1. The trailers were removed from the site at the end of July 2013. The current request is for up to
nine new trailers for use in 2014.
2. The permanent plant workforce is 110 employees with an additional 250 expected during the
spring outage in 2014.
3. Each trailer will be approx. 60' long x 12' wide. Assuming nine trailers, the total square footage of
the maximum temporary trailer space is 6,480 square feet.
Please let me know if there are any other questions.
Thomas Zellmer
Xcel Energy I Responsible By Nature
Project Engineer,Engineering&Construction
1103 King Plant Road,Bayport,Minnesota 55003
P:651.714.6396 C:651.276.2016
E:thomas.d.zellmer(a�xcelenergy.com
XCE LEN E RGY.CPM
Please consider the environment before printing this email