002 3. Contract award April 9, 2002 4. Start construction April 22 to April 29, 2002 IV 5. Complete construction May 10 to May 17, 2002 The construction schedule for Goldridge Group is as follows: 1. Clear & grub & rough grade March 15 — 18, 2002 2. Final grading April 3 — 5, 2002 3. Foundation Construction March 15 — 29, 2002 4. Steel erection March 15 -- April 1, 2002 5. Under floor utilities & cone floor April 10 — 24, 2002 6. Framing & dry wall constr April 25 -- May 8, 2002 7. Parking lot paving May 3 l — June 5, 2002 (this item can be shifted to coincide with completion & acceptance of Street improvements) As we discussed yesterday, it will be necessary to maintain a temporary construction entrance as shown on the plans to avoid conflict with the City's street & utility contractor. This will require coordination for the trail construction along the north side of the bank site. Please confirm the above schedule coordination items. Cc: Brad Coats